Details of Project:
(a)Name of the project(s) EIA Study for Extension of Navigation Channel at Mazagaon Dock, Mumbai
(b)Name of the Company / Organisation MAZAGON DOCK SHIPBUILDERS LIMITED
(c)Registered Address DOCKYARD ROAD, MAZAGON,MUMBAI,Mumbai City,Maharashtra-400010
(d)Legal Status of the Company Central PSU
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant ALPHONSUS S MASCARENHAS
(b)Designation (Owner/ Partner/ CEO) ADDITIONAL GENERAL MANAGER
(c)Address 3RD FLOOR, FOB, SOUTH YARD,MAZAGON DOCK SHIPBUILDERS LIMITED DOCKYARD ROAD MUMBAI,Mumbai,Mumbai City,Maharashtra-400010
(d)Pin code 400010
(e)E-mail mdlmdp@mazdock.com
(f)STD Code. 22(f)Telephone No. 23763100
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity7(e) Ports, Harbours
Minor Activity
(b)Category A
(c)Proposal Number IA/MH/MIS/60102/2016
(d)Master Proposal Number(Single Window) SW/98304/2019
(e)EAC concerned (for category A Projects only) INFRA-2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Mazagon
(b)Pincode 400010
(c)Bounded Latitudes (North)
From
Degree 18.94
Minutes
Second
From
Degree 18.97
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 72.85
Minutes
Second
From
Degree 72.86
Minutes
Second
(e)Survey of India Topo Sheet No. 47 B-13
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 0
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 0
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Maharashtra
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)MaharashtraMumbai CityMumbai
(2.)OrissaJagatsinghapurKujangSANDHAKUDA
6.
Details of Terms of Reference (ToR):
(a)Whether TOR is mandatory for submitting application Yes
(b)MoEF&CC / SEIAA File Number F. No. 21-27/2016-IA-III
(c)Date of Apply of TOR 03 Nov 2016
(d)Date of Issue of TOR / Standard ToR 29 Dec 2016
(e)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :29 Sep 2017
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :31 Oct 2017
Distance of Public Hearing Venue from the Proposed Project :5
Collector office, Mumbai City
State :Maharashtra
District :Mumbai City
Tehsil :Mumbai
Village :Mumbai
10Welcomed projectDistrict Collector
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)NilNil
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Nil0Tons per AnnumRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 210
(b) Funds Allocated for Environment Management (Capital) (in Crores) 0.55
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.30
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.25
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 0
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 0
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)NA0Tons per AnnumNot requiredRoad0 LinkageCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 15 Mar 2017 To 08 Jun 2017
(b)Season Summer
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 4
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube143121142.08100
(2.)SO2Micro Gram per Meter Cube12.48.212.30880
(3.)NOxMicro Gram per Meter Cube32.317.930.9280
(4.)PM2.5Micro Gram per Meter Cube73637360
    14.2.     No. of Ground Water monitoring locations : 4
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)Total Hardnessmg/l37898200600
(2.)Fluoridemg/l1.81.21.01.5
(3.)Chloridesmg/l242552001000
(4.)TSSmg/l0000
(5.)pHNA7.66.86.58.5
(6.)TDSmg/l8701465001500
    14.3.     No. of Surface Water monitoring locations : 10
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHmg/l8.638.12E
(2.)BODmg/l00E
(3.)DOmg/l5.44.3E
(4.)CODmg/l00E
    14.4.     No. of Ambient Noise monitoring locations : 6
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))000
(2.)Leq(Day)A-weighted decibels(dB(A))56.449.165
    14.5.     No. of Soil Sample Monitored locations : 4
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)N(Nitrogen)00
(2.)P(Phosphorus)00
(3.)pH8.58.2
(4.)Electric Conductivity00
(5.)K(Potassium)00
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 2.65 To 4.25
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 2.0 To 5.0
