Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Bahilampur Limestone & Dolomite Mine
(b)Name of the Company / Organisation SHRI RAJA KHANDERAO DESHMUKH PALSIKAR
(c)Registered Address 5, Parth Sankul,Kailah Nagar, Nanded, Dist Nanded, Maharashtra.,,Nanded,Maharashtra-431605
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Raja Khanderao Deshmukh
(b)Designation (Owner/ Partner/ CEO) Owner
(c)Address 5, Parth Sankul, Kailash Nagar, Nanded, Dist nanded, maharashtra,,Nanded,Nanded,Maharashtra-431605
(d)Pin code 431605
(e)E-mail rajakhanderaodeshmukh@gmail.com
(f)STD Code. 2462(f)Telephone No. 250018
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity1(a) Mining of minerals
Minor Activity1(a) Mining of minerals
(b)Category A
(c)Proposal Number IA/MH/MIN/19384/2013
(d)Master Proposal Number(Single Window) SW/94377/2019
(e)EAC concerned (for category A Projects only) Non-Coal Mining
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Survey Nos. 42 and 46
(b)Pincode 445305
(c)Bounded Latitudes (North)
From
Degree 19.769030
Minutes
Second
From
Degree 19.779935
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 78.827954
Minutes
Second
From
Degree 78.834967
Minutes
Second
(e)Survey of India Topo Sheet No. 56 I/13
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 228
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 1.5
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Maharashtra
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)MaharashtraYavatmalZari-Jamani
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number J-11015/284/2013-IA-II(M)
(b)Date of Apply of TOR 07 Aug 2013
(c)Date of Issue of TOR / Standard ToR 13 Feb 2015
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :01 Apr 2017
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :16 May 2017
Distance of Public Hearing Venue from the Proposed Project :0
Project Site
State :Maharashtra
District :Yavatmal
Tehsil :Zari-Jamani
Village :Bahilampur
70Pollution control measures, Employment, Compensation for damage to agriculture crop due to project activities.District Magistrate
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Mining Project with necessary site services-As per Approved Mining Plan
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Limestone and Dolomite50000Tons per AnnumRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 0.85
(b) Funds Allocated for Environment Management (Capital) (in Crores) 0.20
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.017
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.08
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? Yes
d)Inter-State boundaries and international boundaries Yes
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 0
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 0
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Deisel300OthersKilo Liter per annumNearby petrolpumpRoad10 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 02 Mar 2016 To 30 May 2016
(b)Season Summer
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 9
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM2.5Micro Gram per Meter Cube29.710.129.460
(2.)NOxMicro Gram per Meter Cube25.91025.980
(3.)SO2Micro Gram per Meter Cube26.48.126.380
(4.)PM10Micro Gram per Meter Cube54.836.454.3100
    14.2.     No. of Ground Water monitoring locations : 5
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA8.37.16.58.5
(2.)TDSmg/l9916615002000
(3.)Chloridesmg/l13981.42501000
(4.)Heavy MetalsHeavy Metalsmg/l1.3230.006515
(5.)Total Hardnessmg/l376320200600
(6.)Fluoridemg/l10.311.5
(7.)TSSmg/l4.21.800
    14.3.     No. of Surface Water monitoring locations : 5
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA8.67.9C
(2.)DOmg/l6.86.2C
(3.)CODmg/l46.432C
(4.)BODmg/l7.36.9C
    14.4.     No. of Ambient Noise monitoring locations : 9
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))46.937.645
(2.)Leq(Day)A-weighted decibels(dB(A))54.940.655
    14.5.     No. of Soil Sample Monitored locations : 4
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)N(Nitrogen)Kilogram per hectare782326
(2.)P(Phosphorus)Kilogram per hectare12329
(3.)K(Potassium)Kilogram per hectare284122
(4.)pH8.277.92
(5.)Electric ConductivityOthersMicrosecond per centimeter19782
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 11.3 To 4.1
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 1 To 4.5
(c)Whether Ground Water Intersection will be there ? Yes
(d)Upload Copy of Central Ground Water Authority Letter Copy of Central Ground Water Authority Letter
(e)Letter No. NOC awaited, hence copy of application attached
(f)Date of Issue 14 Jan 2019
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater230.5Copy of Permission LetterPipelineOthersMine pit water and BorewellNOC awaited, hence copy of application attached14 Jan 201923
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic Sewage2.45Soak PitOthersSoak Pit02.4
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 2.4
(b)Total Discharged Water (Kilolitre per Day) 2.4
(c)Total Reused Water (Kilolitre per Day) 0
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)RejecgtsOthersMineral Rejects5016Tons0.5RoadOthersFor backfilling use
