1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | COREL PHARMA CHEM PVT. LTD. | (b)Name of the Company / Organisation | COREL PHARMA CHEM PVT LTD | (c)Registered Address | SURVEY NO.473 AND 481, BORISANA, KADI THOL ROAD,,Mahesana,Gujarat-382715 | (d)Legal Status of the Company | Private | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | KIRIT RAMBHAI PATEL | (b)Designation (Owner/ Partner/ CEO) | DIRECTOR | (c)Address | COREL HOUSE, NR.SHAYONA MARBLE, OPP. BHAGWAT PETROL PUMP, S.G. HIGHWAY, GOTA, AHMEDABAD - 382481, GUJARAT, INDIA,,Ahmedabad City,Ahmedabad,Gujarat-382481 | (d)Pin code | 382481 | (e)E-mail | kirit@corelpharmachem.com | (f)STD Code. | 0(f)Telephone No. | 8000880011 | (g)Fax No. | | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
| Minor Activity | | (b)Category | A | (c)Proposal Number | IA/GJ/IND2/65363/2017 | (d)Master Proposal Number(Single Window) | SW/100360/2019 | (e)EAC concerned (for category A Projects only) | Industrial Projects - 3 | (f)Project Type | Fresh EC |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | Survey No. 473 & 481, Boisana Village, Kadi Thol R | (b)Pincode | 382728 | (c)Bounded Latitudes (North) | | From | | Degree | 23.231344 | Minutes | | Second | | From | | Degree | 23.232453 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 72.356417 | Minutes | | Second | | From | | Degree | 72.357019 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | F43G5 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 48.77 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 1 | (j)Seismic Zone | 3 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Gujarat | |
|
|
Details of State(s) of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
(1.) | Gujarat | Mahesana | Kadi | | |
|
6. | Details of Terms of Reference (ToR): | (a)MoEF&CC / SEIAA File Number | IA-J-11011/313/2017-IA-II(I) | (b)Date of Apply of TOR | 29 Jun 2017 | (c)Date of Issue of TOR / Standard ToR | 17 Aug 2017 | (d)Previous TOR Letter | Copy of Previous TOR letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | No | (b)Whether details of Public Hearing available? | Yes | (c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above | Yes | |
|
7.1. Details of Public Hearing |
---|
|
S. No. | Details of Advertisement | Details of Public Hearing | Venue | Location Details | No. of People Attended | Issues Raised | Designation of Presiding Officer | Other Designation of Presiding Officer |
---|
(1.) | | Copy of Public Hearing : | Copy of Public Hearing | Date : | 28 Feb 2019 | Distance of Public Hearing Venue from the Proposed Project : | 0.0 |
| Project Site | State : | Gujarat | District : | Mahesana | Tehsil : | Kadi | Village : | Borisana |
| 85 | Page No. 345 to 347 of Annexure B of EIA Report. | Others | Resident Additional Collector & Additional District Magistrate, Mehsana | |
8. | Details of Project Configuration/Product: | |
|
8.1. Project Configuration |
---|
S. No. | Plant/Equipment/Facility | Configuration | Remarks |
---|
(1.) | PAGE NO. 56 AND 57 OF EIA | PAGE NO OF 56,57 OF EIA | EIA ENCLOSED | |
8.2. Product |
---|
S. No. | Product/Activity (Capacity/Area) | Quantity | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | ACRYLATE POLYMERS (RESIN) | 24000 | Tons per Annum | | Road | | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | Details Not Applicable | |
|
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | N/A | (iv)Valid Upto | N/A | (v)File No. | NA | (vi)Application No. | NA | (vii)Copy of Consent to operate valid as on date | NA | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 20 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 0.41 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 0.40 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 0.0675 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | No | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 30600 | (b)Existing quantity of raw material/fuel | N/A | (c)Total quantity of raw material/fuel | 30600 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | Acrylic monomers | 30600 | Tons per Annum | | SOUTH KOREA, USA AND MALAYSIA | Road | | 500 | Open Market | | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 01 Nov 2017 To 31 Jan 2018 | (b)Season | Winter | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 10 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | PM10 | | Micro Gram per Meter Cube | 74 | 60 | 73.45 | 100 | (2.) | PM2.5 | | Micro Gram per Meter Cube | 36 | 32 | 35.91 | 60 | (3.) | NOx | | Micro Gram per Meter Cube | 32 | 24 | 31.77 | 80 | (4.) | Others | VOC | Micro Gram per Meter Cube | 0.0 | 0.0 | 0.0 | 0.5 | (5.) | SO2 | | Micro Gram per Meter Cube | 18 | 10 | 16.90 | 80 | |
