Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Expansion from 2x100 TPD DRI Kiln to 5x100 TPD DRI Kiln, 20 MW CPP, 2x9 MVA SAF, 1x250 TPD I/O sinter plant & 1x40 TPH I/O washery
(b)Name of the Company / Organisation MAITHAN STEEL AND POWER LTD
(c)Registered Address 9, AJC Bose Road, Ideal Centre, 6th floor, Kolkata,,Barddhaman,West Bengal-700017
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Madhur Agarwalla
(b)Designation (Owner/ Partner/ CEO) Director
(c)Address 9, AJC Bose Road, Ideal Centre, 6th Floor, Kolkata,,Kanksa,Barddhaman,West Bengal-700017
(d)Pin code 700017
(e)E-mail madhur@maithangroup.com
(f)STD Code. 33(f)Telephone No. 39877200
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity3(a) Metallurgical industries (ferrous & non ferrous)
Minor Activity
(b)Category A
(c)Proposal Number IA/WB/IND/70780/2017
(d)Master Proposal Number(Single Window) SW/98424/2019
(e)EAC concerned (for category A Projects only) Industrial Projects - 1
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. 2982,2860,3015,2995,2985,2989,2854,2976
(b)Pincode 723121
(c)Bounded Latitudes (North)
From
Degree 233754.03
Minutes
Second
From
Degree 233757.05
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 865006.13
Minutes
Second
From
Degree 865008.14
Minutes
Second
(e)Survey of India Topo Sheet No. F45C14
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 117
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 3.6
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project West Bengal
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)West BengalPurulia
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number NIL
(b)Date of Apply of TOR NIL
(c)Date of Issue of TOR / Standard ToR NIL
(d)Previous TOR Letter NIL
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :03 Dec 2018
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :11 Jan 2019
Distance of Public Hearing Venue from the Proposed Project :3
Sampriti bhawan, Sarbari More
State :West Bengal
District :Purulia
Tehsil :Raghunathpur
Village :Bonra
70Concern on source of water for the project, Environment Management Plan, Enquired about local development and abatement of pollution , health consciousness program, employment opportunities , plantatiDistrict Magistrate
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)DRI Kiln5x100 TPD
(2.)CPP20 MWWHRB-10 MW, FBC-10 MW
(3.)I/O Washery1x40 TPH
(4.)SAF2x9 MVA
(5.)I/O Sinter1x250 TPD
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Fe-Mn9500Tons per AnnumRoad
(2.)Fe-Si3500Tons per AnnumRoad
(3.)Pig Iron10000Tons per AnnumRoad
(4.)Iron Ore Concentrate160000Tons per AnnumConveyor Belt
(5.)Sponge Iron160000Tons per AnnumRoad,Rail
(6.)Si-Mn7000Tons per AnnumRoad
(7.)Sinter80000Tons per AnnumConveyor Belt
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 28 Aug 2018
(iv)Valid Upto 31 Aug 2023
(v)File No. CO110150
(vi)Application No. CO110150
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 165
(b) Funds Allocated for Environment Management (Capital) (in Crores) 6.6
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 1.49
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.6
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 820504
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 820504
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Coal198157Tons per AnnumSouth AfricaRail750 LinkageCopy of Linkage
(2.)Iron ore510000Tons per AnnumBarbilRail250 LinkageCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Dec 2017 To 28 Feb 2018
(b)Season Winter
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)SO2Micro Gram per Meter Cube23.511.122.180
(2.)OthersCOMicro Gram per Meter Cube5303134982000
(3.)PM2.5Micro Gram per Meter Cube51.130.348.860
(4.)PM10Micro Gram per Meter Cube89.765.189.3100
(5.)NOxMicro Gram per Meter Cube28.414.126.780
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA7.57.16.58.5
(2.)TDSmg/l4013195002000
(3.)Total Hardnessmg/l12896200600
(4.)Chloridesmg/l50422501000
(5.)Fluoridemg/l0.360.2611.5
(6.)Heavy MetalsFemg/l0.130.060.30.3
(7.)TSSmg/l16600
(8.)OthersSulphatemg/l2115200400
    14.3.     No. of Surface Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)BODmg/l7.24.8C
(2.)OthersChloridemg/l52.342.1C
(3.)CODmg/l5030C
(4.)pHNA7.87.2C
(5.)DOmg/l6.64.6C
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))64.450.755
(2.)Leq(Night)A-weighted decibels(dB(A))44.439.145
    14.5.     No. of Soil Sample Monitored locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)N(Nitrogen)Percent0.0250.016
(2.)P(Phosphorus)Percent0.0190.013
(3.)K(Potassium)Percent0.0210.012
(4.)pH7.97.2
(5.)Electric ConductivityOthersmillimho/cm330294
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 4.5 To 4.9
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 1.8 To 2.3
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Surface18003.7Copy of Permission LetterPipelineIntake WellMSPL/U2/SMS/17-18/28903 Apr 20180
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Industrial340340ETPReuse within the Plant & Recycling340
(2.)Domestic7070STPGreen Belt Renewal Plant70
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 410
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 410
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)DolcharIndustrial Waste25650Tons0Conveyor BeltCo-Processing
(2.)Pig Iron SlagIndustrial Waste16000Tons5.33RoadAuthorized Recyclers
(3.)Washery rejectsIndustrial Waste80000Tons2.6RoadOthersSOld to brick plant
(4.)ESP DustIndustrial Waste15000Tons0RoadSanitary Landfills
(5.)CPP ashFly Ash29000Tons2.6RoadAuthorized Recyclers
(6.)CPP Bed ashBottom Ash4100Tons2.6RoadAuthorized Recyclers
(7.)Si-Mn SlagIndustrial Waste7700Tons5.33RoadAuthorized Recyclers
(8.)Fe-Mn SlagIndustrial Waste12700Tons0Conveyor BeltCo-Processing
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM2.5Microgram per Meter Cube48.86.22.0550.8560
