Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Expansion from 0.6 MTPA Non-Recovery coke Oven Plant with 40 MW Power Plant to 1.0 MTPA Integrated Steel Plant , 1.2 MTPA Non-Recovery Coke Oven Plant with 205 MW Power Plant
(b)Name of the Company / Organisation BENGAL ENERGY LIMITED
(c)Registered Address OM Tower , 3rd Floor, 32, Chowringhee Road,Kolkata,West Medinipur,West Bengal-700071
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Arun Kumar Maharaj
(b)Designation (Owner/ Partner/ CEO) Projectcoordinator
(c)Address OM Tower, 3rd Floor,32,J L Nehru Road,Kolkata,Kolkata,Kolkata,West Bengal-700071
(d)Pin code 700071
(e)E-mail bengalenergy5@gmail.com
(f)STD Code. 33(f)Telephone No. 22883355
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity3(a) Metallurgical industries (ferrous & non ferrous)
Minor Activity
(b)Category A
(c)Proposal Number IA/WB/IND/98718/2017
(d)Master Proposal Number(Single Window) SW/98715/2019
(e)EAC concerned (for category A Projects only) Industrial Projects - 1
(f)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. 871,874,875,876,877,878,403,406,407,1,2,3,4
(b)Pincode 721437
(c)Bounded Latitudes (North)
From
Degree 221522.96
Minutes
Second
From
Degree 221527.68
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 872253.37
Minutes
Second
From
Degree 872334.69
Minutes
Second
(e)Survey of India Topo Sheet No. F45J8
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 32
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 16.5
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project West Bengal
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number J-11011/28/2008-IA-II(I)
(c)Date of Issue of TOR 21 Jun 2017
(f)Previous TOR Letter Copy of Previous TOR letter
(b)Date of Apply of EC 09 Mar 2019
(c)Date of Issue of EC 19 Jul 2019
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :13 Apr 2018
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :15 May 2018
Distance of Public Hearing Venue from the Proposed Project :0
Project Site
State :West Bengal
District :West Medinipur
Tehsil :No Data
Village :Dauka
54Concern on Source of water for Industry, Pollution due to expansion, peripheral development, Employment provision, health protection, training program and skill developmentDistrict Magistrate
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Bhubaneswar
(iii)Letter No. 102-279/EPE
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Nov 28 2018 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Lam coke6000006000001200000Tons per Annum(TPA)Conveyor Belt
(2.)Sponge Iron010880001088000Tons per Annum(TPA)Conveyor Belt
(3.)Steel Billet010950001095000Tons per Annum(TPA)Road,RailTransmission line
(4.)Power40165205Mega Watt(MW)Conveyor Belt,OthersTransmission line
(5.)Sinter010000001000000Tons per Annum(TPA)Conveyor Belt
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Non Recovery Coke Oven1x0.6 MTPA1x0.6 MTPA2x0.6 MTPA
(2.)MBF02x320 m32x320 m3
(3.)Sinter01x60 m21x60 m2
(4.)EAF with LF02x80 T2x80 T
(5.)CCM 201000 TPD1000 TPD
(6.)ASU0120 TPD120 TPD
(7.)CCM 102500 TPD2500 TPD
(8.)LF01x25 T1x25 T
(9.)WHRB-DRI /MBF090 MW90 MW
(10.)CPP-AFBC035 MW35 MW
(11.)DRI Kiln04x500 TPD + 4x350 TPD4x500 TPD+4x350 TPD
(12.)IF03x20 T3x20 T
(13.)CPP-WHRB-COB40 MW40 MW80 MW
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 06 May 2017
(iv)Valid Upto 31 Mar 2022
(v)File No. CO102048
(vi)Application No. CO102048
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 4943
(b) Funds Allocated for Environment Management (Capital) (in Crores) 155.1
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 18.10
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 18.33
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 5620190
(b)Existing quantity of raw material/fuel 898390
(c)Total quantity of raw material/fuel 6518580
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Iron Ore fines768000Tons per AnnumBarbilRail210 LinkageCopy of Linkage
(2.)Coking coal1680000Tons per AnnumSingaporeRail670 Fuel Supply AgreementCopy of Linkage
(3.)Dolomite136000Tons per AnnumBiramitrapurRail290 LinkageCopy of Linkage
(4.)Iron ore1998800Tons per AnnumBarbilRail210 LinkageCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Nov 2017 To 31 Jan 2018
(b)Season Winter
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)NOxMicro Gram per Meter Cube18.910.518.280
(2.)PM10Micro Gram per Meter Cube92.361.985.8100
(3.)OthersCOMicro Gram per Meter Cube4733424652000
(4.)PM2.5Micro Gram per Meter Cube43.527.239.580
(5.)SO2Micro Gram per Meter Cube9.66.19.680
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)Total Hardnessmg/l11688200600
(2.)Chloridesmg/l3626.42501000
(3.)Fluoridemg/l0.320.081.01.5
(4.)TSSmg/l0.40.400
(5.)pHNA7.57.16.58.5
(6.)TDSmg/l3422942002000
(7.)Heavy MetalsIronmg/l0.210.091.01.0
(8.)OthersZincmg/l0.060.01515
    14.3.     No. of Surface Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA7.647.23C
(2.)DOmg/l6.84.8C
(3.)CODmg/l3218C
(4.)OthersChloridemg/l28.44.6C
(5.)BODmg/l8.85C
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))59.252.255
(2.)Leq(Night)A-weighted decibels(dB(A))44.641.745
    14.5.     No. of Soil Sample Monitored locations : 6
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH7.967.12
(2.)P(Phosphorus)Percent0.0190.007
(3.)N(Nitrogen)Percent0.0950.019
(4.)K(Potassium)Percent0.080.04
(5.)Electric ConductivityOthersmicromhos/cm401378
