Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Integrated Project of Sugar Plant Expansion (5000 to 7500 TCD), Ethanol Plant Expansion (30 to 100 KLPD) with Incineration Boiler/TG /Auxiliaries for ZLD & Cogeneration Power Plant (44 MW)
(b)Name of the Company / Organisation PADMABUSHAN KRANTIVEER DR NAGNATH ANNA NAYAKAWADI HUTATMA KISAN AHIR SAHAKARI SAKHAR KARKHANA LTD
(c)Registered Address Tal: Walwe, Dist: Sangli,,Sangli,Maharashtra-416313
(d)Legal Status of the Company Others
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Narendra Laxmanrao Kapadnis
(b)Designation (Owner/ Partner/ CEO) Managing Director
(c)Address Padmabushan Krantiveer Dr Nagnath Anna Nayakawadi Hutatma Kisan Ahir Sahakari Sakhar Karkhana Ltd,Tal: Walwe, Dist: Sangli Pincode: 416313,Walwa,Sangli,Maharashtra-416313
(d)Pin code 416313
(e)E-mail ast_hkl@bsnl.in
(f)STD Code. 2342(f)Telephone No. 267540
(g)Fax No. 267539
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(g) Distilleries
5(j) Sugar Industry
Minor Activity1(d) Thermal Power Plants
(b)Category A
(c)Proposal Number IA/MH/IND2/98116/2013
(d)Master Proposal Number(Single Window) SW/98110/2019
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. 149/1B+1B+1C+1D, 166, 169/9, 177/6A, 870/1, 177/6B
(b)Pincode 416310
(c)Bounded Latitudes (North)
From
Degree 17.02
Minutes
Second
From
Degree 74.37
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 17.018
Minutes
Second
From
Degree 74.37
Minutes
Second
(e)Survey of India Topo Sheet No. 47K/8, 47L/5
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 564
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 1
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Maharashtra
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number J-11011/197/2013-IA-II (I)
(c)Date of Issue of TOR 14 Nov 2013
(f)Previous TOR Letter Copy of Previous TOR letter
(b)Date of Apply of EC 02 Apr 2019
(c)Date of Issue of EC 22 Feb 2017
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :11 Sep 2018
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :12 Oct 2018
Distance of Public Hearing Venue from the Proposed Project :0.250
Factory site, Nagnathnagar, Walwe
State :Maharashtra
District :Sangli
Tehsil :Walwa
Village :Nagnathannanagar
90Questioning on Water pollution and air pollution sources, Ash disposal and its managementOthersAdditional district Magistrate
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Nagpur
(iii)Letter No. EC-436/RON/2017-NGP/4870
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Nov 11 2018 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Distillery3070100Kilo Litre per Day(KLD)Road
(2.)Sugar crushing500025007500Tons Crushed per Day(TCD)Road
(3.)Power04444Mega Watt(MW)Road,OthersLocal MSEDC grid
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Sugar-Distillery-CogenRectangularRectangularRectangularNA
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 23 Aug 2018
(iv)Valid Upto 31 Aug 2019
(v)File No. F-1.0/BO/CAC-CELL/UAN NO. 0000028472/R/CAC-1808000
(vi)Application No. 0000029984
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 574.38
(b) Funds Allocated for Environment Management (Capital) (in Crores) 10.5
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 2.87
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.373
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 280
(b)Existing quantity of raw material/fuel 120
(c)Total quantity of raw material/fuel 400
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Molasses400OthersTPDNARoad50 Open MarketCopy of Linkage
(2.)Coal384OthersTPHNARoad150 OthersNACopy of Linkage
(3.)Sugar cane7500Tons Crushed per DayNARoad50 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Mar 2018 To 31 Mar 2018
(b)Season Summer
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 9
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube54.636.948.6100
(2.)PM2.5Micro Gram per Meter Cube32.618.232.560
(3.)NOxMicro Gram per Meter Cube19.49.612.780
(4.)SO2Micro Gram per Meter Cube14.16.19.380
    14.2.     No. of Ground Water monitoring locations : 9
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TSSmg/l82..
(2.)TDSmg/l59036985002000
(3.)Heavy MetalsHexavalent Chromiummg/l00..
(4.)pHNA7.657.386.58.5
(5.)Total Hardnessmg/l1341360200600
(6.)FluorideOthersppm001.01.5
(7.)Chloridesmg/l202027.52501000
    14.3.     No. of Surface Water monitoring locations : 2
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)DOmg/l6.86.4C
(2.)pHNA7.37.2C
(3.)BODmg/l104C
(4.)CODmg/l3715C
    14.4.     No. of Ambient Noise monitoring locations : 9
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))52.542.655
(2.)Leq(Night)A-weighted decibels(dB(A))4239.545
    14.5.     No. of Soil Sample Monitored locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)N(Nitrogen)Kilogram per hectare213175.3
(2.)P(Phosphorus)Kilogram per hectare7.125.8
(3.)K(Potassium)Kilogram per hectare275212
(4.)pH87.4
(5.)Electric ConductivityMillisiemens per Centimetre678459
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 0.35 To 16.45
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 2 To 5
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Surface10902Copy of Permission LetterPipelineJack Well607421 Nov 20031267
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Process condensate430430aerobic and anaerobicReuse within the Plant & Recycling430
(2.)sugar unit waste water700800AerobicReuse within the Plant & Recycling,Green Belt Renewal Plant700
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 1130
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 1130
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Coal ashBottom Ash10320Tons0RoadOthersSent to Brick manufacturing
(2.)PressmudIndustrial Waste48000Tons0.2RoadOthersPress mud will be sold to the farmer as manure.