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersWater Tanker5.61 Not Appliacble PipelineOthersWater Tanker011 Mar 20195.6
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic Sewage00NAReuse within the Plant & Recycling0
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 0
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 0
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Municipal Solid WasteMunicipal Solid Waste6Tons1RoadTreatment, Storage and Disposal Facility(TSDF)
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)SO2Microgram per Meter Cube12.41113.732780
(2.)NOxMicrogram per Meter Cube26.96117.764580
(3.)PM2.5Microgram per Meter Cube730.1558060
(4.)PM10Microgram per Meter Cube1430.17151100
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)NANA00PM100
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 0
(b)Source Nil
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) Nil
(e)Stack Height (in m) 0
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 0
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 0
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 0
(b)Waste/Barren Land (ha.) 1027
(c)Grazing/ Community Land (ha.) 4355
(d)Surface Water Bodies (ha.) 31258
(e)Settlements (ha.) 7415
(f)Industrial (ha.) 0
(g)Forest (ha.) 3913
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Beach 1012
    Total (ha.) 48980
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)OthersDredging0
Total (ha.) 0
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)WLSsanjay gandhi national park28outside study area
(2.)NPAnil30outside study area
(3.)Critically Polluted AreaNavi Mumbai20outside study area
(4.)ESAsnil40outside study area
(5.)ESZssanjay gandhi national park28outside study area
(6.)Wildlife Corridorssanjay gandhi national park28outside study area
(7.)Corridorssanjay gandhi national park28outside study area
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Archaeological SitesGateway of India4Outside core area
(2.)Forestnil0nil
(3.)Defence Installationsnil0nil
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired Nil
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Yet To Start
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area Arabian sea
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 50
(b)Permanent Employment-During Operation 0
(c)Temporary Employment- During Construction 75
(d)Temporary Employment- During Operation 0
(e)No. of working days 200
(f)Total Manpower 125
32.
Green Belt in Ha:
(a)Total Area of Green Belt 0
(b)Percentage of Total Project Area NaN
(c)No. of Plants to be Planted 0
(d)Funds Allocated for Plantation 0
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)Financial-able to move the vessels without depending on the tidal conditions all through the year -reduction in the delivery timelines of war ships and submarines to the Indian Navy
   34.   CRZ Specific Details
S. No.Item Details
1.
Project Details:
(a)CRZ Classification IV
(b)Location Type Non-Eroding Coast
(c)Details of Mangroves Land Involved, if Any No
(d)Area of Mangroves Land (hectare) 0
(e)EIA (Terrestrial) Studies Carried Out
(i)Summary Details of EIA (Terrestrial) Studies attached
(ii)Uploaded Recommendation made in EIAs Copy of Recommendation made in EIAs
(iii)Period of Study from (EIA Terrestrial) 03 Apr 2017
(iv)Period of Study To (EIA Terrestrial) 07 Apr 2017
(f)EIA (Marine) Studies Carried Out
(i)Summary Details of EIA (Marine) Studies attached
(ii)Uploaded Recommendation made in EIAs Copy of Recommendation made in EIAs
(iii)Period of Study from (EIA Marine) 01 May 2017
(iv)Period of Study to (EIA Marine) 31 May 2017
(g)Disaster Management Plan/National Oil Spill Disaster Contigency Plan not applicable
2.
Description of the Project Under Consideration:
(a)Type of Project Others
(i)Agency Name for Preparing CRZ Maps Institute of Remote Sensing (IRS) Anna University,
(ii)Please Specify with salient features Dredging of navigational channel
(iii)Uploaded relevent Document Copy of relevent Document
3.
