|
1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | EIA Study for Extension of Navigation Channel at Mazagaon Dock, Mumbai | (b)Name of the Company / Organisation | MAZAGON DOCK SHIPBUILDERS LIMITED | (c)Registered Address | DOCKYARD ROAD, MAZAGON,MUMBAI,Mumbai City,Maharashtra-400010 | (d)Legal Status of the Company | Central PSU | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | ALPHONSUS S MASCARENHAS | (b)Designation (Owner/ Partner/ CEO) | ADDITIONAL GENERAL MANAGER | (c)Address | 3RD FLOOR, FOB, SOUTH YARD,MAZAGON DOCK SHIPBUILDERS LIMITED
DOCKYARD ROAD MUMBAI,Mumbai,Mumbai City,Maharashtra-400010 | (d)Pin code | 400010 | (e)E-mail | mdlmdp@mazdock.com | (f)STD Code. | 22(f)Telephone No. | 23763100 | (g)Fax No. | | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 7(e) Ports, Harbours
| Minor Activity | | (b)Category | A | (c)Proposal Number | IA/MH/MIS/60102/2016 | (d)Master Proposal Number(Single Window) | SW/98304/2019 | (e)EAC concerned (for category A Projects only) | INFRA-2 | (f)Project Type | Fresh EC |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | Mazagon | (b)Pincode | 400010 | (c)Bounded Latitudes (North) | | From | | Degree | 18.94 | Minutes | | Second | | From | | Degree | 18.97 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 72.85 | Minutes | | Second | | From | | Degree | 72.86 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | 47 B-13 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 0 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 0 | (j)Seismic Zone | 3 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Maharashtra | |
|
|
Details of State(s) of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
(1.) | Maharashtra | Mumbai City | Mumbai | | (2.) | Orissa | Jagatsinghapur | Kujang | SANDHAKUDA | |
|
6. | Details of Terms of Reference (ToR): | (a)Whether TOR is mandatory for submitting application | Yes | (b)MoEF&CC / SEIAA File Number | F. No. 21-27/2016-IA-III | (c)Date of Apply of TOR | 03 Nov 2016 | (d)Date of Issue of TOR / Standard ToR | 29 Dec 2016 | (e)Previous TOR Letter | Copy of Previous TOR letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | No | (b)Whether details of Public Hearing available? | Yes | (c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above | Yes | |
|
7.1. Details of Public Hearing |
---|
|
S. No. | Details of Advertisement | Details of Public Hearing | Venue | Location Details | No. of People Attended | Issues Raised | Designation of Presiding Officer | Other Designation of Presiding Officer |
---|
(1.) | | Copy of Public Hearing : | Copy of Public Hearing | Date : | 31 Oct 2017 | Distance of Public Hearing Venue from the Proposed Project : | 5 |
| Collector office, Mumbai City | State : | Maharashtra | District : | Mumbai City | Tehsil : | Mumbai | Village : | Mumbai |
| 10 | Welcomed project | District Collector | | |
8. | Details of Project Configuration/Product: | |
|
8.1. Project Configuration |
---|
S. No. | Plant/Equipment/Facility | Configuration | Remarks |
---|
(1.) | Nil | Nil | | |
8.2. Product |
---|
S. No. | Product/Activity (Capacity/Area) | Quantity | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | Nil | 0 | Tons per Annum | | Road | | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | Details Not Applicable | |
|