(2.)SO2Microgram per Meter Cube22.18.924.726.8180
(3.)PM10Microgram per Meter Cube89.36.23.6292.93100
(4.)NOxMicrogram per Meter Cube26.78.924.1830.980
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)DRI Cooler 4 & 5---350.5PM1014.6 g/s
(2.)DRI Kiln 4 & 5Coal301.4PM101.23 g/s
(3.)SAF 2x9 MVAElectricity301.6PM102.8 g/s
(4.)Sinter PlantCoal321.0PM100.15 g/s
(5.)Sinter PlantCoal321SO23.6 g/s
(6.)DRi Kiln 4 & 5Coal301.4SO26.26 g/s
(7.)DRI Kiln-3Coal301.8PM100.6 g/s
(8.)DRI Kiln-3Coal301.8SO23.13 g/s
(9.)AFBC 10 MWCoal462.4PM102.26 g/s
(10.)SinterCoal321NOx2.4 g/s
(11.)DRI Cooler 3-300.4PM107.3 g/s
(12.)AFBC 10 MWCoal462.4SO213.9 g/s
(13.)AFBC 10 MWCoal462.4NOx20.56 g/s
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 20
(b)Source Own CPP generation
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 1800 KVA
(e)Stack Height (in m) 5
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 11.9
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 11.9
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 17431
(b)Waste/Barren Land (ha.) 3023
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 3319
(e)Settlements (ha.) 3986
(f)Industrial (ha.) 1107
(g)Forest (ha.) 3453
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Mining , Road, Infrastructure 598
    Total (ha.) 32917
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Main Plant7.21
(2.)Water Reservoir0.76
(3.)Green belt3.93
Total (ha.) 11.9
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)CorridorsNot found0Not Applicable
(2.)Critically Polluted AreaNot found0Not Applicable
(3.)NPANot found0Not Applicable
(4.)ESAsNot found0Not Applicable
(5.)Wildlife CorridorsNot found0Not Applicable
(6.)WLSNot found0Not Applicable
(7.)ESZsNot found0Not Applicable
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Archaeological SitesNot found0Not Applicable
(2.)Defence InstallationsNot found0Not Applicable
(3.)ForestPanchet RF5.15Reserve forest
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 11.9
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired NA
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Damodar
(ii)Direction of Water Bodies in Buffer Area North
(iii)Distance of Water Bodies in Buffer Area 4
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 85
(b)Permanent Employment-During Operation 80
(c)Temporary Employment- During Construction 120
(d)Temporary Employment- During Operation 165
(e)No. of working days 320
(f)Total Manpower 450
32.
Green Belt in Ha:
(a)Total Area of Green Belt 3.93
(b)Percentage of Total Project Area 33.03
(c)No. of Plants to be Planted 5224
(d)Funds Allocated for Plantation 766010
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialEmployment generation, Social upliftment
(2.)EnvironmentalAfforestation
(3.)FinancialRevenue Generation
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 1
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. 77
(ii)Name of the EIA Consultant Global Tech Enviro Experts Pvt Ltd
(iii)Address C - 23, B J B NAGAR Bhubaneswar
(iv)Mobile No. 9437033487
(v)Landline No. 0674243685
(vi)Email Id global1experts@gmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 1
(ix)Validity of Accreditation 23 Nov 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NADetails regarding compliance to the specific ToR conditions has not been included in the EIA report. It is requested to revise the EIA/EMP report by incorporating the compliance to the specific ToR points along with the requisite supporting documents. 08 Mar 2019
2.NAThe correction have been made as per the instruction received 08 Mar 2019
3.NACertified compliance report to the CTO conditions by the Regional Office of SPCB has not been submitted as against compliance to specific ToR no.iv. It is requested to submit the same. 08 Mar 2019
4.NAThe correction have been made as per the instruction received 09 Mar 2019
5.NACertified compliance report to the CTO conditions by the Regional Office of SPCB has not been submitted as against compliance to specific ToR no.iv. It is requested to submit the same. It may be noted that repeatedly you are submitting the same report wherein certified compliance report to the CTO conditions by WBPCB is not there. It is to inform that without the requisite report from WBPCB your proposal cannot be considered by the Ministry. 11 Mar 2019
6.NAThe correction have been made as per the instruction received 02 Jan 2020
7.NAProposal is returned due to the folLowing shortcomings: Form 2: S.No.2: Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency has not been submitted. S.No. 7.1: Complete PH proceedings inter-alia including written representations have not been furnished. S.No.9: Certified compliance report existing CTO conditions from the Regional Office of SPCB has not been furnished. S.No. 15: Permission obtained from the Competent Authority for the drawl of 1900 KLD shall be submitted. EIA report: i. Compliance to the ToR conditions are not given in the EIA report. ii. Consolidated water balance diagram for the existing and proposed expansion shall be furnished. iii. Satellite image of the land cover/land use map of the study area has not been furnished. iv. Material balance and Energy balance has not been furnished. 08 Jan 2020
8.NAThe correction have been made as per the instruction received 09 Jan 2020
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterADS raised for M/s.Maithan Steel & Power Ltd, P.o-Bonra, PS-Neturia, Purulia,WB in 16th meeting held on 24-25th February,2020 is complied pointwise herewith. 14 May 2021
2.NA

NIL

13 Mar 2020
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantMadhur Agarwalla
DesignationDirector
Name of Company (Applicant Name should not be given here)MAITHAN STEEL AND POWER LTD
Address9, AJC Bose Road, Ideal Centre, 6th floor, Kolkata