Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Expansion of Shree Limestone Mine from 8.6 Million TPA to 11.06 Million TPA Limestone Production with 3.42 Million TPA Inter-burden & Over-burden and 0.96 Million TPA Top Soil (ML No. 38/2007, ML. Are
(b)Name of the Company / Organisation SHREE CEMENT EAST PRIVATE LIMITED
(c)Registered Address 21, Strand Road, Kolkata,,Kolkata,West Bengal-700001
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Dr Anil Kumar Trivedi
(b)Designation (Owner/ Partner/ CEO) Authorized Signatory
(c)Address 21, Strand Road Road, Kolkata,,Kolkata,Jhunjhunu,Rajasthan-700001
(d)Pin code 700001
(e)E-mail sceplenv@shreecement.com
(f)STD Code. 0(f)Telephone No.
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity1(a) Mining of minerals
Minor Activity2(b) Mineral beneficiation
(b)Category A
(c)Proposal Number IA/CG/MIN/93467/2017
(d)Master Proposal Number(Single Window) SW/93438/2019
(e)EAC concerned (for category A Projects only) Non-Coal Mining
(f)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Khasra Map is enclosed
(b)Pincode 493113
(c)Bounded Latitudes (North)
From
Degree 213436
Minutes
Second
From
Degree 213706
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 820312
Minutes
Second
From
Degree 820612
Minutes
Second
(e)Survey of India Topo Sheet No. F44Q2, F44P14
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 277
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 25
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Chhattisgarh
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number J-11015/07/2018-IA.II(M)
(c)Date of Issue of TOR 06 Feb 2018
(f)Previous TOR Letter Copy of Previous TOR letter
(b)Date of Apply of EC 14 Mar 2019
(c)Date of Issue of EC 27 Aug 2020
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :01 Jul 2018
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :04 Aug 2018
Distance of Public Hearing Venue from the Proposed Project :3.0
Village Chandi Ground (Near Panchayat Bhawan)
State :Chhattisgarh
District :Balodabazar
Tehsil :Simga
Village :Chandi
62Development of near by area, employment, water and environment etcOthersAdditional District Magistrate
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Nagpur
(iii)Letter No. EC-353/RON/2017-NGP/3998 dated 31.07/2018 and EC-3
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit May 15 2018 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Area531.1260531.126Hectares(ha)Conveyor Belt,Othersnone
(2.)Limestone8.62.4611.059999999999999OthersMillion TPAConveyor Belt
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Drill Machine224
(2.)Hydraulic Excavator347
(3.)Explosive Ven112
(4.)Diesel Tanker223
(5.)Dumper12921
(6.)Water Tanker213
(7.)Rock Breaker334
(8.)Jeep112
(9.)Crusher2X1200 TPH (Primary Crusher)2x450 TPA (Secondary Crusher)2*1200 TPH + 2*450 TPH
(10.)Motor Grader112
(11.)Maintenance Van112
(12.)ANFO Pump Truck112
(13.)Soil Compactor202
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception Copy of Consent to Operate
(iii)Date of Issue 13 Dec 2017
(iv)Valid Upto 12 Dec 2018
(v)File No. No. 5023/TS/CECB/2017
(vi)Application No. Application for renewal of CTO has been submitted
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 67.68
(b) Funds Allocated for Environment Management (Capital) (in Crores) 1.1
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 169.2
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.25
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 0
(b)Existing quantity of raw material/fuel 0
(c)Total quantity of raw material/fuel 0
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Diesel7140OthersKilo LiterOpen MarketRoad50 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Oct 2017 To 31 Dec 2017
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 15
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube84.259.783.71100
(2.)SO2Micro Gram per Meter Cube13.55.313.3380
(3.)NOxMicro Gram per Meter Cube28.512.528.1880
(4.)PM2.5Micro Gram per Meter Cube43.224.342.8260
    14.2.     No. of Ground Water monitoring locations : 10
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA8.027.366.58.5
(2.)TSSNA....
