1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | M/s. Dharashiv Sakhar Karkhana Ltd. | (b)Name of the Company / Organisation | DHARSHIV SAKHAR KARKHANA LTD. | (c)Registered Address | M/s. Dharashiv Sakhar Karkhana Ltd., Village Chorkhali, Tehsil Kalamb, Dist. Osmanabad, Maharashtra,M/s. Dharashiv Sakhar Karkhana Ltd., Village Chorkhali, Tehsil Kalamb, Dist. Osmanabad, Maharashtra,Osmanabad,Maharashtra-413405 | (d)Legal Status of the Company | Private | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | Amar Dhananjay Patil | (b)Designation (Owner/ Partner/ CEO) | MD | (c)Address | M/s. Dharashiv Sakhar Karkhana Ltd., Village Chorkhali, Tehsil Kalamb, Dist. Osmanabad, Maharashtra,M/s. Dharashiv Sakhar Karkhana Ltd., Village Chorkhali, Tehsil Kalamb, Dist. osmanabad, Maharashtra,Kalamb,Osmanabad,Maharashtra-413405 | (d)Pin code | 413405 | (e)E-mail | dharashivsugar@yahoo.co.in | (f)STD Code. | 0(f)Telephone No. | 00 | (g)Fax No. | 00 | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 5(g) Distilleries
| Minor Activity | | (b)Category | A | (c)Proposal Number | IA/MH/IND2/94118/2018 | (d)Master Proposal Number(Single Window) | SW/94117/2019 | (e)EAC concerned (for category A Projects only) | Industrial Projects - 2 | (f)Project Type | Fresh EC |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | Gut No. 55,56,57,58 | (b)Pincode | 413405 | (c)Bounded Latitudes (North) | | From | | Degree | 1822 | Minutes | | Second | | From | | Degree | 1823 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 7550 | Minutes | | Second | | From | | Degree | 7651 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | 0 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 600 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 0 | (j)Seismic Zone | 3 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Maharashtra | |
|
|
Details of State of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
NIL | |
|
6. | Details of Terms of Reference (ToR): | (a)MoEF&CC / SEIAA File Number | No.IA-J-11011/169/2018-IA-II(I) | (b)Date of Apply of TOR | 12 May 2018 | (c)Date of Issue of TOR / Standard ToR | 17 Jun 2018 | (d)Previous TOR Letter | Copy of Previous TOR letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | No | (b)Whether details of Public Hearing available? | Yes | (c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above | Yes | |
|
7.1. Details of Public Hearing |
---|
|
S. No. | Details of Advertisement | Details of Public Hearing | Venue | Location Details | No. of People Attended | Issues Raised | Designation of Presiding Officer | Other Designation of Presiding Officer |
---|
(1.) | | Copy of Public Hearing : | Copy of Public Hearing | Date : | 20 Oct 2018 | Distance of Public Hearing Venue from the Proposed Project : | 0 |
| Dharashiv Sakhar Karkhana Ltd., Gat No. 55,56,57,58, Village Chorakhali, Tehsil Kalamb, Dist. Osmanabad, Maharashtra | State : | Maharashtra | District : | Osmanabad | Tehsil : | Kalamb | Village : | Chorakhali |
| 110 | 1. Weather the local
people suffer due to
pollution problem
after commissioning
of the project
2. Which type of mitigation measures will be taken if there is a pollution for the said
project.
3 | District Magistrate | | |
8. | Details of Project Configuration/Product: | |
|
8.1. Project Configuration |
---|
S. No. | Plant/Equipment/Facility | Configuration | Remarks |
---|
(1.) | Molasses based distillery Unit | 45 | KLPD | |
8.2. Product |
---|
S. No. | Product/Activity (Capacity/Area) | Quantity | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | Molasses based Distillery | 45 | Kilo Litre per Day | | Road | | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | Details Not Applicable | |
|
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | N/A | (iv)Valid Upto | N/A | (v)File No. | NIL | (vi)Application No. | NIL | (vii)Copy of Consent to operate valid as on date | Copy of Consent to Operate | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 72.5 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 5.65 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 1.45 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 0.684 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | Yes | a)Protected areas notified under the wildlife (Protection) Act, 1972 | Yes | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 0 | (b)Existing quantity of raw material/fuel | N/A | (c)Total quantity of raw material/fuel | 0 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | Sulfuric Acid | 0.045 | Kilo Litre per Day | | Open Market | Road | | 150 | Open Market | | Copy of Linkage | (2.) | Molasses as raw material for distillery | 67680 | Tons per Annum | | in house and near by industry | Road,Pipe Conveyor | | 60 | MoU | | Copy of Linkage | (3.) | Turkey red oil | 0.26 | Kilo Litre per Day | | Open Market | Road | | 150 | Open Market | | Copy of Linkage | (4.) | Nutrients | 0.009 | Kilo Litre per Day | | Open Market | Road | | 150 | Open Market | | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 01 Mar 2018 To 01 May 2018 | (b)Season | Summer | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | PM10 | | Micro Gram per Meter Cube | 68 | 53 | 68 | 100 | (2.) | SO2 | | Micro Gram per Meter Cube | 29 | 17 | 28 | 80 | (3.) | PM2.5 | | Micro Gram per Meter Cube | 55 | 22 | 55 | 60 | (4.) | NOx | | Micro Gram per Meter Cube | 37 | 21 | 37 | 80 | |
