Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Development of 8 lanes (Greenfield Highway) from Firozpur Jhirka (Ch. 79+394) to Itawa (Ch. 284+000) Section of NH-148 N (Total length 204.606 km), Under Bharatmala Priyojana Lot-4/Pkg-4 in the state
(b)Name of the Company / Organisation National Highways Authority of India
(c)Registered Address G-5 & 6, Sector-10, Dwarka, New DElhi-110075,G-5 & 6, Sector-10, Dwarka, New DElhi-110075,South West,Delhi-110075
(d)Legal Status of the Company Central Government
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Dr Biswajit Mukhopadhyay
(b)Designation (Owner/ Partner/ CEO) General Manager
(c)Address G-5 & 6, Sector-10, Dwarka, New DElhi-110075,G-5 & 6, Sector-10, Dwarka, New DElhi-110075,,New Delhi,Delhi-110075
(d)Pin code 110075
(e)E-mail biswajit@nhai.org
(f)STD Code. 11(f)Telephone No. 25074200
(g)Fax No. 25093543
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity7(f) Highways
Minor Activity
(b)Category A
(c)Proposal Number IA/RJ/NCP/93313/2018
(d)Master Proposal Number(Single Window) SW/93294/2019
(e)EAC concerned (for category A Projects only) INFRA-1
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. List attached in additional details
(b)Pincode 301001
(c)Bounded Latitudes (North)
From
Degree 26.032575
Minutes
Second
From
Degree 27.653644
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 76.261683
Minutes
Second
From
Degree 77.462950
Minutes
Second
(e)Survey of India Topo Sheet No. 54A14, 54A15, 54A16, 54A12, 54B5, 54B9, 54B6, 54B2
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 348
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 216
(j)Seismic Zone 4
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Rajasthan
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR):
(a)Whether TOR is mandatory for submitting application Yes
(b)MoEF&CC / SEIAA File Number 10-61/2018-IA.III
(c)Date of Apply of TOR 19 Jul 2018
(d)Date of Issue of TOR / Standard ToR 14 Jan 2019
(e)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :11 Dec 2018
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :11 Jan 2019
Distance of Public Hearing Venue from the Proposed Project :7.5
Conference hall, District Magistrate office, Dausa
State :Rajasthan
District :Dausa
Tehsil :Dausa
Village :Dausa City
116Regarding compensation of land and impact of pollution during construction and tree plantation.OthersCEO, Nagar Parishad
(2.)
Date of Advertisement :29 Nov 2018
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :02 Jan 2019
Distance of Public Hearing Venue from the Proposed Project :2.5
Campus, Sub-tehsil Baroda Meo, Tehsil - Lakshmanghar, Alwar
State :Rajasthan
District :Alwar
Tehsil :lakshmangarh
Village :Baroda Meo
66Project affected peoples are more concern about land rates to be given by acquisition authority (CALA). Some people suggest for water sprinkler to mitigate the dust pollution during construction.OthersDIG Stamp Alwar-II
(3.)
Date of Advertisement :30 Nov 2018
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :03 Jan 2019
Distance of Public Hearing Venue from the Proposed Project :24
Conference hall, SDO Office, Tehsil-Nagar, Bharatpur
State :Rajasthan
District :Bharatpur
Tehsil :Nagar
Village :Nagar
48Regarding compensation of land and impact of pollution during construction.OthersAdditional District Magistrate
(4.)
