Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Establishment of Canara Industrial Area of Karnataka Industrial Areas Development Board (KIADB)
(b)Name of the Company / Organisation KARNATAKA INDUSTRIAL AREAS DEVELOPMENT BOARD CANARA
(c)Registered Address Karnataka Industrial Area Development Board, No. 49, 4th and 5th floor, Khanija Bhawan, East Wing, Race Course Road, Bengaluru,,Bangalore Urban,Karnataka-560001
(d)Legal Status of the Company State Government
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Shivkumar K C
(b)Designation (Owner/ Partner/ CEO) DO
(c)Address Baikampay Industrial Area, New Mangaluru,,Mangalore,Dakshina Kannada,Karnataka-575011
(d)Pin code 575011
(e)E-mail canarakiadb@gmail.com
(f)STD Code. 80(f)Telephone No. 2407779
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity7(c) Industrial estates/ parks/ complexes/ areas, export processing Zones
Minor Activity7(c) Industrial estates/ parks/ complexes/ areas, export processing Zones
(b)Category A
(c)Proposal Number IA/KA/NCP/29175/2015
(d)Master Proposal Number(Single Window) SW/100285/2019
(e)EAC concerned (for category A Projects only) INFRA-1
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Ira, Chelur, Balepuni and Kurnadu Village, Bantwal
(b)Pincode 574219
(c)Bounded Latitudes (North)
From
Degree 74.98277778
Minutes
Second
From
Degree 74.9827778
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 12.8169222
Minutes
Second
From
Degree 12.8169223
Minutes
Second
(e)Survey of India Topo Sheet No. D43U14, D43V1,D43U13
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 133
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 4
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Karnataka
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)KarnatakaDakshina KannadaBuntwal
6.
Details of Terms of Reference (ToR):
(a)Whether TOR is mandatory for submitting application Yes
(b)MoEF&CC / SEIAA File Number 21-135/2015-IA-III
(c)Date of Apply of TOR 13 Jul 2015
(d)Date of Issue of TOR / Standard ToR 18 Sep 2015
(e)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :06 Jul 2018
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :09 Aug 2018
Distance of Public Hearing Venue from the Proposed Project :0
Ira, Chelur, Balepuni and Kurnadu Village, Bantwal Taluk, Dakshina Kannada district, Karnataka.
State :Karnataka
District :Dakshina Kannada
Tehsil :Buntwal
Village :Ira, Chelur, Balepuni and Kurnadu Village
200Employment for local people and preferring to install green category industries.District Magistrate
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Project Area236.93Industries,Commercial, Road etc.
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Establishment of Canara Industrial Area236.96HectaresOthersNA
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 330
(b) Funds Allocated for Environment Management (Capital) (in Crores) 0.151
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 2.0
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.0365
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? Yes
d)Inter-State boundaries and international boundaries Yes
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 0
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 0
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Not Applicable0OthersNA0OthersNA0 OthersNACopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Oct 2015 To 31 Dec 2015
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 6
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM2.5Micro Gram per Meter Cube271326.7260
(2.)OthersCOMili Gram per Meter Cube0.990.910.9882
(3.)SO2Micro Gram per Meter Cube7.15.07.05880
(4.)PM10Micro Gram per Meter Cube573556.560100
(5.)NOxMicro Gram per Meter Cube13.77.613.57880
    14.2.     No. of Ground Water monitoring locations : 5
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA7.226.346.58.5
(2.)Chloridesmg/l145552501000
(3.)Fluoridemg/l0.710.231.01.5
(4.)OthersZincmg/l0.310.05515
(5.)Total Hardnessmg/l310102200600
(6.)TDSmg/l6122285002000
(7.)Heavy MetalsLeadmg/l0.0090.0080.010.01
(8.)TSSmg/l12800
    14.3.     No. of Surface Water monitoring locations : 2
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA7.947.36C
(2.)OthersTSSmg/l218C
(3.)DOmg/l7.97.1C
(4.)BODmg/l2.30.9C
(5.)CODmg/l218C
    14.4.     No. of Ambient Noise monitoring locations : 6
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))48.745.575
(2.)Leq(Night)A-weighted decibels(dB(A))41.639.270
    14.5.     No. of Soil Sample Monitored locations : 6
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)N(Nitrogen)Kilogram per hectare411245
(2.)pH7.366.52
(3.)K(Potassium)Kilogram per hectare312197
(4.)P(Phosphorus)Kilogram per hectare69.437.1
(5.)Electric ConductivityMillisiemens per Centimetre1780.051
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 1.85 To 15.17
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 1.65 To 9.40
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Surface40004Copy of Permission LetterPipelineJack Well07-08-F-2224 Oct 20074546
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Sewage Water12001500STPGreen Belt Renewal Plant1200
(2.)Effluent Water33143500ETPReuse within the Plant & Recycling3314
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 4514
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 4514
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)STP SludgeOthersSTP Sludge5.11Tons0RoadOthersUsed as Manure for plantation
(2.)Solid wasteOthersOrganic Waste2222.4Tons0RoadOthersUsed as Manure for plantation etc.