14.2. No. of Ground Water monitoring locations : 5 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | Fluoride | | | mg/l | | 0.066 | 0.03 | 1 | 1.5 | (2.) | TDS | | | mg/l | | 1076 | 988 | 500 | 2000 | (3.) | pH | | | NA | | 7.6 | 7.2 | 6.5 | 8.5 | (4.) | Total Hardness | | | mg/l | | 511 | 482 | 200 | 600 | (5.) | TSS | | | mg/l | | 0 | 0 | 0 | 0 | (6.) | Chlorides | | | mg/l | | 233 | 213 | 250 | 1000 | |
14.3. No. of Surface Water monitoring locations : 4 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | pH | | NA | | 8 | 7.2 | E | (2.) | COD | | mg/l | | 16 | 15 | E | (3.) | DO | | mg/l | | 5.6 | 3.8 | B | (4.) | BOD | | mg/l | | 5 | 3 | E | |
14.4. No. of Ambient Noise monitoring locations : 8 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Day) | A-weighted decibels(dB(A)) | 67.2 | 41.2 | 75 Industrial and 55 Residential | (2.) | Leq(Night) | A-weighted decibels(dB(A)) | 59.4 | 29.5 | 70 Industrial and 45 Residential | |
14.5. No. of Soil Sample Monitored locations : 8 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | pH | | | 7.9 | 7.2 | (2.) | N(Nitrogen) | Kilogram per hectare | | 35.7 | 31.4 | (3.) | K(Potassium) | Kilogram per hectare | | 42.5 | 39.5 | (4.) | Electric Conductivity | Millisiemens per Centimetre | | 0.28 | 0.1 | (5.) | P(Phosphorus) | Kilogram per hectare | | 18.4 | 10.4 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 18.32 To 4.77 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 18.5 To 4 | (c)Whether Ground Water Intersection will be there ? | NA | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | Surface | | 458 | 2.15 | Copy of Permission Letter | Pipeline | | Jack Well | | 39666 | 03 Apr 2019 | 555.55 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | Process | 355 | 500 | Primary + Secondary +Tertiary | Reuse within the Plant & Recycling,Green Belt Renewal Plant | | 355 | | (2.) | cooling purpose | 59 | 500 | Primary + Secondary +Tertiary | Reuse within the Plant & Recycling | | 59 | | (3.) | Boiler | 12 | 500 | Primary + Secondary +Tertiary | Reuse within the Plant & Recycling | | 12 | | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 426 | (b)Total Discharged Water (Kilolitre per Day) | 0 | (c)Total Reused Water (Kilolitre per Day) | 426 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Biogas | Industrial Waste | | 9528 | Tons | 10 | Road | | Others | Given as manure to nearby farmers | (2.) | fly Ash | Fly Ash | | 75 | Tons | 0.5 | Road | | Others | Bio composting and supplied to brick manufacturing | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | PM2.5 | | Microgram per Meter Cube | 53.24 | 1 | 0.76 | 54.2 | 80 | (2.) | SO2 | | Microgram per Meter Cube | 19.96 | 1 | 6.5 | 26.50 | 80 | (3.) | NOx | | Microgram per Meter Cube | 21.99 | 1 | 0.21 | 22.23 | 80 | (4.) | PM10 | | Microgram per Meter Cube | 53.24 | 1 | 0.76 | 54.2 | 100 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | Boiler (15 TPH) | Baggase | 60 | 2.0 | PM10 | | 50 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 1500 | (b)Source | MSEDCL | (c)Uploaded Copy of Agreement | Copy of Agreement | (d)Standby Arrangement (Details of DG Sets) | 0 | (e)Stack Height (in m) | 0 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 0 | (b)Private Land (ha.) | 26.30 | (c)Government Land (ha.) | 0 | (d)Revenue Land (ha.) | 0 | (e)Other Land (ha.) | 0 | Total Land (ha.) | 26.30 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 7857.72 | (b)Waste/Barren Land (ha.) | 7351.47 | (c)Grazing/ Community Land (ha.) | 0 | (d)Surface Water Bodies (ha.) | 820.95 | (e)Settlements (ha.) | 762.44 | (f)Industrial (ha.) | 0 | (g)Forest (ha.) | 0 | (h)Mangroves (ha.) | 0 | (i)Marine Area (ha.) | 0 | (j)Others (ha.) : Fallow land scrub land | 14693.64 | Total (ha.) | 31486.22 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Main Plant | | 2.02 | for process | (2.) | Others | Pollution control facility | 8.09 | for Pollution control facility | (3.) | Green belt | | 10.11 | Green belt development | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | ESAs | NA | 0 | No ESAs within 10 Km radius | (2.) | Corridors | NA | 