Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Proposed construction of Joy’s The Beach Resort Private Limited
(b)Name of the Company / Organisation JOYS THE BEACH RESORT PVT LTD
(c)Registered Address Joys The Beach Resort Pvt Ltd Thirumullavaram, Kollam district,,Kollam,Kerala-695040
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Paul TC
(b)Designation (Owner/ Partner/ CEO) MD
(c)Address No.3, lake view Road, Pudukuppam, nallavadu Post,Pondicherry,Pondicherry Taluk,Pondicherry,Puducherry-605007
(d)Pin code 605007
(e)E-mail projects@thejoys.in
(f)STD Code. 471(f)Telephone No. 2232000
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity8(a) Building and Construction projects
Minor Activity
(b)Category A
(c)Proposal Number IA/KL/MIS/99581/2019
(d)Master Proposal Number(Single Window) SW/99580/2019
(e)EAC concerned (for category A Projects only) INFRA-2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. S.No: 47, 143/2, 46, 203, 205, 205/8, 205/9, 40, 2
(b)Pincode 695040
(c)Bounded Latitudes (North)
From
Degree 8.894206
Minutes
Second
From
Degree 8.897264
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 76.55173
Minutes
Second
From
Degree 77.92894
Minutes
Second
(e)Survey of India Topo Sheet No. 58 D/9
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 10
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 0
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Kerala
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR):
(a)Whether TOR is mandatory for submitting application No
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason since it is a CRZ project, PH is not applicable
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)DG sets400 kVA2 Nos
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Project area51597.92OthersSq.mtsOthersNil
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 96
(b) Funds Allocated for Environment Management (Capital) (in Crores) 1.75
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 1.92
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.18
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 1
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 1
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Diesel100OthersLiters/dayLocalRoad4 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Mar 2016 To 31 Mar 2016
(b)Season Summer
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 4
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM2.5Micro Gram per Meter Cube21.1318.7520.7160
(2.)SO2Micro Gram per Meter Cube10.568.8610.3580
(3.)NOxMicro Gram per Meter Cube22.6418.5422.1980
(4.)PM10Micro Gram per Meter Cube47.3645.5446.41100
    14.2.     No. of Ground Water monitoring locations : 4
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TSSmg/l00100100
(2.)Chloridesmg/l83.319.52501000
(3.)Heavy MetalsZincmg/l0.020.01512
(4.)TDSmg/l378905002000
(5.)Total Hardnessmg/l20030200600
(6.)pHNA7.275.926.58.5
(7.)Fluoridemg/l0.30.211.5
    14.3.     No. of Surface Water monitoring locations : 3
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA8.427.93A
(2.)DOmg/l5.725.48B
(3.)BODmg/l7.41D
(4.)CODmg/l22.64D
    14.4.     No. of Ambient Noise monitoring locations : 4
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))61.656.565
(2.)Leq(Night)A-weighted decibels(dB(A))52.248.855
    14.5.     No. of Soil Sample Monitored locations : 4
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)K(Potassium)Percent0.090.05
(2.)Electric ConductivityOthersµS/cm240142
(3.)N(Nitrogen)Percent0.080.04
(4.)P(Phosphorus)Percent0.040.02
(5.)pH8.367.43
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 0 To 5
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 0 To 5
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Otherskerala Water authority1800.6Copy of Permission LetterPipelineOtherskerala Water authorityPHDn/KLM/DB3-701/201510 Feb 2016180
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Sewage136150STPReuse within the Plant & Recycling,Green Belt Renewal Plant136
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 136
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 136
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)OrganicMunicipal Solid Waste115.43Tons0.8RoadOthersDisposal to Municipality bin