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | N/A | (iv)Valid Upto | N/A | (v)File No. | NA | (vi)Application No. | NA | (vii)Copy of Consent to operate valid as on date | NA | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 210 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 0.55 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 0.30 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 0.25 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | No | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 0 | (b)Existing quantity of raw material/fuel | N/A | (c)Total quantity of raw material/fuel | 0 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | NA | 0 | Tons per Annum | | Not required | Road | | 0 | Linkage | | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 15 Mar 2017 To 08 Jun 2017 | (b)Season | Summer | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 4 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | PM10 | | Micro Gram per Meter Cube | 143 | 121 | 142.08 | 100 | (2.) | SO2 | | Micro Gram per Meter Cube | 12.4 | 8.2 | 12.308 | 80 | (3.) | NOx | | Micro Gram per Meter Cube | 32.3 | 17.9 | 30.92 | 80 | (4.) | PM2.5 | | Micro Gram per Meter Cube | 73 | 63 | 73 | 60 | |
14.2. No. of Ground Water monitoring locations : 4 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | Total Hardness | | | mg/l | | 378 | 98 | 200 | 600 | (2.) | Fluoride | | | mg/l | | 1.8 | 1.2 | 1.0 | 1.5 | (3.) | Chlorides | | | mg/l | | 242 | 55 | 200 | 1000 | (4.) | TSS | | | mg/l | | 0 | 0 | 0 | 0 | (5.) | pH | | | NA | | 7.6 | 6.8 | 6.5 | 8.5 | (6.) | TDS | | | mg/l | | 870 | 146 | 500 | 1500 | |
14.3. No. of Surface Water monitoring locations : 10 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | pH | | mg/l | | 8.63 | 8.12 | E | (2.) | BOD | | mg/l | | 0 | 0 | E | (3.) | DO | | mg/l | | 5.4 | 4.3 | E | (4.) | COD | | mg/l | | 0 | 0 | E | |
14.4. No. of Ambient Noise monitoring locations : 6 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Night) | A-weighted decibels(dB(A)) | 0 | 0 | 0 | (2.) | Leq(Day) | A-weighted decibels(dB(A)) | 56.4 | 49.1 | 65 | |
14.5. No. of Soil Sample Monitored locations : 4 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | N(Nitrogen) | | | 0 | 0 | (2.) | P(Phosphorus) | | | 0 | 0 | (3.) | pH | | | 8.5 | 8.2 | (4.) | Electric Conductivity | | | 0 | 0 | (5.) | K(Potassium) | | | 0 | 0 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 2.65 To 4.25 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 2.0 To 5.0 | (c)Whether Ground Water Intersection will be there ? | No | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | Others | Water Tanker | 5.6 | 1 | Not Appliacble | Pipeline | | Others | Water Tanker | 0 | 11 Mar 2019 | 5.6 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | Domestic Sewage | 0 | 0 | NA | Reuse within the Plant & Recycling | | 0 | | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 0 | (b)Total Discharged Water (Kilolitre per Day) | 0 | (c)Total Reused Water (Kilolitre per Day) | 0 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Municipal Solid Waste | Municipal Solid Waste | | 6 | Tons | 1 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | SO2 | | Microgram per Meter Cube | 12.41 | 1 | 13.73 | 27 | 80 | (2.) | NOx | | Microgram per Meter Cube | 26.96 | 1 | 17.76 | 45 | 80 | (3.) | PM2.5 | | Microgram per Meter Cube | 73 | 0.15 | 5 | 80 | 60 | (4.) | PM10 | | Microgram per Meter Cube | 143 | 0.1 | 7 | 151 | 100 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | NA | NA | 0 | 0 | PM10 | | 0 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 0 | (b)Source | Nil | (c)Uploaded Copy of Agreement | Copy of Agreement | (d)Standby Arrangement (Details of DG Sets) | Nil | (e)Stack Height (in m) | 0 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 0 | (b)Private Land (ha.) | 0 | (c)Government Land (ha.) | 0 | (d)Revenue Land (ha.) | 0 | (e)Other Land (ha.) | 0 | Total Land (ha.) | 0 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 0 | (b)Waste/Barren Land (ha.) | 1027 | (c)Grazing/ Community Land (ha.) | 4355 | (d)Surface Water Bodies (ha.) | 31258 | (e)Settlements (ha.) | 7415 | (f)Industrial (ha.) | 0 | (g)Forest (ha.) | 3913 | (h)Mangroves (ha.) | 0 | (i)Marine Area (ha.) | 0 | (j)Others (ha.) : Beach | 1012 | Total (ha.) | 48980 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Others | Dredging | 0 | | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | WLS | sanjay gandhi national park | 28 | outside study area | (2.) | NPA | nil | 30 | outside study area | (3.) | Critically Polluted Area | Navi Mumbai | 20 | outside study area | (4.) | ESAs | nil | 40 | outside study area | (5.) | ESZs | sanjay gandhi national park | 28 | outside study area | (6.) | Wildlife Corridors | sanjay gandhi national park | 28 | outside study area | (7.) | Corridors | sanjay gandhi national park | 28 | outside study area | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Archaeological Sites | | Gateway of India | 4 | Outside core area | (2.) | Forest | | nil | 0 | nil | (3.) | Defence Installations | | nil | 0 | nil | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 0 | (b)Land yet to be acquired(Ha) | 0 | (c)Status of Land acquisition if not acquired | Nil | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 0 | (b)No. of Households | 0 | (c)No. of PDFs (Project Displaced Families) | 0 | (d)No. of PAFs (Project Affected Families) | 0 | (e)Funds Allocated for R&R(in INR) (in Lacs) | 0 | (f)Status of R&R | Yet To Start | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | No | (b)Whether conservation plan for Schedule-I Species has been prepared ? | No | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | Yes | (i)Details of Water Bodies in Core Area | Arabian sea | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | No | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 50 | (b)Permanent Employment-During Operation | 0 | (c)Temporary Employment- During Construction | 75 | (d)Temporary Employment- During Operation | 0 | (e)No. of working days | 200 | (f)Total Manpower | 125 | |
|
32. | Green Belt in Ha: | (a)Total Area of Green Belt | 0 | (b)Percentage of Total Project Area | NaN | (c)No. of Plants to be Planted | 0 | (d)Funds Allocated for Plantation | 0 | (e)Uploaded Green Belt plan | Copy of Green Belt Plan | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Financial | -able to move the vessels without depending on the tidal conditions all through the year
-reduction in the delivery timelines of war ships and submarines to the Indian Navy | |
|
|
1. | Project Details: | (a)CRZ Classification | IV | (b)Location Type | Non-Eroding Coast | (c)Details of Mangroves Land Involved, if Any | No | (d)Area of Mangroves Land (hectare) | 0 | (e)EIA (Terrestrial) Studies | Carried Out | (i)Summary Details of EIA (Terrestrial) Studies | attached | (ii)Uploaded Recommendation made in EIAs | Copy of Recommendation made in EIAs | (iii)Period of Study from (EIA Terrestrial) | 03 Apr 2017 | (iv)Period of Study To (EIA Terrestrial) | 07 Apr 2017 | (f)EIA (Marine) Studies | Carried Out | (i)Summary Details of EIA (Marine) Studies | attached | (ii)Uploaded Recommendation made in EIAs | Copy of Recommendation made in EIAs | (iii)Period of Study from (EIA Marine) | 01 May 2017 | (iv)Period of Study to (EIA Marine) | 31 May 2017 | (g)Disaster Management Plan/National Oil Spill Disaster Contigency Plan | not applicable | |
|
2. | Description of the Project Under Consideration: | (a)Type of Project | Others | (i)Agency Name for Preparing CRZ Maps | Institute of Remote Sensing (IRS) Anna University, | (ii)Please Specify with salient features | Dredging of navigational channel | (iii)Uploaded relevent Document | Copy of relevent Document | |
|