0 | No Corridors within 10 Km radius | (3.) | Wildlife Corridors | NA | 0 | No wildlife corridors within 10 Km radius | (4.) | ESZs | NA | 0 | No ESZs within 10 Km radius | (5.) | NPA | NA | 0 | No NPA within 10 Km radius | (6.) | Critically Polluted Area | NA | 0 | No critically polluted area within 10 Km radius | (7.) | WLS | Yedashi Ramling Wild life santuary | 8.5 | As per Yedshi sanctuary map, our project site is located away from Eco sensitive Zone ,thus there no requirement to obtained NOC from wild life division. | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Archaeological Sites | | NA | 0 | No Archiological sites within 10 Km radius | (2.) | Defence Installations | | NA | 0 | No Defense installation within 10 Km radius | (3.) | Forest | | NA | 0 | No Forest within 10 Km radius | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
25. | Tree Cutting: | (a)No. of Trees Cut for the Project (if Forest Land not Involved) | 0 | (b)Details of Tree Cutting and Planting of Trees | Not Applicable | |
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 26.30 | (b)Land yet to be acquired(Ha) | 0 | (c)Status of Land acquisition if not acquired | In hand | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 0 | (b)No. of Households | 0 | (c)No. of PDFs (Project Displaced Families) | 0 | (d)No. of PAFs (Project Affected Families) | 0 | (e)Funds Allocated for R&R(in INR) (in Lacs) | 0 | (f)Status of R&R | Completed | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | No | (b)Whether conservation plan for Schedule-I Species has been prepared ? | No | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | No | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | No | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 0 | (b)Permanent Employment-During Operation | 95 | (c)Temporary Employment- During Construction | 0 | (d)Temporary Employment- During Operation | 20 | (e)No. of working days | 210 | (f)Total Manpower | 115 | |
|
32. | Green Belt in Ha: | (a)Total Area of Green Belt | 10.11 | (b)Percentage of Total Project Area | 38.44 | (c)No. of Plants to be Planted | 33149 | (d)Funds Allocated for Plantation | 0.45 | (e)Uploaded Green Belt plan | Copy of Green Belt Plan | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Environmental | greening area will be increase | (2.) | Social | Employment Generation will be generate for near by people | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details : NOT APPLICABLE |
35. Sector Specific Details For Industrial Projects - 2 |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | (QCI/NABET Accredited Vide S. No. 140,Dated 15.06. | (ii)Name of the EIA Consultant | M/s. Sri Sai Manasa Nature Tech Pvt. Ltd. | (iii)Address | Plot No. 74/A, Flat No 102, Central Bank Building Kalyan Nagar, Hyderabad 500038 | (iv)Mobile No. | 9010529529 | (v)Landline No. | 0402316333 | (vi)Email Id | ssmntpl@gmail.com | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | Industrial Projects - 2 | (ix)Validity of Accreditation | 19 Jul 2019 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought: |
---|
Sno. | EDS Letter | Remarks | Date of EDS |
---|
1. | NA | Public hearing proceedings not attached/uploaded against column 7.1 of Form-2. Also, please provide firm commitment of the concerned regulatory authority (in English) to allow surface water requirement of 458 cum/day. | 23 Mar 2019 | 2. | NA | The correction have been made as per the instruction received | 05 Apr 2019 | 3. | NA | The correction have been made as per the instruction received | 05 Apr 2019 | 4. | NA | Please reply to the observations dated 23/3/2019 for further consideration of the proposal. | 13 Apr 2019 | 5. | NA | The correction have been made as per the instruction received | 26 Apr 2019 | 6. | NA | Please reply to our observations dated 23/3/2019, reiterated on 13/4/2019, for consideration of the proposal. | 04 May 2019 | 7. | NA | The correction have been made as per the instruction received | 18 May 2019 | 8. | NA | Please inform/clarify the following:-
- Yedashi Ramling WLS is within 10 km from the project site. In such a case, no requirement of permission from the Standing Committee of NBWL needs to be confirmed.
- Entries against items 14.1 & 18.1 (regarding air quality) of Form-2 are not consistent. PM10 & PM2.5 values are reported to be same at 53.24 ug/m3, which requires revisiting of the whole exercise. | 25 May 2019 | |
Additional Detail Sought : NIL |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | Amar Dhananjay Patil | Designation | MD | Name of Company (Applicant Name should not be given here) | DHARSHIV SAKHAR KARKHANA LTD. | Address | M/s. Dharashiv Sakhar Karkhana Ltd., Village Chorkhali, Tehsil Kalamb, Dist. Osmanabad, Maharashtra |
|