Distance of Project (in meters) from ltl/htl to be stated :
(a)Clause of CRZ Notification Under which the Project is a Permissible/Regulated Activity IV
(b)Whether CRZ Map Indicating HTL,LTL Demarcation in 1:4000 Scale Prepared? Yes
(i)Distance of Project (in meters) from HTL to be Stated 0
(ii)Uploaded Maps(Shape File) Copy of Maps
(iii)Distance of Project(in meters) from LTL to be Stated 0
(iv)Uploaded Maps(Shape File) Copy of Maps
(c)Whether Project Layout Superimposed on CRZ Map 1:4000 Scale ? Yes
(i)Uploaded Maps (Shape File) Copy of Maps
(d)Whether CRZ Map 1:25000 Covering 7 km Radius Around Project Site Prepared ? Yes
(i)Uploaded Maps (Shape File) Copy of Maps
(e)Whether CRZ Map Indicating CRZ-I,II,III and IV Including Other Notified ESAs Prepared Yes
(i)Uploaded Maps (kml File) Copy of Maps
(f)NOC from State Pollution Control Boards Obtained No
(g)Details of Rain Water Harvesting System
4.
Recommendation of State Coastal Zone Management Authority:
(a)Copy of CZMA Copy of CZMA
(b)State the Conditions Imposed i) The proposed activity should be undertaken stri
(c)Social and Environmental Issues and Mitigations Measures Suggested Including but not Limited to R&R, Water, Air, Hazardous Wastes, Ecological aspects, etc. (Brief Details to be Provided) Not Applicable
   35.   Sector Specific Details For INFRA-2
S. No.Item Details
1.
Details of Building Construction:
(a)Maximum Height of the Building (Meters) 0
(b)Total No. of Flats to be Build 0
(c)No. of Buildings 0
(d)Total plot area (sqm) 0
(e)Total built up area (sqm) 0
2.
Foreshore Facilities and/or Marine Disposal:
(a)Whether Project Involves Foreshore Activities and/or marine Disposal? Yes
(b)Upload Shoreline Study Copy of Shoreline stuudy
(c)Type of Cargo 0
(d)Quantity of Cargo 0
(e)Control Measures of Cargo 0
(f)Dust Control Measures 0
(g)Quantum 0
(h)Quantity of Dredging (Cubic meter per day) 14400
(i)Type of Dredging Capital
(j)Disposal of Dredge Material 3000000
(k)Details of Outfall Diffusers nil
(l)No. of Dilution Expected 0
(m)Distance at which the Outlet will Reach Ambient Parameters 0
(n)Details of Monitoring at Outfall nil
(o)Copy of NoC from PCB in case of Marine Disposal Copy of NoC
3.
Rain Water Harvesting:
(a)No. of Storage 0
(b)Capacity 0
(c)No. of Recharge Pits 0
(d)Capacity 0
4.
Parking:
(a)Details of 4 Wheeler/ 2 Wheeler Parking Nil
5.
Energy Saving Measures:
(a)Source/Mode Nil
(b)Percentage 0
(c)Quantity 0
6.
Other details:
(a)Details of impact on Water Bodies and Drainage patters of catchment area not applicable
(b)Details of Traffic Density Impact Assessment and Modelling Study Copy of Details of Traffic Density Impact Assessment and Modelling Study
(c)In case Underground Tunnel Project below the Forest Land - Subsidence Impact Study report Copy of Underground Tunnel Project below the Forest Land - Subsidence Impact Study report
     7.       Type of Industries to be established with Industrial Estate as per their category A/B
S. No.Type of IndustryNo. of UnitsCategory A/B
NIL
8.
Length of the alignment N/A
9.
Details Bridges/ROB/Interchanges,Flyovers,Vehicle Underpass and Pedestrian Underpass
Details Not Applicable
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1619/RA0106
(ii)Name of the EIA Consultant WAPCOS limited
(iii)Address 76 C, sector-18, Gurgaon, Haryana
(iv)Mobile No. 9811487830
(v)Landline No. 0124239739
(vi)Email Id environment@wapcos.co.in
(vii)Category of Accreditation A
(viii)Sector of Accreditation INFRA-2
(ix)Validity of Accreditation 01 Dec 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantALPHONSUS S MASCARENHAS
DesignationADDITIONAL GENERAL MANAGER
Name of Company (Applicant Name should not be given here)MAZAGON DOCK SHIPBUILDERS LIMITED
AddressDOCKYARD ROAD, MAZAGON