Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Gularia Chini Mills Unit-Distillery
(b)Name of the Company / Organisation M/S GULARIA CHINI MILLS
(c)Registered Address M/s Gularia Chini Mills Village Nausar Gularia, Block Bijua, Tehsil-Gola, District Lakhimpur Kheri,,Lakhimpur Kheri,Uttar Pradesh-262901
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant NKAGARWAL Agarwal
(b)Designation (Owner/ Partner/ CEO) EXECUTIVEPRESIDENT
(c)Address Village Nausar Gularia, Block Bijua, Tehsil Gola, District Lakhimpur Kheri Uttar Pradesh,,Mohammadi,Lakhimpur Kheri,Uttar Pradesh-262901
(d)Pin code 262901
(e)E-mail chinimillgularia@gmail.com
(f)STD Code. 522(f)Telephone No. 212223
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(g) Distilleries
Minor Activity
(b)Category A
(c)Proposal Number IA/UP/IND2/75830/2018
(d)Master Proposal Number(Single Window) SW/98513/2019
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. (Khasra no. 265, 264, 272, 267, 274, 266, 269, 270
(b)Pincode 262901
(c)Bounded Latitudes (North)
From
Degree 28.13.41
Minutes
Second
From
Degree 28.13.47
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 80.38.08
Minutes
Second
From
Degree 80.38.24
Minutes
Second
(e)Survey of India Topo Sheet No. 62D/11,62D/12
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 89
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 0
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Uttar Pradesh
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)TelanganaAdilabadTamsiKorata
(2.)MaharashtraYavatmalKelapurChannaka
(3.)ManipurBishnupurNambol Sub-DivisionLaikot
(4.)ManipurImphal EastSawombung Sub-DivisionLaikot
(5.)ManipurUkhrulUkhrul Central Sub-DivisionZalengbung to Hatha
(6.)ManipurUkhrulPhungyar Phaisat Sub-DivisionThawai and Leingangching
(7.)Uttar PradeshLakhimpur KheriMohammdi
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number IA-J-11011/236/2018-IA-II(I)
(b)Date of Apply of TOR 22 Jul 2018
(c)Date of Issue of TOR / Standard ToR 24 Aug 2018
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :20 Jan 2019
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :22 Feb 2019
Distance of Public Hearing Venue from the Proposed Project :0.1
Inside proposed project site
State :Uttar Pradesh
District :Lakhimpur Kheri
Tehsil :Mohammadi
Village :rudrapur gularia
186Issues regarding employment, social responsibilities, control of waste water generation, ground water abstraction, air pollution control measures, rain water harvesting, ash disposal, were raisedDistrict Magistrate
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Molasses based distillery160 KLDRS/ENA/Ethanol
(2.)Co-generation power plant8.0 MW
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Co-generation power plant8.0Mega Watt(MW)Otherselectric transmission line
(2.)Molasses based distillery160Kilo Litre per DayRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 01 Mar 2019
(iv)Valid Upto 01 Mar 2019
(v)File No. na
(vi)Application No. after grant of EC unit will apply for CTE and CTO
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 208.742
(b) Funds Allocated for Environment Management (Capital) (in Crores) 110
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 3.13
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 1.1
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 720
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 720
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Molasses259200Otherston/annumfrom adjacent own sugar unitRoad0.4 CaptiveCopy of Linkage
(2.)Bagasse as fuel for co generation power plant91800Otherston/annumfrom adjacent own sugar unitRoad0.4 Othersfrom adjacent own sugar unitCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 15 Sep 2018 To 15 Dec 2018
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)SO2Micro Gram per Meter Cube16.89.814.480
(2.)PM2.5Micro Gram per Meter Cube58.229.458.160
(3.)PM10Micro Gram per Meter Cube88.847.687.5100
(4.)NOxMicro Gram per Meter Cube26.415.222.180
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHOtherspH7.67.38.58.5
(2.)Total Hardnessmg/l344220200600
(3.)Fluoridemg/l0.420.171.01.5
(4.)Heavy MetalsIronmg/l0.240.110.160.3
(5.)TDSmg/l753.4437.45002000
(6.)TSSmg/l.....