(2.)SoilOthersOverburden1072Tons0.5RoadOthersFor use of Greenbelt development
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube54.850.0454.84100
(2.)PM2.5Microgram per Meter Cube29.6050.0329.63160
(3.)SO2Microgram per Meter Cube26.4000.01526.4280
(4.)NOxMicrogram per Meter Cube25.900.00125.9280
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)NANA00OthersNANA
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 10
(b)Source MSEGCL
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) Not Rquired
(e)Stack Height (in m) 0
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 4.224
(c)Government Land (ha.) 42.896
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 47.12
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 4.224
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 0
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Government Land 42.896
    Total (ha.) 47.120000000000005
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Main Plant0-
(2.)Township0-
(3.)Ash Pond0-
(4.)Tailing Pond0-
(5.)Desalination Plant0-
(6.)Green belt6.04-
(7.)Quarry Area35.432 Ha void and 3.4 Ha backfilling (Greenbelt)
(8.)Safety Zone3.18Greenbelt shall be created
(9.)OB Dump Area2.5Shall be biologically reclaimed
Total (ha.) 47.12
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)NPANone0Not withn 15 km radius area
(2.)Wildlife CorridorsNone0Not withn 15 km radius area
(3.)WLSNone0Not withn 15 km radius area
(4.)Critically Polluted AreaNone0Not withn 15 km radius area
(5.)ESZsNone0Not withn 15 km radius area
(6.)CorridorsNone0Not withn 15 km radius area
(7.)ESAsNone0Not withn 15 km radius area
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Defence InstallationsNone0Not within 15 km radius area
(2.)OthersInterstate boundaryMaharashtra-Telangana States border1.5Maharashtra-Telangana States border
(3.)ForestNone0Besides this there are 7 RF within Buffer Zone
(4.)Archaeological SitesNone0Not within 15 km radius area
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0
(b)Land yet to be acquired(Ha) 47.12
(c)Status of Land acquisition if not acquired Yet to start
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Yet To Start
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Penganga River, Mukutban reservoir and other seasonal nalas
(ii)Direction of Water Bodies in Buffer Area South
(iii)Distance of Water Bodies in Buffer Area 1.5
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 35
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 0
(e)No. of working days 300
(f)Total Manpower 35
32.
Green Belt in Ha:
(a)Total Area of Green Belt 13.62
(b)Percentage of Total Project Area 28.90
(c)No. of Plants to be Planted 37000
(d)Funds Allocated for Plantation 500000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)FinancialCapital cost of 0.85 crores including 0.20 Cr for environmental protection, 0.05 Cr as capital cost of CSR activities and 0.05 Cr as recurring CSR cost. The project will contribute to state through various taxes.
(2.)EnvironmentalImproving green belt, backfilling of existing pit /OB and its reclaimation
(3.)SocialDirect employment to 35 eligible persons preferable local persons besides creating indirect employment opportunities. Various CSR/CER activities in adjoining villages will help in improving social status.
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Non-Coal Mining
S. No.Item Details
     1.       No. of Mineral(s) to be Mined : 2
S. No.Mineral(s) to be Mined Major or Minor Mineral
(1.)LimestoneMajor
(2.)DolomiteMinor
2.
Mine Capacity in ROM (Run of Mine) 50000 tonns per annum
3.
Uploaded 500 meters Cluster Certificate from State Mines and Geology in case of minor minerals Copy of 500 meters Cluster Certificate from State Mines and Geology
4.
Mining Plan:
(a)Approval Letter No. YTL/LST-DOL/MPLN-1023/NGP
(b)Date of Approval 15 Sep 2010
(c)Approved Letter Copy of Approved Letter
(d)Approved By State Mining and Geology Department IBM
(e)Approved Mining Lease Area 47.12
(f)Approved Capacity 50000
5.
Technical Details:
(a)Total Geological Reserves (Million Ton) 17.88
(b)Mineable Reserves (Million Ton) 16
(c)Extractable Reserves(Million Ton) 16
(d)Percent(%) of Extraction 89.49
(e)Grade of Coal /Ore /Mineral CaO : 48.63% to 53.52%, MgO 0.39 to 4.8%, SiO2 0.38 to 1.38
(f)Stripping Ratio 1 : 0.05
(g)Category of Gaseousness (Only for Coal Mining, Others may Write NA) NA
(h)Average Gradient(Degree) -
(i)Mining Method Opencast
(j)Life of Mine (Years) 30
6.
Details of Beneficiations:
(a)Whether it is proposed to install beneficiation plant/Coal washery within the mining lease area No
(b)Whether it is proposed to install crusher within the mining lease area No
7.
Details of Seams:
(a)Whether details of seam applicable No
8.
Details of Mining Lease:
(a)Mining Lease Area (in Hectare) 47.12
(b)Whether obtained Letter of Intent (LOI) from the state government ? Yes
(i)Copy of Letter of Intent Copy of Letter of Intent
(ii)Date of issue of LOI 11 Jan 2017
(iii)Validity of LOI 50
(iv)Reference No. of LOI MMN-1008/C.R 2486/Ind-9
(c)Whether Lease Deed Executed ? No
(i)Reason thereof Environmental Clearance awaited
(d)Whether Lease Deed Renewed ? No
(i)Reason thereof Lease yet to be executed
9.