(3.)TDSmg/l8012345002000
(4.)Total Hardnessmg/l552.29216.46200600
(5.)Fluoridemg/l1.060.5411.5
(6.)Chloridesmg/l181.4111.402501000
(7.)Heavy MetalsCoppermg/l0.020.020.051.5
    14.3.     No. of Surface Water monitoring locations : 6
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA8.087.36E
(2.)DOmg/l5.04.4E
(3.)CODmg/l25.696.8E
(4.)BODmg/l7.202.3E
    14.4.     No. of Ambient Noise monitoring locations : 15
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))65.649.575
(2.)Leq(Night)A-weighted decibels(dB(A))58.849.570
    14.5.     No. of Soil Sample Monitored locations : 10
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)K(Potassium)Kilogram per hectare492.07215.9
(2.)N(Nitrogen)Kilogram per hectare306.54215.45
(3.)Electric ConductivityMillisiemens per Centimetre0.420.17
(4.)P(Phosphorus)Kilogram per hectare55.620.22
(5.)pH8.057.60
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 10 To 5
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 3 To 5
(c)Whether Ground Water Intersection will be there ? Yes
(d)Upload Copy of Central Ground Water Authority Letter Copy of Central Ground Water Authority Letter
(e)Letter No. 21-4(36)/NCCR/CGWA/2008-2079
(f)Date of Issue 24 Oct 2018
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater3000.1Copy of Permission LetterPipelineTube Well21-4(36)/NCCR/CGWA/2008-207924 Oct 20183000
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Workshop2030Oil water separatorOthersUsed in dust suppression200
(2.)Domestic & Utility1020sock pit via septic tankOtherssock pit via septic tank010
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 30
(b)Total Discharged Water (Kilolitre per Day) 10
(c)Total Reused Water (Kilolitre per Day) 20
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Waste (OB & IB)OthersOB & IB3420000Tons0OthersHaul RoadOthersBackfilling and waste dump in ML area
(2.)ToP SoilOthersTop Soil960000Tons0Othershaul roadOthersPlantation & Green Belt Development
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM2.5Microgram per Meter Cube40.31.456.7847.0960
(2.)SO2Microgram per Meter Cube12.41.575.2517.6680
(3.)NOxMicrogram per Meter Cube21.02.87.5828.5980
(4.)PM10Microgram per Meter Cube78.21.578.586.8100
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)Primary Crusher 2Power302PM10825 g/sec
(2.)Secondary Crusher 1Power151.5PM10458 g/sec
(3.)Secondary Crusher 2Power151.5PM10458 g/sec
(4.)Primary Crusher 1Power302PM10825 g/sec
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 4760
(b)Source Existing & Proposed 125 MW CPP 100 MW WHRS
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 0
(e)Stack Height (in m) 30
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 452.404
(c)Government Land (ha.) 78.722
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 531.126
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 452.404
(b)Waste/Barren Land (ha.) 78.722
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 0
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : 0 0
    Total (ha.) 531.126
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)OB Dump Area21Waste Dump stabilized by plantation
(2.)Water Reservoir319.2
(3.)Township22
(4.)Green belt77.89.3 ha - green belt, 68.5 ha on virgin area
(5.)Area for Solid Waste Management7070 ha - back filled and reclaimed by plantation
(6.)OthersUndisturbed Area21.126
Total (ha.) 531.126
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNone0No CPA within 10 radius of Mine Site
(2.)WLSNone0No WLS within 10 radius of Mine Site
(3.)NPANone0No NPA within 10 radius of Mine Site
(4.)CorridorsNone0No Corridors within 10 radius of Mine Site
(5.)Wildlife CorridorsNone0No Wildlife Corridors within 10 radius of Mine Site
(6.)ESAsNone0No ESZs within 10 radius of Mine Site
(7.)ESZsNone0No ESZs within 10 radius of Mine Site
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestDhabadih Reserve Forest0.25Proper Protection measures will be taken
(2.)Defence InstallationsNone0No Defense installation within 10km radius
(3.)Archaeological SitesNone0No Archaeological site within 10km radius
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) Not Applicable
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 449.846
(b)Land yet to be acquired(Ha) 2.558
(c)Status of Land acquisition if not acquired 78.772
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Mahanadi Canal
(ii)Direction of Water Bodies in Buffer Area East
(iii)Distance of Water Bodies in Buffer Area 0.05
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 20
(b)Permanent Employment-During Operation 195
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 0
(e)No. of working days 340
(f)Total Manpower 215
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt56.35119.65176
(2.)Funds Allocated432568
(3.)No. of Plants139186300814440000
(4.)Percentage of Total Project Area10.6022.5233.12
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)FinancialThe Project will contribute additional revenue to the State and Central Govt. in the form of royalty, cess and other taxes etc.
(2.)Environmental• At the conceptual stage total excavated area will be 389.2 ha out of which 319.2 ha area will be converted into water reservoir and 70 ha area will be backfilled. The water reservoir will be helpful for recharge of ground water. • At end of life of mine, about, total greenbelt/Plantation will be done on 176 ha (70 ha on backfilled area and 21 ha area on waste dump, 7.2 ha in colony area, 9.3 ha on 7.5 m barrier zone & 68.5 ha on virgin area) which will be beneficial to the environment & will p
(3.)Social• M/s. Shree Cement Limited is undertaking/ will undertake activities for the upliftment of the social community through community development in various ways as under: ? Education Promotion Program ? Health & Family Welfare Programme ? Infrastructure Development ? Social Welfare& Skill Development Activities ? Sustainable Livelihood
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Non-Coal Mining
S. No.Item Details
     1.       No. of Mineral(s) to be Mined : 1
S. No.Mineral(s) to be Mined Major or Minor Mineral
(1.)LimestoneMajor
2.