14.2. No. of Ground Water monitoring locations : 5 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | pH | | | NA | | 7.9 | 7.6 | 7.0 | 8.5 | (2.) | Heavy Metals | | IRON | mg/l | | 0.05 | 0.04 | 3.0 | 3.0 | (3.) | Others | Alkalinity | | mg/l | | 380 | 333 | 200 | 600 | (4.) | Chlorides | | | mg/l | | 390 | 276 | 250 | 1000 | (5.) | TSS | | | mg/l | | 10 | 8 | 100 | 100 | (6.) | TDS | | | mg/l | | 1117 | 776 | 500 | 2000 | (7.) | Total Hardness | | | mg/l | | 290 | 215 | 200 | 600 | (8.) | Fluoride | | | mg/l | | 0.01 | 0.01 | 0.1 | 0.1 | |
14.3. No. of Surface Water monitoring locations : 3 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | DO | | mg/l | | 7.0 | 6.0 | A | (2.) | BOD | | mg/l | | 5.9 | 5.5 | A | (3.) | COD | | mg/l | | 18.0 | 16.5 | A | (4.) | Others | TDS | mg/l | | 820 | 166 | A | (5.) | pH | | NA | | 8.3 | 8.0 | A | |
14.4. No. of Ambient Noise monitoring locations : 10 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Day) | A-weighted decibels(dB(A)) | 69 | 48 | 75 | (2.) | Leq(Night) | A-weighted decibels(dB(A)) | 58 | 44 | 55 | |
14.5. No. of Soil Sample Monitored locations : 10 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | pH | | | 8.8 | 8.3 | (2.) | Electric Conductivity | Millisiemens per Centimetre | | 0.2458 | 0.2042 | (3.) | N(Nitrogen) | Percent | | 0.044 | 0.023 | (4.) | P(Phosphorus) | Milligram per Kilogram | | 3.0 | 2.4 | (5.) | K(Potassium) | Milligram per Kilogram | | 71.2 | 52.0 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 100 To 108 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 108 To 137 | (c)Whether Ground Water Intersection will be there ? | No | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | GroundWater | | 129 | 0.3 | Not Appliacble | Pipeline | | Tube Well | | CGWA | 29 Sep 2018 | 129 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | INDUSTRIAL | 26 | 12 | PRIMARY & TERTIARY | Reuse within the Plant & Recycling,Others | ZLD | 21.2 | 4.8 | (2.) | DOMESTIC | 8 | 8 | ASP | Green Belt Renewal Plant | | 8 | | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 34 | (b)Total Discharged Water (Kilolitre per Day) | 4.8 | (c)Total Reused Water (Kilolitre per Day) | 29.2 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | ETP SLUDGE & EVAPORATION RESIDUE | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 8.4 | Tons | 57 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (2.) | PROCESS WASTE ORGANIC | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 12 | Tons | 57 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (3.) | USED OIL/SPENT OIL | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 0.025 | Tons | 30 | Road | | Authorized Recyclers | | (4.) | DISCARDED CONTAINERS/BARRELS/LINERS | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 540 | Tons | 30 | Road | | Authorized Recyclers | | (5.) | INORGANIC SALT | Industrial Waste | | 24 | Tons | 57 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | PM10 | | Microgram per Meter Cube | 78 | 1.0 | 0.4 | 79 | 100 | (2.) | PM2.5 | | Microgram per Meter Cube | 38.0 | 1 | 0.17 | 39 | 60 | (3.) | SO2 | | Microgram per Meter Cube | 18.0 | 1 | 1.98 | 20.0 | 80 | (4.) | NOx | | Microgram per Meter Cube | 32 | 1 | 0.71 | 33 | 80 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | FLU GAS | WHITE COAL/BRIQETS | 30 | 0.5 | PM10 | | 80 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 2000 | (b)Source | UGVCL | (c)Uploaded Copy of Agreement | Not Applicable | (d)Standby Arrangement (Details of DG Sets) | 4 | (e)Stack Height (in m) | 5 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 00 | (b)Private Land (ha.) | 5.6129 | (c)Government Land (ha.) | 00 | (d)Revenue Land (ha.) | 00 | (e)Other Land (ha.) | 00 | Total Land (ha.) | 5.6129 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 00 | (b)Waste/Barren Land (ha.) | 00 | (c)Grazing/ Community Land (ha.) | 00 | (d)Surface Water Bodies (ha.) | 00 | (e)Settlements (ha.) | 00 | (f)Industrial (ha.) | 5.6129 | (g)Forest (ha.) | 00 | (h)Mangroves (ha.) | 00 | (i)Marine Area (ha.) | 00 | (j)Others (ha.) : DEFENSE | 00 | Total (ha.) | 5.6129 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Main Plant | | 0.7775 | | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Wildlife Corridors | NA | 18 | Thol bird sanctuary | (2.) | Corridors | NA | 11 | NA | (3.) | Critically Polluted Area | NA | 50 | Vatva | (4.) | NPA | NA | 11 | NA | (5.) | ESAs | NA | 11 | NA | (6.) | WLS | NA | 11 | NA | (7.) | ESZs | NA | 11 | NA | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Archaeological Sites | | NA | 30 | Ahmedabad | (2.) | Defence Installations | | NA | 20 | Vadsar air force station | (3.) | Forest | | NA | 375 | Gir national park | (4.) | Others | NPA | NA | 11 | NA | |
|
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
25. | Tree Cutting: | (a)No. of Trees Cut for the Project (if Forest Land not Involved) | 00 | (b)Details of Tree Cutting and Planting of Trees | Not Applicable | |
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 5.6129 | (b)Land yet to be acquired(Ha) | 00 | (c)Status of Land acquisition if not acquired | NA | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 00 | (b)No. of Households | 00 | (c)No. of PDFs (Project Displaced Families) | 00 | (d)No. of PAFs (Project Affected Families) | 00 | (e)Funds Allocated for R&R(in INR) (in Lacs) | 00 | (f)Status of R&R | Yet To Start | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | No | (b)Whether conservation plan for Schedule-I Species has been prepared ? | No | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | No | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | No | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 5 | (b)Permanent Employment-During Operation | 195 | (c)Temporary Employment- During Construction | 10 | (d)Temporary Employment- During Operation | 10 | (e)No. of working days | 7 | (f)Total Manpower | 220 | |
|
32. | Green Belt in Ha: | (a)Total Area of Green Belt | 1.8750 | (b)Percentage of Total Project Area | 33.41 | (c)No. of Plants to be Planted | 10000 | (d)Funds Allocated for Plantation | 2500000 | (e)Uploaded Green Belt plan | Copy of Green Belt Plan | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
NIL | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details For Industrial Projects - 3 |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | HON. HIGH COURT ORDER NO. 2702 | (ii)Name of the EIA Consultant | B. S. RANA | (iii)Address | 426, GANJ BAZAR, OPP AMBAJI MANDIR, AHMEDABAD | (iv)Mobile No. | 9909362746 | (v)Landline No. | 9586249761 | (vi)Email Id | bsranaenviro@gmail.com | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | Industrial Projects - 3 | (ix)Validity of Accreditation | 27 Jun 2019 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought: |
---|
Sno. | EDS Letter | Remarks | Date of EDS |
---|
1. | NA | No proposal/details visible on the portal. | 06 Apr 2019 | 2. | NA | The correction have been made as per the instruction received | 09 Apr 2019 | 3. | NA | Still no proposal/details visible on the portal. Please ensure the same. | 13 Apr 2019 | 4. | NA | The correction have been made as per the instruction received | 15 Apr 2019 | 5. | NA | No proposal/details visible on the portal. Please check with NIC team. | 20 Apr 2019 | 6. | NA | The correction have been made as per the instruction received | 23 Apr 2019 | 7. | NA | Please inform/clarify the following:-
- Whether the proposed industrial operations are in conformity with permitted land use of the area. That needs to be confirmed along with supporting documents.
- Whether such polluting units are allowed by SPCB in the area. Status of Consent to Establish, if any.
- Permission required for ground water withdrawal of 129 cum/day. | 30 Apr 2019 | 8. | NA | The correction have been made as per the instruction received | 06 May 2019 | |
Additional Detail Sought: |
---|
Sno. | ADS Letter | Remarks | Date of ADS |
---|
1. | NA | |
|