OB (Over Burden) Management:
(a) Details of External Dumps:
(i)No. of OB Dumps 1
(ii)Total Area (in Hectare) 2.5
(iii)Height (in meter) 5
(iv)Quantity (in Million Cubic meter) 0.04
(v)No. of year back fill up 20
(b) Details of Internal Dumps:
(i)No. of Internal Dumps 1
(ii)Total Area (in Hectare) 3.4
(iii)Height (in meter) 15
(iv)Quantity (in Million Cubic meter) 0.51
10.
Details of Topsoil Management:
(a)Quantity of Topsoil excavated during the entire life of the mine (in Million Cubic metre) 0.0086
(b)Quantity of Topsoil proposed for utilization for reclamation during the entire life of the mine (in Million Cubic metre) 0.0086
(c)Quantity of Topsoil proposed for utilization for other activities during the entire life of the mine (in Million Cubic metre) 0
11.
Details of Final Mine Void:
(a)Area (in Hectare) 32
(b)Depth (in meter) 16
(c)Volume (in Million Cubic meter) 0.512
12.
Details of Quarry:
(a)Final Void of 32 (hectare) at a Depth of 16 meter which is Proposed to be Converted into a Water Body.
(b)Total Quarry Area (ha) 35.4
13.
Details of Transportation:
(a)In Pit/Underground to Surface By Dumper/Tipper
(b)Surface to Siding/Loading by Tipper
(c)Transportation / Conveyor Details By Road
     14.      Details of Land Usage (Pre-Mining)
S. No.LAND USE Other LAND USEWITHIN ML AREA (Hectare)OUTSIDE ML AREA (Hectare)TOTAL (Hectare)
(1.)FOREST LAND000
(2.)GRAZING LAND000
(3.)AGRICULTURE LAND4.22404.224
(4.)SURFACE WATER BODIES000
(5.)SETTLEMENTS000
(6.)WASTE LAND000
(7.)OTHERS(Specify)Government land42.896042.896
TOTAL47.12047.12
     15.      Details of Land Usage (Post-Mining)
S. No.LAND USE Other LAND USEPlantation (ha)Water Body (ha)Public Use (ha)Undisturbed (ha)Total
(1.)EXTERNAL OB DUMPS2.5002.5
(2.)ROADS000.40.4
(3.)BUILT UP AREA (COLONY/OFFICE)0000
(4.)GREEN BELT3.75003.75
(5.)EXCAVATION/QUARRY3.432035.4
(6.)Otherinfrastructure001.11.1
(7.)VIRGIN AREA0000
(8.)TOP SOIL STORAGE0.57000.57
(9.)INTERNAL OB DUMPS3.4003.4
TOTAL13.62321.5047.12
16.
Details of Reclamation:
Total Afforestation Plan shall be Implemented Covering of Mining.
This will Include:
(a)External OB Dump(in hectare) 2.5
(b)Internal Dump(in hectare) 3.4
(c)Quarry(in hectare) 35.4
(d)Safety Zone(in hectare) 3.18
(e)Final Void of 32 (hectare) at a Depth of 16 meter which is Proposed to be Converted into a Water Body.
(f)Density of Tree Plantation per ha (in no.) 2000
(g)Others in ha (such as Excavation Area along ML Boundary, along Roads and Infrastructure, Embankment Area and in Township Located Outside the Lease etc) 4.54
(h)Total afforestation plant (in hectare) 13.62
17.
Status of progressive Mining Closure Plan:
Details Not Applicable
     18.      Details of Actual Coal/ ORE Production vis-a-vis Sanctioned Capacity since the Inception:
S. No.Financial Year Sanctioned Capacity as per EC (MTPA)Sanctioned Capacity as per CTOSanctioned Capacity as per approved mining planActual Production Excess Production Beyond the EC / CTO/ Mining Plan Sanctioned Capacity (MTPA)
(1.)201900000
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1720/RA 0105
(ii)Name of the EIA Consultant Srushti Seva Private Limited
(iii)Address “Harihar Niwas, Agresan Road,, Near Adivasi Bhavan, Giripeth,, Nagpur-440010. (Maharashtra)
(iv)Mobile No. 9422108095
(v)Landline No. 2542426
(vi)Email Id srspl15@gmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Non-Coal Mining
(ix)Validity of Accreditation 15 May 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Copy of District Survey Report Copy of District Survey Report
(h)Uploaded Copy of Replenishment Study Report & Baseline Survey Data Copy of Replenishment Study Report & Baseline Survey Data
(i)Uploaded Additional File Copy of Additional File
(j)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1.NAyour request is accepted. Your request to submit all the documents for further consideration. 06 Sep 2019
2. ADS Reply LetterRequest for extension to submission of compliance of ADS generated 12.04.2019. 28 Aug 2019
3.NA

deferred

12 Apr 2019
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantRaja Khanderao Deshmukh
DesignationOwner
Name of Company (Applicant Name should not be given here)SHRI RAJA KHANDERAO DESHMUKH PALSIKAR
Address5, Parth Sankul,Kailah Nagar, Nanded, Dist Nanded, Maharashtra.
Print