S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Hindys Lab Pvt. Ltd.
(b)Name of the Company / Organisation HONOUR INFRAESTATES LTD
(c)Registered Address chanakya puri,chanakya puri new delhi,New Delhi,Karnataka-281203
(d)Legal Status of the Company Central Government
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Mohan Reddy C
(b)Designation (Owner/ Partner/ CEO) Director
(c)Address Hetero Corporate Office, 7-2-A2, Industrial Estates, Sanath Nagar,,Ameerpet,Hyderabad,Telangana-500018
(d)Pin code 500018
(e)E-mail jagadeeswar.v@heterodrugs.com
(f)STD Code. 40(f)Telephone No. 12345678
(g)Fax No. 23700405
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
Minor Activity
(b)Category A
(c)Proposal Number IA/TG/IND2/94648/2017
(d)Master Proposal Number(Single Window) SW/94642/2019
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Sy. No. 289, 290, 291 and 292, Veliminedu Village,
(b)Pincode 508114
(c)Bounded Latitudes (North)
From
Degree 17.132946
Minutes
Second
From
Degree 17.133476
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 79.12738
Minutes
Second
From
Degree 79.14293
Minutes
Second
(e)Survey of India Topo Sheet No. E44M15, E44M16, E44N3, E44N4
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 334
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 290
(j)Seismic Zone 1
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Telangana
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number J-11011/114/2017-IA II (I)
(c)Date of Issue of TOR 26 May 2017
(f)Previous TOR Letter NA
(b)Date of Apply of EC 19 Sep 2019
(c)Date of Issue of EC 09 Apr 2020
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :13 Aug 2018
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :18 Sep 2018
Distance of Public Hearing Venue from the Proposed Project :0
At Project Site
State :Telangana
District :Nalgonda
Tehsil :Chityala
Village :Veliminedu
4001. Employement 2. Water Pollution 3. Odor nucianceOthersJoint Collector & Addl. District Magistrate
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By SPCB
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on
(iii)Letter No. TSPCB/RCP/NLG/CFO&HWM/HO/2016-05
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Dec 7 2017 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Bulk Drug and Intermediates5.25144.75150OthersTons Per MonthRoad
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Bulk Drug and Intermediates5.25144.75150Tons Per Month
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 13 Mar 2019
(iv)Valid Upto 31 Jul 2020
(v)File No. TSPCB/RCP/NLG/CFO&HWM/HO/2019
(vi)Application No. TSPCB/RCP/NLG/CFO&HWM/HO/2016-05
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 45
(b) Funds Allocated for Environment Management (Capital) (in Crores) 6.57
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 1.11
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 6.97
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 193
(b)Existing quantity of raw material/fuel 6.5
(c)Total quantity of raw material/fuel 199.5
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Organic Chemicals199.5OthersTonsIndigenousRoad300 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Mar 2017 To 01 Jun 2017
(b)Season Summer
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 10
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)NOxMicro Gram per Meter Cube1291180
(2.)OthersVOC in PPMNA1.20.31.1NA
(3.)PM2.5Micro Gram per Meter Cube24112360
(4.)PM10Micro Gram per Meter Cube563254100
(5.)SO2Micro Gram per Meter Cube1291280
    14.2.     No. of Ground Water monitoring locations : 10
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TSSmg/l1310100100
(2.)Fluoridemg/l0.870.411
(3.)Total Hardnessmg/l790130200200
(4.)TDSmg/l1081327500500
(5.)Chloridesmg/l36574250250
(6.)pHNA7.8777
    14.3.     No. of Surface Water monitoring locations : 2
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)CODmg/l1311B
(2.)pHNA6.676.6E
(3.)DOmg/l4.44.3B
(4.)BODmg/l43.7B
    14.4.     No. of Ambient Noise monitoring locations : 10
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))534455
(2.)Leq(Night)A-weighted decibels(dB(A))403445
    14.5.     No. of Soil Sample Monitored locations : 10
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH86.8
(2.)N(Nitrogen)Percent0.290.017
(3.)P(Phosphorus)Percent0.760.32
(4.)K(Potassium)Milligram per Kilogram388239
(5.)Electric ConductivityOthersds/m0.30.04
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 2.3 To 26
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 0.54 To 16
(c)Whether Ground Water Intersection will be there ? NA
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersMission Bhagiratha205.30.1Copy of Permission LetterPipelineOthersPipelineT1/DEE2/MB Grid/Bulk Water Connections/2017-1809 Feb 2019210
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)High TDS and High COD Stream61.1100Effluent is stripped in a steam stripper to remove organics and then concentrated in multiple effect evaporators (MEE) followed by drying in agitated thin film dryer (ATFD). Stripper condensate will be sent to cement plants for Co-Incineration. Salt from ATFD is sent to TSDF. Distillate from MEE and ATFD is sent for further treatment in biological treatment plantOthersReused in Cooling towers and Boiler Make up592.1