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)Others(Specify)COMicrogram per Meter Cube0000.00000012
(2.)SO2Microgram per Meter Cube0000.000000000180
(3.)NOxMicrogram per Meter Cube0000.000000000180
(4.)PM2.5Microgram per Meter Cube0000.00000000160
(5.)PM10Microgram per Meter Cube0000.000000001100
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)0000PM100
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 34200
(b)Source Mangalore Electricity Supply Company Limited (MESC
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 100
(e)Stack Height (in m) 27
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 6.33
(b)Private Land (ha.) 0
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 230.6
    Total Land (ha.) 236.93
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 0
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 0
(g)Forest (ha.) 6.33
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : land 230.6
    Total (ha.) 236.93
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)OthersIndustrial, Commercial, etc236.93Industrial, Commercial, etc
Total (ha.) 236.93
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNA0Nil within 15km radius
(2.)WLSNA0Nil within 15km radius
(3.)NPANA0Nil within 15km radius
(4.)Wildlife CorridorsNA0Nil within 15km radius
(5.)ESAsNA0Nil within 15km radius
(6.)ESZsNA0Nil within 15km radius
(7.)CorridorsNA0Nil within 15km radius
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Archaeological SitesNA0Nil within 15km radius
(2.)Defence InstallationsNA0Nil within 15km radius
(3.)OthersForestVirakhamba Reserved Forest9.4Towards E
(4.)ForestKalanjimale Reserved Forest6.3Towards SSE
23.3.
(a)Whether Noc / Permission from the competent authority is required? Yes
(i)Uploaded Noc / Permission from the competent authority Copy of Noc / Permission from the competent authority
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 236.93
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired payment issues to land owners.
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 200
(b)Permanent Employment-During Operation 24000
(c)Temporary Employment- During Construction 500
(d)Temporary Employment- During Operation 800
(e)No. of working days 300
(f)Total Manpower 25500
32.
Green Belt in Ha:
(a)Total Area of Green Belt 26.389551
(b)Percentage of Total Project Area 11.14
(c)No. of Plants to be Planted 4000
(d)Funds Allocated for Plantation 1500000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)EnvironmentalGreen belt development will be carried out.
(2.)Financial• The economic condition of the people in the respective area will be improved and facilities like education, plantation and parks, community, post offices and medical will be developed.
(3.)SocialThe proposed development of Canara Industrial Area shall lead to direct and indirect employment to the people in the surrounding area.
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For INFRA-1
S. No.Item Details
1.
Details of Building Construction:
(a)Maximum Height of the Building (Meters) 0
(b)Total No. of Flats to be Build 0
(c)No. of Buildings 0
(d)Total plot area (sqm) 236.93
(e)Total built up area (sqm) 236.93
2.
Foreshore Facilities and/or Marine Disposal:
(a)Whether Project Involves Foreshore Activities and/or marine Disposal? No
3.
Rain Water Harvesting:
(a)No. of Storage 0
(b)Capacity 0
(c)No. of Recharge Pits 3540
(d)Capacity 50971
4.
Parking:
(a)Details of 4 Wheeler/ 2 Wheeler Parking 38.23746
5.
Energy Saving Measures:
(a)Source/Mode Solar Heater
(b)Percentage 3
(c)Quantity 102.6
6.
Other details:
(a)Details of impact on Water Bodies and Drainage patters of catchment area 0
(b)Details of Traffic Density Impact Assessment and Modelling Study Copy of Details of Traffic Density Impact Assessment and Modelling Study
(c)In case Underground Tunnel Project below the Forest Land - Subsidence Impact Study report Copy of Underground Tunnel Project below the Forest Land - Subsidence Impact Study report
     7.       Type of Industries to be established with Industrial Estate as per their category A/B
S. No.Type of IndustryNo. of UnitsCategory A/B
(1.)Green Category3B
(2.)Organe Category2B
8.
Length of the alignment N/A
9.
Details Bridges/ROB/Interchanges,Flyovers,Vehicle Underpass and Pedestrian Underpass
Details Not Applicable
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? Yes
(b)Name of the Court High Courts
(c)Name of the Sub Court Karnataka
(d)Case No. W.P 47802/2014, W.P 47803/2014,W.P 51318/2014,WA :
(e)Orders/Directions of the court ,if any and its relevance with the proposed project District Court, Dakshina Kannada
(f)Case Details Under Process
(g)Uploaded Court Order Copy of Court Order
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1619/RA0048
(ii)Name of the EIA Consultant ABC Techno Labs India Pvt Ltd
(iii)Address ABC TOWER #400, 13th Street, SIDCO Industrial Estate (North Phase) Ambattur – 600 098 Land Mark: Near National Productivity Council
(iv)Mobile No. 9940304000
(v)Landline No. 0442625779
(vi)Email Id eia@abctechnolab.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation INFRA-1
(ix)Validity of Accreditation 15 Nov 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAPlease submit following documents/clarification: 1. Authorisation letter does not bear the name of person authorised. Please sunbmit revised authorisation letter. 2. ToR validity extension letter. 3. What is status of Forest Land (59 acre)? Also please provide details of land encroached by State Forest Department. Submit the detailed land use plan. 4. Status of Forest land application submitted for diversion. 5. If forest land is not involved, a certificate from local DFO (State Forest Department) stating that no forest land is involved in this project. 6. Public Hearing report and advertisement is not readable. Please submit the readable documents. 07 Jun 2019
2.NAThe correction have been made as per the instruction received 07 Jun 2019
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1.NA

Print