Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Construction of 4/6 lane Access Control National Highway No. 754K from Dhadhaniya Sasan (Jodhpur district) to Rajasthan-Gujarat Border near Sanchore (District-Jalore) in the state of Rajasthan
(b)Name of the Company / Organisation National Highways Authority of India
(c)Registered Address G-5 & 6, Sector-10, Dwarka, New DElhi-110075,G-5 & 6, Sector-10, Dwarka, New DElhi-110075,South West,Delhi-110075
(d)Legal Status of the Company Central Government
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Dr Biswajit Mukhopadhyay
(b)Designation (Owner/ Partner/ CEO) General Manager
(c)Address G-5 & 6, Sector-10, Dwarka, New DElhi-110075,G-5 & 6, Sector-10, Dwarka, New DElhi-110075,,New Delhi,Delhi-110075
(d)Pin code 110075
(e)E-mail biswajit@nhai.org
(f)STD Code. 11(f)Telephone No. 25074200
(g)Fax No. 25093543
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity7(f) Highways
Minor Activity7(f) Highways
(b)Category A
(c)Proposal Number IA/RJ/NCP/94687/2018
(d)Master Proposal Number(Single Window) SW/94686/2019
(e)EAC concerned (for category A Projects only) INFRA-1
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Project expressway takes from design Ch. -1+142 at
(b)Pincode 343041
(c)Bounded Latitudes (North)
From
Degree 24.664342
Minutes
Second
From
Degree 26.320147
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 71.746350
Minutes
Second
From
Degree 72.596897
Minutes
Second
(e)Survey of India Topo Sheet No. H44C15
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 55
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 0
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Rajasthan
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR):
(a)Whether TOR is mandatory for submitting application Yes
(b)MoEF&CC / SEIAA File Number 10-51/2018-IA.III
(c)Date of Apply of TOR 10 Jul 2018
(d)Date of Issue of TOR / Standard ToR 12 Sep 2018
(e)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :22 Dec 2018
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :28 Jan 2019
Distance of Public Hearing Venue from the Proposed Project :2
State Secondary School
State :Rajasthan
District :Jodhpur
Tehsil :Jodhpur
Village :Dhadhaniya Bhayala
70Land compensation amountOthersAdditional District Collector Jodhpur
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)N/AN/AN/A
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)N/A0OthersN/AOthersN/A
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 4043
(b) Funds Allocated for Environment Management (Capital) (in Crores) 33.8
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 20.2
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 16.9
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 7483017.32
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 7483017.32
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Bitumen122593.786OthersCumNearby project areaRoad10 LinkageCopy of Linkage
(2.)Cement571508.045OthersCumNearby project areaRoad10 LinkageCopy of Linkage
(3.)Coarse Sand4571809.322OthersCumMine quarryRoad10 MoUCopy of Linkage
(4.)Sand2217106.167OthersCumMine quarryRoad10 MoUCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Apr 2018 To 30 Jun 2018
(b)Season Pre-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 15
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM2.5Micro Gram per Meter Cube40.822.239.260
(2.)NOxMicro Gram per Meter Cube22.88.622.280
(3.)PM10Micro Gram per Meter Cube98.554.297.8100
(4.)SO2Micro Gram per Meter Cube16.56.515.980
    14.2.     No. of Ground Water monitoring locations : 5
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA7.927.286.58.5
(2.)TSSmg/l0000
(3.)Total Hardnessmg/l896.60799.90200600
(4.)Fluoridemg/l0.720.5411.5
(5.)Heavy MetalsZnmg/l0.080.040.30.3
(6.)Chloridesmg/l8617962501000
(7.)TDSmg/l2422.702265.405002000
    14.3.     No. of Surface Water monitoring locations : 3
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)BODmg/l24.26.0C
(2.)CODmg/l80.023.1C
(3.)DOmg/l5.94.0C
(4.)pHNA7.456.9C
    14.4.     No. of Ambient Noise monitoring locations : 15
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))62.450.265
(2.)Leq(Night)A-weighted decibels(dB(A))53.237.855
    14.5.     No. of Soil Sample Monitored locations : 15
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH6.886.44
(2.)N(Nitrogen)Milligram per Kilogram528505
(3.)P(Phosphorus)Milligram per Kilogram218.4170.34
(4.)K(Potassium)Milligram per Kilogram138128
(5.)Electric ConductivityOthersmicromhos per cm475440
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 5 To 50
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 0.01 To 114.9
(c)Whether Ground Water Intersection will be there ? NA
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Surface190000Copy of Permission LetterPipelineIntake WellN/A01 Feb 20190
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)N/A00N/AGreen Belt Renewal Plant0
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 0
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 0
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)N/AIndustrial Waste0Tons0RoadAuthorized Recyclers
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)SO2Microgram per Meter Cube00016.580
(2.)PM10Microgram per Meter Cube00098.5100
(3.)PM2.5Microgram per Meter Cube00040.860
(4.)NOxMicrogram per Meter Cube00022.880
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)N/AN/A00PM100
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 0
(b)Source N/A
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) N/A
(e)Stack Height (in m) 0
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 13.219
(b)Private Land (ha.) 1641.441
(c)Government Land (ha.) 75.50
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 1730.16
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 1492.731
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 220.51
(e)Settlements (ha.) 3.7
(f)Industrial (ha.) 0
(g)Forest (ha.) 13.219
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : N/A 0
    Total (ha.) 1730.16
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Green belt416.5
Total (ha.) 416.5
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)NPAN/A0N/A
(2.)Critically Polluted AreaN/A0N/A
(3.)Wildlife CorridorsN/A0N/A
(4.)ESAsN/A0N/A
(5.)WLSN/A0N/A
(6.)CorridorsN/A0N/A
(7.)ESZsN/A0N/A
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Defence InstallationsN/A0N/A
(2.)ForestProtected Forest0along crossing of rail/road/canal
(3.)Archaeological SitesN/A0N/A
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? Yes
(a)Forests Clearance Status Application for Forest Clearance yet to be submitted
(b)Legal Status of Forest Land Protected
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 5909
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 1730.16
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired N/A
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 77
(b)No. of Households 2238
(c)No. of PDFs (Project Displaced Families) 370
(d)No. of PAFs (Project Affected Families) 2238
(e)Funds Allocated for R&R(in INR) (in Lacs) 1728.32
(f)Status of R&R In-Progress
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species Peacock
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area 179 Wells, 5 Ponds
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 100
(b)Permanent Employment-During Operation 100
(c)Temporary Employment- During Construction 700
(d)Temporary Employment- During Operation 200
(e)No. of working days 340
(f)Total Manpower 1100
32.