Mine Capacity in ROM (Run of Mine) 14.48
3.
Uploaded 500 meters Cluster Certificate from State Mines and Geology in case of minor minerals Copy of 500 meters Cluster Certificate from State Mines and Geology
4.
Mining Plan:
(a)Approval Letter No. Balodabazar/ Chup/MP-1125/2017/717
(b)Date of Approval 30 Nov 2017
(c)Approved Letter Copy of Approved Letter
(d)Approved By State Mining and Geology Department IBM
(e)Approved Mining Lease Area 531.126
(f)Approved Capacity 11.6
5.
Technical Details:
(a)Total Geological Reserves (Million Ton) 237.9
(b)Mineable Reserves (Million Ton) 208.6
(c)Extractable Reserves(Million Ton) 208.6
(d)Percent(%) of Extraction 100
(e)Grade of Coal /Ore /Mineral Cement Grade
(f)Stripping Ratio 1 : 0.4
(g)Category of Gaseousness (Only for Coal Mining, Others may Write NA) NA
(h)Average Gradient(Degree) 45
(i)Mining Method Opencast
(j)Life of Mine (Years) 20
6.
Details of Beneficiations:
(a)Whether it is proposed to install beneficiation plant/Coal washery within the mining lease area No
(b)Whether it is proposed to install crusher within the mining lease area Yes
(c)No. of crushers 4
     6.1.    Details of crusher:
S. No.Crusher ID Capacity (in PH)Remarks
(1.)11200 Primary Crusher
(2.)21200 Primary Crusher
(3.)3450 Secondary Crusher
(4.)4450 Secondary Crusher
7.
Details of Seams:
(a)Whether details of seam applicable No
8.
Details of Mining Lease:
(a)Mining Lease Area (in Hectare) 531.126
(b)Whether obtained Letter of Intent (LOI) from the state government ? Yes
(i)Copy of Letter of Intent Copy of Letter of Intent
(ii)Date of issue of LOI 25 Mar 2008
(iii)Validity of LOI 50
(iv)Reference No. of LOI F 2-32/2003/12(3)
(c)Whether Lease Deed Executed ? Yes
(i)Copy of Executed Lease deed valid as on Date Copy of Executed Lease deed
(ii)Provide area in Hectare as per executed lease deed (initial) document 531.126
(iii)Validity of the lease deed From : 11 Jan 2011 To : 10 Jan 2061
(iv)Date of Execution of Mining Lese 11 Jan 2011
(v)Reference Number Government order no. F-2/32/2003/12 (3)
(d)Whether Lease Deed Renewed ? No
(i)Reason thereof lase valid upto 2061
9.
OB (Over Burden) Management:
(a) Details of External Dumps:
(i)No. of OB Dumps 0
(ii)Total Area (in Hectare) 0
(iii)Height (in meter) 0
(iv)Quantity (in Million Cubic meter) 0
(v)No. of year back fill up 0
(b) Details of Internal Dumps:
(i)No. of Internal Dumps 1
(ii)Total Area (in Hectare) 21
(iii)Height (in meter) 30
(iv)Quantity (in Million Cubic meter) 4.8
10.
Details of Topsoil Management:
(a)Quantity of Topsoil excavated during the entire life of the mine (in Million Cubic metre) 1.58
(b)Quantity of Topsoil proposed for utilization for reclamation during the entire life of the mine (in Million Cubic metre) 1.58
(c)Quantity of Topsoil proposed for utilization for other activities during the entire life of the mine (in Million Cubic metre) 0
11.
Details of Final Mine Void:
(a)Area (in Hectare) 70
(b)Depth (in meter) 80
(c)Volume (in Million Cubic meter) 56
12.
Details of Quarry:
(a)Final Void of 319.2 (hectare) at a Depth of 80 meter which is Proposed to be Converted into a Water Body.
(b)Total Quarry Area (ha) 389.2
13.
