Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Group Housing Complex “SPLENDOR GRANDE"
(b)Name of the Company / Organisation SPLENDOR LANDBASE LTD
(c)Registered Address 5TH FLOOR SPLENDOR FORUM DISTRICT CENTRE JASOLA,,South,Delhi-110025
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant SAJAN BEHRANI
(b)Designation (Owner/ Partner/ CEO) SVP
(c)Address 5TH FLOOR SPLENDOR FORUM DISTRICT CENTRE JASOLA NEW DELHI,,Defence Colony,South,Delhi-110025
(d)Pin code 110025
(e)E-mail akg25022019@gmail.com
(f)STD Code. 11(f)Telephone No. 41041091
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity8(a) Building and Construction projects
Minor Activity8(a) Building and Construction projects
(b)Category B1
   Reason for Applying at Ministry Other
   Other Reason for Applying at Ministry CPA
(c)Proposal Number IA/HR/MIS/98094/2019
(d)Master Proposal Number(Single Window) SW/98092/2019
(e)EAC concerned (for category A Projects only) INFRA-2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Sector-19
(b)Pincode 132103
(c)Bounded Latitudes (North)
From
Degree 30
Minutes
Second
From
Degree 30
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 60
Minutes
Second
From
Degree 64
Minutes
Second
(e)Survey of India Topo Sheet No. 56
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 244.5
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 10
(j)Seismic Zone 4
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Haryana
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR):
(a)Whether TOR is mandatory for submitting application No
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason 8(a)
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)BUILDING CONSTRUCTIONCONSTRUCTION
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)CONSTRUCTION126426OthersSQMRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 350
(b) Funds Allocated for Environment Management (Capital) (in Crores) 1.2
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 1
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) .42
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 126726
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 126726
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)CONSTRUCTION MATERIAL126726OthersSQMLOCAL BODYRoad5 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 24 Feb 2019 To 02 Mar 2019
(b)Season Winter
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 0
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube0000
(2.)PM2.5Micro Gram per Meter Cube0000
(3.)SO2Micro Gram per Meter Cube0000
(4.)NOxMicro Gram per Meter Cube0000
    14.2.     No. of Ground Water monitoring locations : 0
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHmg/l0000
(2.)Total Hardnessmg/l0000
(3.)Fluoridemg/l0000
(4.)Heavy MetalsLEADmg/l0000
(5.)TSSmg/l0000
(6.)Chloridesmg/l0000
(7.)TDSmg/l0000
    14.3.     No. of Surface Water monitoring locations : 0
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHmg/l00A
(2.)DOmg/l00A
(3.)BODmg/l00A
(4.)CODmg/l00A
    14.4.     No. of Ambient Noise monitoring locations : 0
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))000
(2.)Leq(Day)A-weighted decibels(dB(A))000
    14.5.     No. of Soil Sample Monitored locations : 0
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)N(Nitrogen)Milligram per Kilogram00
(2.)P(Phosphorus)Kilogram per hectare00
(3.)Electric ConductivityKilogram per hectare00
(4.)K(Potassium)Kilogram per hectare00
(5.)pHKilogram per hectare00
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 0 To 0
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 0 To 0
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersMUNICIPAL WATER642.2Copy of Permission LetterPipelineOthersPIPELINE002 Mar 2019642
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)DOMESTIC372400SAFTReuse within the Plant & Recycling372
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 372
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 372
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)2420OthersDOMESTIC883.3Tons20RoadAuthorized Recyclers
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM2.5Microgram per Meter Cube6510.156660
(2.)SO2Microgram per Meter Cube2010.02520.580
(3.)PM10Microgram per Meter Cube120100.25121100
(4.)NOxMicrogram per Meter Cube2510.02525.580
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)NONO00PM100
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 3520
(b)Source LOCAL ELECTRICITY BAORD
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 4
(e)Stack Height (in m) 12
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 0
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 6.73
    Total Land (ha.) 6.73
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 0
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 0
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : OWN LAND 6.73
    Total (ha.) 6.73
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Built Up Area6.73
Total (ha.) 6.73
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)WLSNA0NA
(2.)ESAsNA0NA
(3.)CorridorsNA0NA
(4.)Critically Polluted AreaPANIPAT7PANIPAT IS AN CPA AS PER THE NOTIFICATION OF CPCB
(5.)NPANA0NA
(6.)ESZsNA0NA
(7.)Wildlife CorridorsNA0NA
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestNA0NA
(2.)Defence InstallationsNA0NA
(3.)Archaeological SitesNA0NA
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 6.73
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 25
(b)Permanent Employment-During Operation 25
(c)Temporary Employment- During Construction 25
(d)Temporary Employment- During Operation 25
(e)No. of working days 365
(f)Total Manpower 100
32.