Green Belt in Ha:
(a)Total Area of Green Belt 416.5
(b)Percentage of Total Project Area 24.07
(c)No. of Plants to be Planted 124800
(d)Funds Allocated for Plantation 187200000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialEmployment Generation
(2.)EnvironmentalFaster transportation will ultimately lead to massive savings in the form of reduced wear and tear of vehicles, reduced vehicle operating costs (VOCs) and total reduction in transportation costs etc.
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For INFRA-1
S. No.Item Details
1.
Details of Building Construction:
(a)Maximum Height of the Building (Meters) 0
(b)Total No. of Flats to be Build 0
(c)No. of Buildings 0
(d)Total plot area (sqm) 0
(e)Total built up area (sqm) 0
2.
Foreshore Facilities and/or Marine Disposal:
(a)Whether Project Involves Foreshore Activities and/or marine Disposal? No
3.
Rain Water Harvesting:
(a)No. of Storage 0
(b)Capacity 0
(c)No. of Recharge Pits 0
(d)Capacity 0
4.
Parking:
(a)Details of 4 Wheeler/ 2 Wheeler Parking N/A
5.
Energy Saving Measures:
(a)Source/Mode N/A
(b)Percentage 0
(c)Quantity 0
6.
Other details:
(a)Details of impact on Water Bodies and Drainage patters of catchment area 179 wells and 5 ponds
(b)Details of Traffic Density Impact Assessment and Modelling Study Copy of Details of Traffic Density Impact Assessment and Modelling Study
(c)In case Underground Tunnel Project below the Forest Land - Subsidence Impact Study report Copy of Underground Tunnel Project below the Forest Land - Subsidence Impact Study report
     7.       Type of Industries to be established with Industrial Estate as per their category A/B
S. No.Type of IndustryNo. of UnitsCategory A/B
NIL
8.
Length of the alignment 208.242
9.
Details Bridges/ROB/Interchanges,Flyovers,Vehicle Underpass and Pedestrian Underpass
(a)Total No. of Bridges 30
(b)Total No. of ROB 1
(c)Total No. of Interchanges 9
(d)Total No. of Flyovers 0
(e)Total No. of Vehicle Underpass 19
(f)Total No. of Pedestrian Underpass 0
(g)Details of other utilities rail and road corridors SVUP - 85 LVUP - 34, Culverts - 282
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1619/IA 0018
(ii)Name of the EIA Consultant Enviro Infra Solutions Pvt. Ltd.
(iii)Address 301,302 & 305, SRBC, Plot No. INS - 12, Sector - 9,Vasundhara, Ghaziabad. (U.P.) - 201012
(iv)Mobile No. 9818922344
(v)Landline No. 0120415118
(vi)Email Id eis@enviroinfrasolutions.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation INFRA-1
(ix)Validity of Accreditation 09 Nov 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File NA
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterPoint wise reply against shortcomings/Additional details sought by MoEF&CC on dated 12.04.2019 04 May 2019
2.NAThe EAC, after detailed deliberations during 211th meeting held on 27th March, 2019, deferred the proposal for want of following information/documents: (i) Details of all the packages of the proposed alignment shall be submitted. (ii) Predictive Modelling for PM2.5 and PM10 along with the mitigation measures. (iii) In compliance to the submission of the proponent, a certificate from Chief Wildlife Warden stating that no Protected Area or Wildlife Corridor falls within the 10 km radius of the proposed alignment shall be submitted to the Ministry. (iv) Certificate of accreditation from QCI/NABET. 12 Apr 2019
3. ADS Reply LetterThe revised EIA/EMP report after incorporating the Public Hearing details of all the 3 districts (i.e. Jodhpur, Jalore and Barmer). The Public Hearing details are in Annexure 7 of EIA/EMP report. 12 Mar 2019
4.NAThe EAC, during 208th meeting held on 19-20 February, 2019, observed Public Hearing has been conducted for only two out of three districts. Therefore, the EAC did not consider the proposal and advised the PP to submit the revised EIA/EMP after incorporating all the Public Hearing reports of the all districts involved in this project. Hence the proposal was deferred by the EAC. 12 Mar 2019
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantDr Biswajit Mukhopadhyay
DesignationGeneral Manager
Name of Company (Applicant Name should not be given here)National Highways Authority of India
AddressG-5 & 6, Sector-10, Dwarka, New DElhi-110075
Print