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 4.29 To 8
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 1.85 To 3.9
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Surface1316517Copy of Permission LetterPipelineIntake Well17/I-4M-26(06)(Pt)23 Mar 201014400
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Industrial63876400ETPReuse within the Plant & Recycling6387
(2.)Domestic300300STPGreen Belt Renewal Plant300
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 6687
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 6687
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)EAF & IF SlagIndustrial Waste120000Tons4.3RoadOthersConstruction Work
(2.)IF & EAF Flue dustIndustrial Waste24000Tons0Conveyor BeltCo-Processing
(3.)DolcharIndustrial Waste272000Tons0Conveyor BeltCo-Processing
(4.)DRI Ash & DustIndustrial Waste575600Tons4RoadSanitary Landfills
(5.)BF SlagIndustrial Waste184760Tons17RoadAuthorized Recyclers
(6.)BF Sludge + DustIndustrial Waste293670Tons17RoadAuthorized Recyclers
(7.)CPPBottom Ash100500Tons17RoadAuthorized Recyclers
(8.)CPPFly Ash150750Tons25RoadAuthorized Recyclers
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM2.5Microgram per Meter Cube39.55.891.1640.760
(2.)NOxMicrogram per Meter Cube17.35.5439.6956.9980
(3.)PM10Microgram per Meter Cube85.85.891.6887.5100
(4.)SO2Microgram per Meter Cube175.5422.739.7480
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)500 TPD DRI IIICoal502.6SO213.9
(2.)500 TPD DRI IIICoal502.6PM102.15
(3.)500 TPD DRI IVCoal502.6PM102.15
(4.)500 TPD DRI IVCoal502.6SO213.9
(5.)3x20 IFElectricity302.5PM103.5
(6.)60 m2 SinterCoal552NOx16.8
(7.)320 m3 MBF ICoal302PM101.09
(8.)1x500 TPD DRICoal502.6PM102.15
(9.)1x500 TPDCoal502.6SO213.9
(10.)2x350 TPD DRI ICoal602.8SO219.44
(11.)500 TPD DRI IICoal502.6SO213.9
(12.)2x350 TPD DRI IICoal602.8PM103.01
(13.)2x350 TPD DRI IICoal602.8SO219.44
(14.)0.6 MTPA Non recovery coke ovenCoal603.8PM102.6
(15.)0.6 MTPA Non recovery Coke ovenCoal603.8PM102.6
(16.)0.6 MTPA Non recovery coke oven IICoal603.8SO224.78
(17.)60 m2 SinterCoal552SO224.6
(18.)60 m2 SinterCoal552PM101.02
(19.)320 m3 MBF IICoal302PM101.09
(20.)RHMP---301.5PM107
(21.)500 TPD DRI IICOal502.6PM102.15
(22.)2x350 TPD DRI ICoal602.8PM103.01
(23.)0.6 MTPA Non recovery COke ovenCoal603.8SO224.78
(24.)2x80 T EAFElectricity303.6PM108.5
(25.)35 MW AFBCCoal622.6PM102.36
(26.)35 MW AFBCCoal622.6SO238.1
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 153000
(b)Source Own CPP
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 2000
(e)Stack Height (in m) 9
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 161.87
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 161.87
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 24391
(b)Waste/Barren Land (ha.) 311
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 1327
(e)Settlements (ha.) 6773
(f)Industrial (ha.) 27
(g)Forest (ha.) 2830
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Infrastructure 1117
    Total (ha.) 36776
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Green belt53.41
(2.)Water Reservoir10.4
(3.)Main Plant55.08
(4.)Area for Solid Waste Management12.21
(5.)OthersVacant Area30.77
Total (ha.) 161.87
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNA0Not found
(2.)NPANA0Not found
(3.)ESAsNA0Not found
(4.)ESZsNA0Not found
(5.)Wildlife CorridorsNA0Not found
(6.)CorridorsNA0Not found
(7.)WLSNA0Not found
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestNA0Not Found
(2.)Archaeological SitesNA0Not Found
(3.)Defence InstallationsNA0Not Found
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 161.87
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired NA
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Kalighai
(ii)Direction of Water Bodies in Buffer Area South
(iii)Distance of Water Bodies in Buffer Area 4.7
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 240
(b)Permanent Employment-During Operation 160
(c)Temporary Employment- During Construction 350
(d)Temporary Employment- During Operation 605
(e)No. of working days 320
(f)Total Manpower 1355
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt56.0056
(2.)Percentage of Total Project Area34034
(3.)No. of Plants11216011216
(4.)Funds Allocated11513000011513000
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)EnvironmentalAfforestation, RWH
(2.)SocialEmployment generation, Social Upliftment, Peripheral Development
(3.)FinancialRevenue Generation
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 1
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. 77
(ii)Name of the EIA Consultant Global Tech Enviro Experts Pvt Ltd
(iii)Address C-23, BJB Nagar Bhubaneswar
(iv)Mobile No. 9437033487
(v)Landline No. 0674243685
(vi)Email Id global1experts@gmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 1
(ix)Validity of Accreditation 26 Oct 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File NA
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterCompliance is herewith submitted against the ADS raised for M/s Bengal Energy Limited at Dauka, West Bengal. 14 May 2019
2.NA

Committee deferred the proposal for want of additional information. 

12 Apr 2019
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantArun Kumar Maharaj
DesignationProjectcoordinator
Name of Company (Applicant Name should not be given here)BENGAL ENERGY LIMITED
AddressOM Tower , 3rd Floor, 32, Chowringhee Road