Green Belt in Ha:
(a)Total Area of Green Belt 0.099
(b)Percentage of Total Project Area 1.47
(c)No. of Plants to be Planted 840
(d)Funds Allocated for Plantation 0.012
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialEmployment generation
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For INFRA-2
S. No.Item Details
1.
Details of Building Construction:
(a)Maximum Height of the Building (Meters) 60
(b)Total No. of Flats to be Build 724
(c)No. of Buildings 7
(d)Total plot area (sqm) 67339.97
(e)Total built up area (sqm) 126726
2.
Foreshore Facilities and/or Marine Disposal:
(a)Whether Project Involves Foreshore Activities and/or marine Disposal? No
3.
Rain Water Harvesting:
(a)No. of Storage 1
(b)Capacity 20
(c)No. of Recharge Pits 15
(d)Capacity 35
4.
Parking:
(a)Details of 4 Wheeler/ 2 Wheeler Parking 1089
5.
Energy Saving Measures:
(a)Source/Mode SOLAR ENERGY
(b)Percentage 10
(c)Quantity 10
6.
Other details:
(a)Details of impact on Water Bodies and Drainage patters of catchment area 0
(b)Details of Traffic Density Impact Assessment and Modelling Study Copy of Details of Traffic Density Impact Assessment and Modelling Study
(c)In case Underground Tunnel Project below the Forest Land - Subsidence Impact Study report Copy of Underground Tunnel Project below the Forest Land - Subsidence Impact Study report
     7.       Type of Industries to be established with Industrial Estate as per their category A/B
S. No.Type of IndustryNo. of UnitsCategory A/B
NIL
8.
Length of the alignment N/A
9.
Details Bridges/ROB/Interchanges,Flyovers,Vehicle Underpass and Pedestrian Underpass
Details Not Applicable
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. HIGH COURT STAY
(ii)Name of the EIA Consultant SHRI ENVIRONMENT TECHNOLOGY INSTITUTE
(iii)Address WZ-679 NANGAL RAYA NEW DELHI-46
(iv)Mobile No. 9818101668
(v)Landline No. 0114104109
(vi)Email Id setinewdelhi@gmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation INFRA-2
(ix)Validity of Accreditation 10 May 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAThis is an expansion project. Kindly submit details of earlier Environmental Clearance And Certified Compliance Report issued by the MoEF&CC, Regional Office or concerned Regional Office of Central Pollution Control Board or the Member Secretary of the respective State Pollution Control Board for the conditions stipulated in the environmental clearance issued earlier along with an action taken report on issues which have been stated to be partially complied or non/not complied. 08 Mar 2019
2.NAThe correction have been made as per the instruction received 25 Sep 2019
3.NAThis is a Category “B” project. As per Ministry’s O.M. No. J11013/5/2010-IA-II(I) dated 24th May, 2011, building construction project would continue to remain as category “B” irrespective of the location with respect to identified critically polluted areas. Such project would continue to be appraised by the respective SEIAAs. SEIAA/SEAC, Haryana has been functional. Kindly apply to SEIAA/SEAC Haryana and withdraw the proposal from this portal. 01 Oct 2019
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantSAJAN BEHRANI
DesignationSVP
Name of Company (Applicant Name should not be given here)SPLENDOR LANDBASE LTD
Address5TH FLOOR SPLENDOR FORUM DISTRICT CENTRE JASOLA
Print