Details of Transportation:
(a)In Pit/Underground to Surface from working face to crusher hopper will be carrie
(b)Surface to Siding/Loading Loading will be done by Hydraulic Excavators
(c)Transportation / Conveyor Details Crusher to Cement plant by Covered Conveyor Belt
     14.      Details of Land Usage (Pre-Mining)
S. No.LAND USE Other LAND USEWITHIN ML AREA (Hectare)OUTSIDE ML AREA (Hectare)TOTAL (Hectare)
(1.)SURFACE WATER BODIES000
(2.)AGRICULTURE LAND452.4040452.404
(3.)WASTE LAND78.722078.722
(4.)FOREST LAND000
(5.)GRAZING LAND000
(6.)SETTLEMENTS000
TOTAL531.1260531.126
     15.      Details of Land Usage (Post-Mining)
S. No.LAND USE Other LAND USEPlantation (ha)Water Body (ha)Public Use (ha)Undisturbed (ha)Total
(1.)EXCAVATION/QUARRY70319.20389.2
(2.)BUILT UP AREA (COLONY/OFFICE)7.2014.822
(3.)TOP SOIL STORAGE0000
(4.)EXTERNAL OB DUMPS0000
(5.)ROADS0000
(6.)INTERNAL OB DUMPS210021
(7.)OtherUndisturbed Area0021.12621.126
(8.)VIRGIN AREA68.50068.5
(9.)GREEN BELT9.3009.3
TOTAL176319.235.9260531.126
16.
Details of Reclamation:
Total Afforestation Plan shall be Implemented Covering of Mining.
This will Include:
(a)External OB Dump(in hectare) 0
(b)Internal Dump(in hectare) 21
(c)Quarry(in hectare) 389.2
(d)Safety Zone(in hectare) 9.3
(e)Final Void of 319.2 (hectare) at a Depth of 80 meter which is Proposed to be Converted into a Water Body.
(f)Density of Tree Plantation per ha (in no.) 2500
(g)Others in ha (such as Excavation Area along ML Boundary, along Roads and Infrastructure, Embankment Area and in Township Located Outside the Lease etc) .
(h)Total afforestation plant (in hectare) 176
17.
Status of progressive Mining Closure Plan:
Copy of Implementation of Various Activities as per Approved Progressive Mine Closure Plan Copy of Implementation of Various Activities as per Approved Progressive Mine Closure Plan
Any Deviation from the Approved Progressive Mine Closure Plan 0
Total Area Excavated (in hectare) 58.93
Total Area Backfilled after Excavation (in hectare) 0
Total Area Reclaimed (in hectare) 56.35
     18.      Details of Actual Coal/ ORE Production vis-a-vis Sanctioned Capacity since the Inception:
S. No.Financial Year Sanctioned Capacity as per EC (MTPA)Sanctioned Capacity as per CTOSanctioned Capacity as per approved mining planActual Production Excess Production Beyond the EC / CTO/ Mining Plan Sanctioned Capacity (MTPA)
(1.)2015164.84.84.31.980
(2.)2016174.84.84.32.990
(3.)2017188.68.68.824.110
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1619/RA 0069
(ii)Name of the EIA Consultant J.M. EnviroNet Pvt. Ltd.
(iii)Address 202-A, ABW Tower, MG Road, IFFCO Chowk, Sector 25, Gurugram (Haryana) – 122001
(iv)Mobile No. 9509267011
(v)Landline No. 0124414192
(vi)Email Id jmenviron@hotmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Non-Coal Mining
(ix)Validity of Accreditation 18 May 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NA(i) Details of TOR /EC has not uploaded as S. no. 6 of Form 2. (ii) Copy of certified compliance report has not uploaded (iii) Details of past production of mine since its inception, duly authenticated by Department of Mines & Geology, State Government. (iv) The details of with respect to heavy metal in S. No. 14.2 of Form 2. (v) Copy of valid CGWA approval needs to be submitted. (vi) Copy of Green belt plan needs to be uploaded. (vii) Copy of approved mine plan has not uploaded. (viii) S. No. 17. Of form 2 is not adequate (ix) Name of company/PP mentioned as Rakesh Bhargava. However the document is related to Shree Cement. 21 Feb 2019
2.NAThe correction have been made as per the instruction received 23 Feb 2019
3.NA(i). PP has submitted the copy of proceedings of the Public Hearing, however there is no mentioning of letter number and date of the letter etc. in the proceedings. State Pollution Control may be requested to submit the copy of proceedings with latter no. and date. Authenticated translated copy of the PH proceedings shall also be submitted. (ii). Compliance report inter-alia mentioned some of the non-compliances of earlier EC conditions. However, the action plan has not uploaded by the PP on Parivesh Portal. (iii). Compliance of order dated 02.8.2017 in CWP No. 114/2014 of Hon'ble Supreme court (Common Cause Vs Union of India &Ors.). Details of demand if any raised by Department of Mining and Geology. Details of payment, if any made to Department of Mines & Geology (iv). Earlier EDS was clearly mentioned that, “Name of company/PP mentioned as Rakesh Bhargava. However the document is related to Shree Cement.” Ministry has earlier also mentioned many time, however PP is ignoring the d 01 Mar 2019
4.NAThe correction have been made as per the instruction received 14 Mar 2019
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterRespected Sir, We are herewith submitting the ADS Reply for your kind consideration. Best Regards 30 Jun 2020
2.NA

deferred

10 May 2019
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantDr Anil Kumar Trivedi