(2.)InorganicMunicipal Solid Waste94.44Tons0.8RoadAuthorized Recyclers
(3.)InorganicMunicipal Solid Waste94.44Tons0.8RoadAuthorized Recyclers
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)NOxMicrogram per Meter Cube22.640022.64180
(2.)PM2.5Microgram per Meter Cube21.130021.13160
(3.)PM10Microgram per Meter Cube47.360047.361100
(4.)SO2Microgram per Meter Cube10.560010.56180
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)400 kVADiesel50.15PM101.18 E-01
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 500
(b)Source KSEB
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) DG set Capacity of 2 x 400 kVA
(e)Stack Height (in m) 4
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 5.15979
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 5.15979
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 6704
(b)Waste/Barren Land (ha.) 92
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 3517
(e)Settlements (ha.) 3393
(f)Industrial (ha.) 0
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 18594
(j)Others (ha.) : nil 0
    Total (ha.) 32300
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Main Plant5.15979overall area
Total (ha.) 5.15979
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNil0Nil
(2.)WLSNil0Nil
(3.)NPANil0Nil
(4.)ESZsNil0Nil
(5.)CorridorsNil0Nil
(6.)ESAsNil0Nil
(7.)Wildlife CorridorsNil0Nil
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestNil0Nil
(2.)Defence InstallationsNil0Nil
(3.)Archaeological SitesNil0Nil
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Yet To Start
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Ashtamudi Lake
(ii)Direction of Water Bodies in Buffer Area East
(iii)Distance of Water Bodies in Buffer Area 2.89
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 300
(c)Temporary Employment- During Construction 75
(d)Temporary Employment- During Operation 320
(e)No. of working days 365
(f)Total Manpower 695
32.
Green Belt in Ha:
(a)Total Area of Green Belt 1.7561
(b)Percentage of Total Project Area 34.03
(c)No. of Plants to be Planted 2635
(d)Funds Allocated for Plantation 1500000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.       Project Benefits
S. No. Type of Project BenefitsDetails of Project Benefits
NIL
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For INFRA-2
S. No.Item Details
1.
Details of Building Construction:
(a)Maximum Height of the Building (Meters) 17
(b)Total No. of Flats to be Build 241
(c)No. of Buildings 7
(d)Total plot area (sqm) 51597.9
(e)Total built up area (sqm) 19929.5
2.
Foreshore Facilities and/or Marine Disposal:
(a)Whether Project Involves Foreshore Activities and/or marine Disposal? No
3.
Rain Water Harvesting:
(a)No. of Storage 1
(b)Capacity 20000
(c)No. of Recharge Pits 2
(d)Capacity 9.024
4.
Parking:
(a)Details of 4 Wheeler/ 2 Wheeler Parking 237 car parks against requirement of 234
5.
Energy Saving Measures:
(a)Source/Mode Solar plant
(b)Percentage 0.2
(c)Quantity 1
6.
Other details:
(a)Details of impact on Water Bodies and Drainage patters of catchment area nil
(b)Details of Traffic Density Impact Assessment and Modelling Study Copy of Details of Traffic Density Impact Assessment and Modelling Study
(c)In case Underground Tunnel Project below the Forest Land - Subsidence Impact Study report Copy of Underground Tunnel Project below the Forest Land - Subsidence Impact Study report
     7.       Type of Industries to be established with Industrial Estate as per their category A/B
S. No.Type of IndustryNo. of UnitsCategory A/B
NIL
8.
Length of the alignment N/A
9.
Details Bridges/ROB/Interchanges,Flyovers,Vehicle Underpass and Pedestrian Underpass
Details Not Applicable
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1619/RA 0083
(ii)Name of the EIA Consultant Hubert Enviro Care System Pvt Ltd
(iii)Address A21, 3rd Phase, Thiru Vi Ka Industriel Estate, Behind Lions Club School, Guindy
(iv)Mobile No. 9884390811
(v)Landline No. 0444363550
(vi)Email Id moses@hecs.in
(vii)Category of Accreditation A
(viii)Sector of Accreditation INFRA-2
(ix)Validity of Accreditation 13 Oct 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantPaul TC
DesignationMD
Name of Company (Applicant Name should not be given here)JOYS THE BEACH RESORT PVT LTD
AddressJoys The Beach Resort Pvt Ltd Thirumullavaram, Kollam district
Print