Date of Advertisement :06 Dec 2018
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :11 Jan 2019
Distance of Public Hearing Venue from the Proposed Project :8.8
Conference hall, Panchayat Samiti, Sawai Madhopur
State :Rajasthan
District :Sawai Madhopur
Tehsil :Sawai Madhopur
Village :SWM City
122Regarding compensation of land and impact of pollution during construction and tree plantation.OthersADM
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)HMP, Batching plant, WMM & CrusherTo be decided by Contractor
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Greenfield Excess Control Highway204.606KilometersRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 5518
(b) Funds Allocated for Environment Management (Capital) (in Crores) 20.95
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 43.02
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.6
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 237730
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 237730
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Soil46020738OthersCUMNearby Approved borrow areaRoad3.5 Open MarketCopy of Linkage
(2.)Granular material/Moorum2335842OthersCUMNearby Approved QuarryRoad20 Open MarketCopy of Linkage
(3.)Aggregate2743101OthersCUMNearby Approved QuarryRoad20 Open MarketCopy of Linkage
(4.)Sand410444OthersCUMNearby Approved QuarryRoad20 Open MarketCopy of Linkage
(5.)Filler70324OthersMTNearby Approved QuarryRoad20 Open MarketCopy of Linkage
(6.)Stone Dust1522752OthersCUMNearby Approved QuarryRoad20 Open MarketCopy of Linkage
(7.)Cement363855OthersMTNearby Approved QuarryRoad20 Open MarketCopy of Linkage
(8.)HYSD Bar1137903OthersMTNearby Approved QuarryRoad30 Open MarketCopy of Linkage
(9.)Bitumen237730OthersMTNARoad0 OthersTo be decide by ContrctorCopy of Linkage
(10.)Water6375612OthersKLSurface WaterOthersTanker Supply5 OthersSurface Water BodyCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Mar 2018 To 30 May 2018
(b)Season Pre-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 12
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube94.2651.0694.17100
(2.)SO2Micro Gram per Meter Cube20.296.0419.8380
(3.)NOxMicro Gram per Meter Cube37.4310.2736.9280
(4.)PM2.5Micro Gram per Meter Cube57.4521.2656.9460
(5.)OthersCOMicro Gram per Meter Cube0.920.420.9204
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TDSmg/l27301155002000
(2.)Chloridesmg/l634.3842.292501000
(3.)Fluoridemg/l1.360.361.01.5
(4.)Heavy MetalsLead ( as Pb)mg/l0.050.050.010.01
(5.)OthersCalcium (as Ca)mg/l278.960.28475200
(6.)TSSmg/l0000
(7.)pHNA9.077.206.58.5
(8.)Total Hardnessmg/l106828200600
    14.3.     No. of Surface Water monitoring locations : 3
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA8.477.17C
(2.)DOmg/l5.75.3C
(3.)BODmg/l10.36.4C
(4.)CODmg/l32.422.6C
(5.)OthersTotal ColiformOthersMPN/100ml00C
    14.4.     No. of Ambient Noise monitoring locations : 12
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))38.933.445
(2.)Leq(Day)A-weighted decibels(dB(A))51.846.5655
    14.5.     No. of Soil Sample Monitored locations : 10
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)K(Potassium)Milligram per Kilogram165.2145.2
(2.)Electric ConductivityOthersMhos/cm0.340.14
(3.)pH7.657.04
(4.)P(Phosphorus)Milligram per Kilogram39.528.7
(5.)N(Nitrogen)Milligram per Kilogram346332
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 10 To 40
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 10 To 40
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Surface87340 Not Appliacble modeOthersTankerIntake WellNA01 Jan 20190
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Camp Site3035STPGreen Belt Renewal Plant30
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 30
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 30
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)NAMunicipal Solid Waste231Tons50RoadTreatment, Storage and Disposal Facility(TSDF)
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube94.260094.27100
(2.)Others(Specify)COMicrogram per Meter Cube0.920.0500.811.742000
(3.)SO2Microgram per Meter Cube20.290020.3080
(4.)PM2.5Microgram per Meter Cube57.450057.4660
(5.)NOxMicrogram per Meter Cube37.430037.4480
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)NANA00PM100
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 0
(b)Source NA
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) Not Applicable
(e)Stack Height (in m) 0
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 27.866
(b)Private Land (ha.) 1792.64
(c)Government Land (ha.) 234.364
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 206.98
    Total Land (ha.) 2261.85
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 1654
(b)Waste/Barren Land (ha.) 493
(c)Grazing/ Community Land (ha.) 75
(d)Surface Water Bodies (ha.) 3
(e)Settlements (ha.) 8
(f)Industrial (ha.) 0
(g)Forest (ha.) 28
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : 0 0
    Total (ha.) 2261
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)OthersROW with Rest Area2261.85ROW Including Rest Area
Total (ha.) 2261.85
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)NPANA0NA
(2.)ESAsNA0NA
(3.)Wildlife CorridorsNA0NA
(4.)ESZsNA0NA
(5.)WLSNA0NA
(6.)Critically Polluted AreaNA0NA
(7.)CorridorsNA0NA
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Archaeological SitesNA0NA
(2.)ForestReserve & Protected Forest0.1Forest areas falling within the proposed ROW
(3.)Defence InstallationsNA0NA
(4.)OthersNANA0NA
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 30247
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0
(b)Land yet to be acquired(Ha) 2261.85
(c)Status of Land acquisition if not acquired under progress
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 161
(b)No. of Households 624
(c)No. of PDFs (Project Displaced Families) 624
(d)No. of PAFs (Project Affected Families) 7036
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Yet To Start
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area 11
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 2000
(b)Permanent Employment-During Operation 200
(c)Temporary Employment- During Construction 400
(d)Temporary Employment- During Operation 200
(e)No. of working days 730
(f)Total Manpower 2800
32.