3. | Distance of Project (in meters) from ltl/htl to be stated : | (a)Clause of CRZ Notification Under which the Project is a Permissible/Regulated Activity | IV | (b)Whether CRZ Map Indicating HTL,LTL Demarcation in 1:4000 Scale Prepared? | Yes | (i)Distance of Project (in meters) from HTL to be Stated | 0 | (ii)Uploaded Maps(Shape File) | Copy of Maps | (iii)Distance of Project(in meters) from LTL to be Stated | 0 | (iv)Uploaded Maps(Shape File) | Copy of Maps | (c)Whether Project Layout Superimposed on CRZ Map 1:4000 Scale ? | Yes | (i)Uploaded Maps (Shape File) | Copy of Maps | (d)Whether CRZ Map 1:25000 Covering 7 km Radius Around Project Site Prepared ? | Yes | (i)Uploaded Maps (Shape File) | Copy of Maps | (e)Whether CRZ Map Indicating CRZ-I,II,III and IV Including Other Notified ESAs Prepared | Yes | (i)Uploaded Maps (kml File) | Copy of Maps | (f)NOC from State Pollution Control Boards Obtained | No | (g)Details of Rain Water Harvesting System | | |
|
4. | Recommendation of State Coastal Zone Management Authority: | (a)Copy of CZMA | Copy of CZMA | (b)State the Conditions Imposed | i) The proposed activity should be undertaken stri | (c)Social and Environmental Issues and Mitigations Measures Suggested Including but not Limited to R&R, Water, Air, Hazardous Wastes, Ecological aspects, etc. (Brief Details to be Provided) | Not Applicable | |
|
35. Sector Specific Details For INFRA-2 |
|
1. | Details of Building Construction: | (a)Maximum Height of the Building (Meters) | 0 | (b)Total No. of Flats to be Build | 0 | (c)No. of Buildings | 0 | (d)Total plot area (sqm) | 0 | (e)Total built up area (sqm) | 0 | |
|
2. | Foreshore Facilities and/or Marine Disposal: | (a)Whether Project Involves Foreshore Activities and/or marine Disposal? | Yes | (b)Upload Shoreline Study | Copy of Shoreline stuudy | (c)Type of Cargo | 0 | (d)Quantity of Cargo | 0 | (e)Control Measures of Cargo | 0 | (f)Dust Control Measures | 0 | (g)Quantum | 0 | (h)Quantity of Dredging (Cubic meter per day) | 14400 | (i)Type of Dredging | Capital | (j)Disposal of Dredge Material | 3000000 | (k)Details of Outfall Diffusers | nil | (l)No. of Dilution Expected | 0 | (m)Distance at which the Outlet will Reach Ambient Parameters | 0 | (n)Details of Monitoring at Outfall | nil | (o)Copy of NoC from PCB in case of Marine Disposal | Copy of NoC | |
|
3. | Rain Water Harvesting: | (a)No. of Storage | 0 | (b)Capacity | 0 | (c)No. of Recharge Pits | 0 | (d)Capacity | 0 | |
|
4. | Parking: | (a)Details of 4 Wheeler/ 2 Wheeler Parking | Nil | |
|
5. | Energy Saving Measures: | (a)Source/Mode | Nil | (b)Percentage | 0 | (c)Quantity | 0 | |
|
|
7. Type of Industries to be established with Industrial Estate as per their category A/B |
---|
S. No. | Type of Industry | No. of Units | Category A/B |
---|
NIL | |
8. | Length of the alignment | N/A | |
|
9. | Details Bridges/ROB/Interchanges,Flyovers,Vehicle Underpass and Pedestrian Underpass | Details Not Applicable | |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | NABET/EIA/1619/RA0106 | (ii)Name of the EIA Consultant | WAPCOS limited | (iii)Address | 76 C, sector-18, Gurgaon, Haryana | (iv)Mobile No. | 9811487830 | (v)Landline No. | 0124239739 | (vi)Email Id | environment@wapcos.co.in | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | INFRA-2 | (ix)Validity of Accreditation | 01 Dec 2019 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought : NIL |
Additional Detail Sought : NIL |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | ALPHONSUS S MASCARENHAS | Designation | ADDITIONAL GENERAL MANAGER | Name of Company (Applicant Name should not be given here) | MAZAGON DOCK SHIPBUILDERS LIMITED | Address | DOCKYARD ROAD, MAZAGON |
|