1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | Meridian Polymers | (b)Name of the Company / Organisation | MERIDIAN POLYMERS | (c)Registered Address | Meridan Polymers
Sy.No. 169/Part-2, Manhalli Village, Bidar Taluk and Distarict, Karnataka,,Bidar,Karnataka-585257 | (d)Legal Status of the Company | Central Government | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | Udoye Udoye Rau Sendol Sendol | (b)Designation (Owner/ Partner/ CEO) | MD | (c)Address | Sy. No. 169/Part-2, Manhalli Village, Bidar Taluk and District, Karnataka,,Bidar,Bidar,Karnataka-585257 | (d)Pin code | 585257 | (e)E-mail | meridianpolymers1@gmail.com | (f)STD Code. | 40(f)Telephone No. | 29802967 | (g)Fax No. | 29802967 | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
| Minor Activity | | (b)Category | A | (c)Proposal Number | IA/KA/IND2/72938/2018 | (d)Master Proposal Number(Single Window) | SW/98106/2019 | (e)EAC concerned (for category A Projects only) | Industrial Projects - 2 | (f)Project Type | Fresh EC |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | Sy. No. 169/Part-2, Manhalli village, Bidar Taluk | (b)Pincode | 585403 | (c)Bounded Latitudes (North) | | From | | Degree | 17.450881 | Minutes | | Second | | From | | Degree | 17.451334 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 77.285518 | Minutes | | Second | | From | | Degree | 77.285929 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | E43R5, E43R6, E43R9 E43R10 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 653 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 432 | (j)Seismic Zone | 1 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Karnataka | |
|
|
Details of State(s) of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
(1.) | Karnataka | Bidar | Bidar | | (2.) | Uttar Pradesh | Chandauli | Chandauli | | |
|
6. | Details of Terms of Reference (ToR): | (a)MoEF&CC / SEIAA File Number | IA-J-11011/51/2018-IA-II(I) | (b)Date of Apply of TOR | 12 Feb 2018 | (c)Date of Issue of TOR / Standard ToR | 22 Mar 2018 | (d)Previous TOR Letter | Copy of Previous TOR letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | No | (b)Whether details of Public Hearing available? | Yes | (c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above | Yes | |
|
7.1. Details of Public Hearing |
---|
|
S. No. | Details of Advertisement | Details of Public Hearing | Venue | Location Details | No. of People Attended | Issues Raised | Designation of Presiding Officer | Other Designation of Presiding Officer |
---|
(1.) | | Copy of Public Hearing : | Copy of Public Hearing | Date : | 17 Jan 2019 | Distance of Public Hearing Venue from the Proposed Project : | 0 |
| At Project Site | State : | Karnataka | District : | Bidar | Tehsil : | Bidar | Village : | Manhalli |
| 50 | 1. Employment Potential
2. Wastewater discharge
3. Greenbelt development | Others | Additional Deputy Commissioner | |
8. | Details of Project Configuration/Product: | |
|
8.1. Project Configuration |
---|
S. No. | Plant/Equipment/Facility | Configuration | Remarks |
---|
(1.) | Purified Carboxy methy Cellulose | 2000 TPA | | |
8.2. Product |
---|
S. No. | Product/Activity (Capacity/Area) | Quantity | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | Purified Carboxy Methyl Cellulose | 2000 | Tons per Annum | | Road | | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | Details Not Applicable | |
|
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | N/A | (iv)Valid Upto | N/A | (v)File No. | NA | (vi)Application No. | NA | (vii)Copy of Consent to operate valid as on date | NA | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 24.3 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 2.53 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 0.486 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 2.78 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | Yes | d)Inter-State boundaries and international boundaries | Yes | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 2665 | (b)Existing quantity of raw material/fuel | N/A | (c)Total quantity of raw material/fuel | 2665 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | Cotton Cellulose | 1160000 | Tons per Annum | | Indigenous | Road | | 75 | Open Market | | Copy of Linkage | (2.) | Wood Cellulose | 110000 | Tons per Annum | | Indigenous | Road | | 130 | Open Market | | Copy of Linkage | (3.) | Caustic lye | 960000 | Tons per Annum | | Indigenous | Road | | 130 | Open Market | | Copy of Linkage | (4.) | ethyl alcohol | 1160000 | Tons per Annum | | Indigenous | Road | | 25 | Open Market | | Copy of Linkage | (5.) | MONO CHLROACETIC ACID | 1100000 | Tons per Annum | | Indigenous | Road | | 130 | Open Market | | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 01 Mar 2018 To 31 May 2018 | (b)Season | Summer | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | PM2.5 | | Micro Gram per Meter Cube | 19 | 13 | 18 | 60 | (2.) | PM10 | | Micro Gram per Meter Cube | 45 | 33 | 33 | 100 | (3.) | SO2 | | Micro Gram per Meter Cube | 12 | 9 | 12 | 80 | (4.) | NOx | | Micro Gram per Meter Cube | 12 | 9 | 12 | 80 | |