Green Belt in Ha:
(a)Total Area of Green Belt 856
(b)Percentage of Total Project Area 37.85
(c)No. of Plants to be Planted 345741
(d)Funds Allocated for Plantation 518611500
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)Social1. High-speed connectivity and access, 2. Aiding economic growth, 3. Growth of backward areas, 4. Decongestion of existing National and State Highways, 6. Usage shift, 7. • Improved safety & 8. Support to industry
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For INFRA-1
S. No.Item Details
1.
Details of Building Construction:
(a)Maximum Height of the Building (Meters) 0
(b)Total No. of Flats to be Build 0
(c)No. of Buildings 0
(d)Total plot area (sqm) 0
(e)Total built up area (sqm) 0
2.
Foreshore Facilities and/or Marine Disposal:
(a)Whether Project Involves Foreshore Activities and/or marine Disposal? No
3.
Rain Water Harvesting:
(a)No. of Storage 0
(b)Capacity 0
(c)No. of Recharge Pits 0
(d)Capacity 0
4.
Parking:
(a)Details of 4 Wheeler/ 2 Wheeler Parking 0
5.
Energy Saving Measures:
(a)Source/Mode NA
(b)Percentage 0
(c)Quantity 0
6.
Other details:
(a)Details of impact on Water Bodies and Drainage patters of catchment area 0
(b)Details of Traffic Density Impact Assessment and Modelling Study Copy of Details of Traffic Density Impact Assessment and Modelling Study
(c)In case Underground Tunnel Project below the Forest Land - Subsidence Impact Study report Copy of Underground Tunnel Project below the Forest Land - Subsidence Impact Study report
     7.       Type of Industries to be established with Industrial Estate as per their category A/B
S. No.Type of IndustryNo. of UnitsCategory A/B
NIL
8.
Length of the alignment 204.606
9.
Details Bridges/ROB/Interchanges,Flyovers,Vehicle Underpass and Pedestrian Underpass
(a)Total No. of Bridges 47
(b)Total No. of ROB 9
(c)Total No. of Interchanges 11
(d)Total No. of Flyovers 6
(e)Total No. of Vehicle Underpass 169
(f)Total No. of Pedestrian Underpass 0
(g)Details of other utilities rail and road corridors Culvert-185
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1821/RA0116
(ii)Name of the EIA Consultant Feedback Infra Pvt. Ltd.
(iii)Address 15th Floor, Tower 9B, DLF Cyber City, Phase-III, Gurugram 122002
(iv)Mobile No. 9868563137
(v)Landline No. 0124431664
(vi)Email Id raj.singh@feedbackinfra.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation INFRA-1
(ix)Validity of Accreditation 26 Aug 2021
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File NA
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantDr Biswajit Mukhopadhyay
DesignationGeneral Manager
Name of Company (Applicant Name should not be given here)National Highways Authority of India
AddressG-5 & 6, Sector-10, Dwarka, New DElhi-110075
Print