(3.)Bagasse ashIndustrial Waste38400Tons0RoadOthersBagasse ash will be sold to farmer as manure
(4.)Spent wash ashBottom Ash9000Tons0.1RoadOthersBrick manufacturer
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube54.60.60.1954.8100
(2.)PM2.5Microgram per Meter Cube30.60.603160
(3.)NOxMicrogram per Meter Cube18.7801.7120.580
(4.)SO2Microgram per Meter Cube14.10.66.020.280
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)220 TPH and 40 TPH boilerBagasse, Cpn. SW and Coal723.5SO26
(2.)220 TPH and 40 TPH boilerBagasse, Conc. SW and Coal723.5NOx1.71
(3.)220 TPH and 40 TPH boilerBagasse, Conc. SW, Coal723.5PM100.19
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 9.3
(b)Source Own TG
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 3 X 1000
(e)Stack Height (in m) 10
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 25.9
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 25.9
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 8186
(b)Waste/Barren Land (ha.) 14251
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 294
(e)Settlements (ha.) 1148
(f)Industrial (ha.) 0
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : vegetation 7511
    Total (ha.) 31390
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Main Plant2.8Sugar+ Cogen+Distillery Existing and proposed
(2.)Green belt8.5Existing and Proposed
Total (ha.) 11.3
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)WLSNA0NA
(2.)ESZsNA0NA
(3.)CorridorsNA0NA
(4.)NPANA0NA
(5.)ESAsNA0NA
(6.)Critically Polluted AreaNA0NA
(7.)Wildlife CorridorsNA0NA
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Archaeological SitesNA0na
(2.)Defence InstallationsNA0NA
(3.)OthersNANA0NA
(4.)ForestNA0NA
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Krishna river
(ii)Direction of Water Bodies in Buffer Area North East
(iii)Distance of Water Bodies in Buffer Area 2.2
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 50
(c)Temporary Employment- During Construction 20
(d)Temporary Employment- During Operation 10
(e)No. of working days 300
(f)Total Manpower 80
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt20.711.3622.07
(2.)Percentage of Total Project Area32133
(3.)No. of Plants60006006600
(4.)Funds Allocated3.51518.5
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)EnvironmentalA large demand is anticipated for alcohol as a fuel. Alcohol is an eco-friendly product and is a substitute to the imported petroleum. • Factory proposes zero liquid discharge method for waste water treatment. Maximum waste water will be recycled back into the system.
(2.)Social• The industry is in the rural region and economically backward. Creation of job opportunity and other business activity will improve the economy and attitude of the public towards education and health. This may result in the creation of additional education and health care facilities in this rural area.
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1720/RA 0075
(ii)Name of the EIA Consultant MITCON Consultancy & Engineering Services Ltd.
(iii)Address Environment Management and Engineering Division Behind DIC Office, Agri College Campus, Shivajinagar, Pune 411 005, Maharashtra (INDIA)
(iv)Mobile No. 9665043400
(v)Landline No. 0226628940
(vi)Email Id eme@mitconindia.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 17 Mar 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NA- Details of ECs dated 17/9/2017 & 22/2/2017 to be mentioned in column 6 of Form-2. - Co-gen power plant of 24 MW (as per the EC dated 22/2/2017) was supposed to operate along with operation of the distillery. In view of the same yet to be established, present system needs to be explained. Also, the said power plant still a part of the approved scope of work (EC dated 22/2/2017), details in this regard need to be corrected accordingly in Form-2. 24 Mar 2019
2.NAThe correction have been made as per the instruction received 02 Apr 2019
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterSubmission of clarification as per 8th EAC dated 30.05.2019 for proposed integrated project of sugar plant expansion and ethanol plant expansion with incineration boiler/TG/ Auxiliaries for ZLD & Co-generation Power plant 29 Jun 2019
2.NAThe EAC, after deliberations, desired for clarification/inputs in respect of the following:- ?Details of existing products and utilities commissioned/not commissioned as per the existing ECs. ?Action Taken Report on non complied points reflected in the certified compliance report, to be forwarded by the Regional Office of the Ministry. ?Approval from PESO for the site and layout plan for storage facilities. ?Plan for achieving ZLD for the entire unit, with Incineration route Plan for Corporate Environment Responsibility. The proposal was deferred for the needful. 12 Jun 2019
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantNarendra Laxmanrao Kapadnis
DesignationManaging Director
Name of Company (Applicant Name should not be given here)PADMABUSHAN KRANTIVEER DR NAGNATH ANNA NAYAKAWADI HUTATMA KISAN AHIR SAHAKARI SAKHAR KARKHANA LTD
AddressTal: Walwe, Dist: Sangli
Print