14.2. No. of Ground Water monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | TSS | | | mg/l | | 19 | 11 | 500 | 500 | (2.) | TDS | | | mg/l | | 363 | 191 | 500 | 500 | (3.) | Total Hardness | | | mg/l | | 225 | 90 | 200 | 200 | (4.) | Chlorides | | | mg/l | | 106 | 11 | 250 | 250 | (5.) | pH | | | NA | | 7.94 | 6.79 | 7 | 8.5 | (6.) | Fluoride | | | mg/l | | 0.5 | 0.24 | 1 | 1 | |
14.3. No. of Surface Water monitoring locations : 3 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | DO | | mg/l | | 5.2 | 5 | B | (2.) | BOD | | mg/l | | 2.4 | 2 | B | (3.) | pH | | NA | | 7.31 | 7.19 | B | (4.) | COD | | mg/l | | 15 | 12 | B | |
14.4. No. of Ambient Noise monitoring locations : 8 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Day) | A-weighted decibels(dB(A)) | 49 | 47 | 55 | (2.) | Leq(Night) | A-weighted decibels(dB(A)) | 35 | 33 | 45 | |
14.5. No. of Soil Sample Monitored locations : 8 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | N(Nitrogen) | Percent | | 0.155 | 0.015 | (2.) | P(Phosphorus) | Percent | | 0.01 | 0.001 | (3.) | Electric Conductivity | Others | ds/m | 0.29 | 0.1 | (4.) | K(Potassium) | Milligram per Kilogram | | 451 | 133 | (5.) | pH | | | 7 | 6.15 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 1.45 To 17.73 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 0.69 To 16.46 | (c)Whether Ground Water Intersection will be there ? | No | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | GroundWater | | 155 | 0 | Copy of Permission Letter | Pipeline | | Tube Well | | Sr.Go.Gr. wa/2018-19/112 | 11 Sep 2018 | 155 | (2.) | GroundWater | | 155 | 0.015 | Copy of Permission Letter | Pipeline | | Tube Well | | G.W.B/G.W. No Objection/2019-20/87 | 13 Jun 2019 | 155 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | High TDS and High COD Stream | 30 | 50 | Sent to Stripper. Stripper condensate shall be disposed to cement industries for co-processing/TSDF. Stripper bottom is sent to MEE followed by AFTD. Condensate from MEE shall be sent to biological treatment plant followed by RO. RO rejects are sent to MEE and permeate is reused in cooling towers make-up | Reuse within the Plant & Recycling | | 30 | | (2.) | Low TDS and COD Stream | 34.5 | 85 | Along with condensate from MEE and ATFD of High TDS and COD treatment method sent to Biological Treatment System followed by RO. RO permeate reused for cooling towers and boiler makeup. RO rejects are sent to MEE | Reuse within the Plant & Recycling | | 34.5 | | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 64.5 | (b)Total Discharged Water (Kilolitre per Day) | 0 | (c)Total Reused Water (Kilolitre per Day) | 64.5 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Ash from Boiler | Bottom Ash | | 3780 | Tons | 30 | Road | | Others | Sent to Brick Manufactures | (2.) | Stripper Distillate | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 165.6 | Kilolitre | 150 | Road | | Co-Processing | | (3.) | ETP Sludge | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 14.4 | Tons | 150 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (4.) | Solvent Residue | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 684 | Tons | 150 | Road | | Others | Sent to TSDF or Cement Plants for Co-Processing | (5.) | Waste Oil | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 1.65 | Kilolitre | 30 | Road | | Authorized Recyclers | | (6.) | Spent solvent | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 16200 | Tons | 0 | Road | | Others | Recovered within plant premises and reused | (7.) | Evaporation Salts | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 1332 | Tons | 150 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | PM10 | | Microgram per Meter Cube | 45 | 2.3 | 0.0 | 45.04 | 100 | (2.) | PM2.5 | | Microgram per Meter Cube | 18 | 2.3 | 0.0 | 18.03 | 60 | (3.) | SO2 | | Microgram per Meter Cube | 12 | 2.3 | 0.1 | 12.11 | 80 | (4.) | NOx | | Microgram per Meter Cube | 12 | 2.3 | 0.1 | 12.12 | 60 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | 6TPH Boiler | Coal | 30 | 0.9 | PM10 | | 0.6 g/s | (2.) | 6TPH Boiler | Coal | 30 | 0.9 | SO2 | | 0.7 g/s | (3.) | 6TPH Boiler | Coal | 30 | 0.9 | NOx | | 0.25 g/s | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 1400 | (b)Source | BESCOM | (c)Uploaded Copy of Agreement | Not Applicable | (d)Standby Arrangement (Details of DG Sets) | 2x500 kVA DG Sets | (e)Stack Height (in m) | 5 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 0 | (b)Private Land (ha.) | 1.214 | (c)Government Land (ha.) | 0 | (d)Revenue Land (ha.) | 0 | (e)Other Land (ha.) | 0 | Total Land (ha.) | 1.214 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 0 | (b)Waste/Barren Land (ha.) | 0 | (c)Grazing/ Community Land (ha.) | 0 | (d)Surface Water Bodies (ha.) | 0 | (e)Settlements (ha.) | 0 | (f)Industrial (ha.) | 0 | (g)Forest (ha.) | 0 | (h)Mangroves (ha.) | 0 | (i)Marine Area (ha.) | 0 | (j)Others (ha.) : Lease for 25 years: Area 1.214 ha | 1.214 | Total (ha.) | 1.214 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Green belt | | 0.404 | | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | WLS | NA | 0 | No WLS within 10 km of Study Area | (2.) | Wildlife Corridors | NA | 0 | No Wildlife Corridors within 10 km Study Area | (3.) | Critically Polluted Area | NA | 0 | No Critically Polluted Area within 10 km of Study Area | (4.) | ESAs | NA | 0 | No ESAs within 10 km Study Area | (5.) | Corridors | NA | 0 | No Corridors within 10 km Study Area | (6.) | NPA | NA | 0 | No NPA within 10 km of Study Area | (7.) | ESZs | NA | 0 | No ESZs within 10 km Study Area | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Forest | | Honnadi RF | 4.6 | In West Direction | (2.) | Others | Reserve Forest 2 | Kalbemal RF | 6.9 | In North Direction | (3.) | Archaeological Sites | | NA | 0 | No Archaeological Sites within 10 km Study Area | (4.) | Defence Installations | | NA | 0 | No Defence Installations within 10 km Study Area | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
25. | Tree Cutting: | (a)No. of Trees Cut for the Project (if Forest Land not Involved) | Not Applicable | (b)Details of Tree Cutting and Planting of Trees | Not Applicable | |
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 1.214 | (b)Land yet to be acquired(Ha) | 0 | (c)Status of Land acquisition if not acquired | Acquired | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 0 | (b)No. of Households | 0 | (c)No. of PDFs (Project Displaced Families) | 0 | (d)No. of PAFs (Project Affected Families) | 0 | (e)Funds Allocated for R&R(in INR) (in Lacs) | 0 | (f)Status of R&R | Completed | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | No | (b)Whether conservation plan for Schedule-I Species has been prepared ? | No | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | No | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | Yes | (i)Details of Water Bodies in Buffer Area | Madhura Canal Stream | (ii)Direction of Water Bodies in Buffer Area | North East | (iii)Distance of Water Bodies in Buffer Area | 4.4 | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 50 | (b)Permanent Employment-During Operation | 100 | (c)Temporary Employment- During Construction | 20 | (d)Temporary Employment- During Operation | 20 | (e)No. of working days | 360 | (f)Total Manpower | 190 | |
|
32. | Green Belt in Ha: | (a)Total Area of Green Belt | 0.404 | (b)Percentage of Total Project Area | 33.28 | (c)No. of Plants to be Planted | 750 | (d)Funds Allocated for Plantation | 300000 | (e)Uploaded Green Belt plan | Copy of Green Belt Plan | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Social | Employement Potential | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details : NOT APPLICABLE |
35. Sector Specific Details For Industrial Projects - 2 |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | NABET/EIA/1619/RA0077 | (ii)Name of the EIA Consultant | Team Labs and Consultants | (iii)Address | TEAM Labs and Consultants B-115-117 & 509, Annapurna Block, Aditya Enclave, Ameerpet, Hyderabad-500 038 | (iv)Mobile No. | 0402374855 | (v)Landline No. | 0402374855 | (vi)Email Id | teamlabs@gmail.com | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | Industrial Projects - 2 | (ix)Validity of Accreditation | 01 Dec 2019 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought: |
---|
Sno. | EDS Letter | Remarks | Date of EDS |
---|
1. | NA | Please inform/clarify the following:-
- Whether the proposed industrial operations are in conformity with permitted land use of the area. The same needs to be confirmed along with the supporting documents. Whether such polluting units would be allowed by the SPCB in the non-industrial area.
- Justification for applicability of the EIA Notification, 2006 to the proposed project/activity.
- Permission from the concerned regulatory authority for ground water withdrawal of 155 cum/day. | 23 Mar 2019 | 2. | NA | The correction have been made as per the instruction received | 18 Sep 2019 | |
Additional Detail Sought : NIL |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | Udoye Udoye Rau Sendol Sendol | Designation | MD | Name of Company (Applicant Name should not be given here) | MERIDIAN POLYMERS | Address | Meridan Polymers
Sy.No. 169/Part-2, Manhalli Village, Bidar Taluk and Distarict, Karnataka |
|