(2.)Low TDS and Low COD Stream39.5150Sent to Biological Treatment System followed by RO. RO permeate reused for cooling towers and boiler makeup. RO rejects are sent to MEEOthersReused in Cooling towers and Boiler Make up381.5
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 100.6
(b)Total Discharged Water (Kilolitre per Day) 3.6
(c)Total Reused Water (Kilolitre per Day) 97
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Solvent ResidueHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1015Tons60RoadOthersSent to TSDF or Cement Plants for Co-processing
(2.)Evaporation SaltsHazardous Waste (as per Hazardous and Other Waste Management rules 2016)876Tons50RoadTreatment, Storage and Disposal Facility(TSDF)
(3.)Boiler AshBottom Ash7300Tons5RoadOthersSent to Brick Manufacturers
(4.)Organic ResidueHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1398Tons60RoadOthersSent to TSDF or Cement Plants for Co-processing
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube541.61.155.16100
(2.)PM2.5Microgram per Meter Cube23600.523.5260
(3.)SO2Microgram per Meter Cube12803.315.3680
(4.)NOxMicrogram per Meter Cube12804.216.2880
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)2x10 TPH BoilerCoal301.3PM100.85 g/sec
(2.)2x10TPH BoilerCoal301.3SO21.8 g/sec
(3.)2x10TPH BoilerCoal301.3NOx2.1 g/sec
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 5250
(b)Source TSSPDCL
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 1 x 1500 2 x 1000 3 x 500 and 1 x 250
(e)Stack Height (in m) 10
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 4.45
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 4.45
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 0
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 0
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Private Land 4.45
    Total (ha.) 4.45
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Green belt1.5
Total (ha.) 1.5
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)CorridorsNA0.00No Corridors
(2.)Wildlife CorridorsNA0.00No Wildlife Corridors
(3.)ESZsNA0.00No ESZs
(4.)Critically Polluted AreaPatancheru Bollaram78.5Critically Polluted Area
(5.)ESAsNA0.00No ESAs
(6.)WLSNA0.00No WLS
(7.)NPANA0.00No NPA
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestChityal RF7in East
(2.)Defence InstallationsNA0.00No Defence Installations
(3.)Archaeological SitesNA0.00No Archaeological Sites
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0.00
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 4.45
(b)Land yet to be acquired(Ha) 0.00
(c)Status of Land acquisition if not acquired Acquired
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0.00
(b)No. of Households 0.00
(c)No. of PDFs (Project Displaced Families) 0.00
(d)No. of PAFs (Project Affected Families) 0.00
(e)Funds Allocated for R&R(in INR) (in Lacs) 0.00
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Chinna Vagu a Seasonal nala
(ii)Direction of Water Bodies in Buffer Area South West
(iii)Distance of Water Bodies in Buffer Area 5.5
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 30
(b)Permanent Employment-During Operation 60
(c)Temporary Employment- During Construction 10
(d)Temporary Employment- During Operation 10
(e)No. of working days 365
(f)Total Manpower 110
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt0.461.041.5
(2.)Percentage of Total Project Area2013.733.7
(3.)No. of Plants3000800011000
(4.)Funds Allocated358
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialEmployement Potential
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1619/RA 0077
(ii)Name of the EIA Consultant Team Labs and Consultants
(iii)Address TEAM Labs and Consultants B-115-117 & 509, Annapurna Block, Aditya Enclave, Ameerpet, Hyderabad-500 038
(iv)Mobile No. 986641599
(v)Landline No. 0402374855
(vi)Email Id teamlabs@gmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 01 Dec 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAPlease inform/clarify the following:- - EC status for the present production @5.25 TPM and the compliance status thereof. - Present status of permission required for ground water withdrawal of 210 cum/day. 27 Jul 2019
2.NAThe correction have been made as per the instruction received 09 Aug 2019
3.NA- CTE dated 28/4/2006 is to set up the unit at survey nos.291 & 292, whereas the present proposal involves more survey nos.289 & 290. In such a case, present industrial operations at survey nos.289 & 290 also needs to be clarified along with supporting documents. - In spite of the said CTE, no requirement of prior EC for the present production @5.25 TPM under the then EIA Notification, 1994 needs to be justified. 05 Sep 2019
4.NAThe correction have been made as per the instruction received 19 Sep 2019
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterDear Sir, Please find the enclosed point wasie response of queries rasied during EAC meeting held on 21.11.2019. 27 Jan 2020
2.NA

The EAC, after detailed deliberations has asked for clarification/inputs, in respect of the following:-

 