(7.)Chloridesmg/l80.0814.112501000
    14.3.     No. of Surface Water monitoring locations : 2
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)BODmg/l26.616.2B
(2.)CODmg/l82.264B
(3.)pHOtherspH7.77.5B
(4.)DOmg/l4.94.7B
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))61.85075
(2.)Leq(Night)A-weighted decibels(dB(A))53.74470
    14.5.     No. of Soil Sample Monitored locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pHOtherspH7.87.6
(2.)N(Nitrogen)Milligram per Kilogram28.7623.24
(3.)P(Phosphorus)Milligram per Kilogram140.2109.9
(4.)K(Potassium)Milligram per Kilogram89.355.2
(5.)Electric ConductivityOthersmicro siemens/Cm308250
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 3.0 To 5.0
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 2.0 To 3.0
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater9800.1Copy of Permission LettermodeOthersGROUND WATERTube Well21-4/6727/UP/IND/201901 Mar 2019980
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)SPENT WASH8001000SPENT WASH SHALL BE CONCENTRATED IN MEEOthersCONC. SPENTWASH SHALL BE USED AS FUEL IN BOILER8000
(2.)CONDENSATES11001200CONDENSATE POLISHING UNITOthers100%RECYCLING WILL BE DONE11000
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 1900
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 1900
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)FERMENTER SLUDGEIndustrial Waste5760Tons1RoadCo-Processing
(2.)ASHBottom Ash21610.8Tons1RoadCo-Processing
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube88.80.6051.5390.4100
(2.)SO2Microgram per Meter Cube16.80.5204.6221.4580
(3.)PM2.5Microgram per Meter Cube.....
(4.)NOxMicrogram per Meter Cube.....
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)SLOP FIRED BOILER 60 TPHSLOP + BAGASSE722.5PM101.53
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 4500
(b)Source UNIT SHALL INSTALL OWN CO-GENERATION POWER PLANT
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) .
(e)Stack Height (in m) .
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 8.747
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 8.747
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 229300
(b)Waste/Barren Land (ha.) 16000
(c)Grazing/ Community Land (ha.) 2198
(d)Surface Water Bodies (ha.) 5300
(e)Settlements (ha.) 26815
(f)Industrial (ha.) 0
(g)Forest (ha.) 34410
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : 0 0
    Total (ha.) 314023
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)OthersCOMPLETE PLANT8.747
Total (ha.) 8.747
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)WLSNA0NO WLS OBSERVED IN STUDY AREA
(2.)ESAsNA0NO ESA OBSERVED IN STUDY AREA
(3.)CorridorsNA0NO Corridor OBSERVED IN STUDY AREA
(4.)ESZsNA0NO ESZ OBSERVED IN STUDY AREA
(5.)Critically Polluted AreaNA0NO CPA OBSERVED IN STUDY AREA
(6.)Wildlife CorridorsNA0NO Corridor OBSERVED IN STUDY AREA
(7.)NPANA0NO NPA OBSERVED IN STUDY AREA
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)OthersFORESTRayapur Reserved Forest1.93South Direction
(2.)Defence InstallationsNA.NO ANY DEFENSE AREA OBSERVED IN STUDY AREA
(3.)ForestChhairasi Reserved Forest13.2South West Direction
(4.)Archaeological SitesNA.NO ANY ARCHAEOLOGICAL SITES OBSERVED IN STUDY AREA
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 8.747
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired LAND ACQUIRED AND LAND CONVERSION HAS BEEN DONE
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 30
(b)Permanent Employment-During Operation 60
(c)Temporary Employment- During Construction 30
(d)Temporary Employment- During Operation 40
(e)No. of working days 360
(f)Total Manpower 160
32.
Green Belt in Ha:
(a)Total Area of Green Belt 2.888
(b)Percentage of Total Project Area 33.02
(c)No. of Plants to be Planted 2000
(d)Funds Allocated for Plantation 1500000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialThe proposed CER Cost is Rs. 4.17484 Lakhs (2% of capital investment), as per office memorandum no. F.No. 22-65/2017-IA.III dated 1st May 2018 as project is green field (New distillery project).
(2.)Environmentalunit shall work on 4 r principle: reduction, reuse, recycling and recovery
(3.)FinancialThe industry shall create direct/indirect employment due to upcoming project
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1619/SA056
(ii)Name of the EIA Consultant Ascenso Enviro Private Limited
(iii)Address Ascenso Enviro Private Limited D-79, Second Floor Sector-6, Noida Uttar Pradesh-201301
(iv)Mobile No. 9454721732
(v)Landline No. 011232323
(vi)Email Id anshumaan110@gmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 03 Oct 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NA- Whether the proposed industrial operations (molasses/grain based distillery) are in conformity with permitted land use of the area. That needs to be confirmed along with supporting documents. - As per the ToR, distillery is to be operated on dual feed stock (molasses and grain), whereas, the proposal for EC shows a different picture. As such, the proposal is not in compliance with the ToR issued for the project. - Adequate availability of raw materials (molasses and grain) to run the distillery @160 KLD. 24 Mar 2019
2.NAThe correction have been made as per the instruction received 27 Mar 2019
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterWe have re-modelled and estimated the incremental concentrations as per direction.. 07 Jun 2019
2.NA

Deferred

17 May 2019
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantNKAGARWAL Agarwal
DesignationEXECUTIVEPRESIDENT
Name of Company (Applicant Name should not be given here)M/S GULARIA CHINI MILLS
AddressM/s Gularia Chini Mills Village Nausar Gularia, Block Bijua, Tehsil-Gola, District Lakhimpur Kheri