|
1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | Proposed Project for the Manufacture of Pesticides (Aluminium Phosphide, Zinc Phosphide, Magnesium Phosphide Technical & Its Formulation) | (b)Name of the Company / Organisation | INTEGRATED CHEMISOL PVT LTD | (c)Registered Address | Plot No.4924,Notified industrial area,GIDC Sarigam,Ta:Umbergaon,,Valsad,Gujarat-396155 | (d)Legal Status of the Company | Private | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | Bhargav Desai | (b)Designation (Owner/ Partner/ CEO) | Director | (c)Address | Plot No.4924,Notified Industrial Area,GIDC Sarigam,,Umbergaon,Valsad,Gujarat-396155 | (d)Pin code | 396155 | (e)E-mail | bdesai@integratedpesticides.in | (f)STD Code. | 260(f)Telephone No. | 2970305 | (g)Fax No. | | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 5(b) Pesticides industry and pesticide specific intermediates (excluding formulations)
| Minor Activity | 5(b) Pesticides industry and pesticide specific intermediates (excluding formulations)
| (b)Category | A | (c)Proposal Number | IA/GJ/IND2/91857/2018 | (d)Master Proposal Number(Single Window) | SW/91853/2019 | (e)EAC concerned (for category A Projects only) | Industrial Projects - 2 | (f)Project Type | Fresh EC |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | Plot No. 4924, Notified Industrial Area, GIDC Sari | (b)Pincode | 396155 | (c)Bounded Latitudes (North) | | From | | Degree | 72.846177 | Minutes | | Second | | From | | Degree | 72.846330 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 20.286752 | Minutes | | Second | | From | | Degree | 20.287183 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | F43S15 & F43S16 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 28 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 00 | (j)Seismic Zone | 3 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Gujarat | |
|
|
Details of State of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
NIL | |
|
6. | Details of Terms of Reference (ToR): | (a)MoEF&CC / SEIAA File Number | No.IA-J-11011/201/2018-IA-II(I) | (b)Date of Apply of TOR | 16 Jun 2018 | (c)Date of Issue of TOR / Standard ToR | 22 Jul 2018 | (d)Previous TOR Letter | Copy of Previous TOR letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | No | (b)Whether details of Public Hearing available? | No | (c)Reason | Since the project is located in Notified Industrial Estate of GIDC Sarigam, Public hearing is not applicable. | (d)Supporting Document | Copy of Supporting Document | |
|
8. | Details of Project Configuration/Product: | |
|
8.1. Project Configuration |
---|
S. No. | Plant/Equipment/Facility | Configuration | Remarks |
---|
(1.) | Steam Boiler, TPH | 0.2 | | (2.) | D.G. Set (Standby), kVA | 100 | | (3.) | Cooling Tower, TR | 300 | | |
8.2. Product |
---|
S. No. | Product/Activity (Capacity/Area) | Quantity | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | Aluminium Phosphide/Zinc Phosphide/ Magnesium Phosphide Technical | 500 | Others | TPM | Road | | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | Details Not Applicable | |
|
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | 24 Jun 2018 | (iv)Valid Upto | 24 Jun 2018 | (v)File No. | NA | (vi)Application No. | NA | (vii)Copy of Consent to operate valid as on date | NA | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 6 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 0.1 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 0.12 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 0.5 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | No | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 1732 | (b)Existing quantity of raw material/fuel | N/A | (c)Total quantity of raw material/fuel | 1732 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | Ground Nut Oil | 76.8 | Tons per Annum | | Local | Road | | 0.5 | Open Market | | Copy of Linkage | (2.) | Red phosphorus | 3078 | Tons per Annum | | Local | Road | | 0.5 | Open Market | | Copy of Linkage | (3.) | Aluminum powder | 3180 | Tons per Annum | | Local | Road | | 0.5 | Open Market | | Copy of Linkage | (4.) | Paraffin Wax | 270 | Tons per Annum | | Local | Road | | 0.5 | Open Market | | Copy of Linkage | (5.) | Magnesium oxide | 61.2 | Tons per Annum | | Local | Road | | 0.5 | Open Market | | Copy of Linkage | (6.) | Graphite Powder | 90 | Tons per Annum | | Local | Road | | 0.5 | Open Market | | Copy of Linkage | (7.) | Saw dust | 180 | Tons per Annum | | Local | Road | | 0.5 | Open Market | | Copy of Linkage | (8.) | Yellow Phosphorus | 4470 | Tons per Annum | | Local | Road | | 0.5 | Open Market | | Copy of Linkage | (9.) | Magnesium | 3228 | Tons per Annum | | Local | Road | | 0.5 | Open Market | | Copy of Linkage | (10.) | water for scrubber | 1440 | Tons per Annum | | Local | Road | | 0.5 | Open Market | | Copy of Linkage | (11.) | Zinc Powder | 4710 | Tons per Annum | | Local | Road | | 0.5 | Open Market | | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 01 Oct 2018 To 31 Dec 2018 | (b)Season | Post-Monsoon | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | PM10 | | Micro Gram per Meter Cube | 86.1 | 61.9 | 85.7 | 100 | (2.) | PM2.5 | | Micro Gram per Meter Cube | 47.1 | 32 | 46.3 | 60 | (3.) | NOx | | Micro Gram per Meter Cube | 23 | 16.2 | 23 | 80 | (4.) | Others | CO | Micro Gram per Meter Cube | 688 | 344 | 688 | 2000 | (5.) | SO2 | | Micro Gram per Meter Cube | 17.6 | 9.4 | 17.5 | 80 | |
14.2. No. of Ground Water monitoring locations : 7 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | pH | | | mg/l | | 7.28 | 7.14 | 6.5 | 8.5 | (2.) | Others | Iron | | mg/l | | 0.28 | 0.14 | 0.3 | 0 | (3.) | TDS | | | mg/l | | 924 | 602 | 500 | 2000 | (4.) | Total Hardness | | | mg/l | | 584 | 384 | 200 | 600 | (5.) | Chlorides | | | mg/l | | 202 | 148 | 250 | 1000 | (6.) | Fluoride | | | mg/l | | 0.6 | 0.4 | 1 | 1.5 | (7.) | TSS | | | mg/l | | 2 | 2 | 0 | 0 | |
14.3. No. of Surface Water monitoring locations : 2 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | DO | | mg/l | | 4.9 | 4.7 | C | (2.) | BOD | | mg/l | | 6 | 4 | C | (3.) | pH | | mg/l | | 8.02 | 7.96 | C | (4.) | COD | | mg/l | | 20 | 10 | C | |
14.4. No. of Ambient Noise monitoring locations : 8 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Day) | A-weighted decibels(dB(A)) | 77.1 | 50.2 | 75 | (2.) | Leq(Night) | A-weighted decibels(dB(A)) | 73.5 | 42.1 | 70 | |
14.5. No. of Soil Sample Monitored locations : 4 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | pH | | | 7.82 | 7.56 | (2.) | K(Potassium) | Milliequivalents per 100 Gram | | 2 | 1.2 | (3.) | N(Nitrogen) | Percent | | 0.056 | 0.03 | (4.) | Electric Conductivity | Others | dS/m | 1.18 | 0.86 | (5.) | P(Phosphorus) | Milliequivalents per 100 Gram | | 19 | 9.8 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 6 To 6 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 12 To 9 | (c)Whether Ground Water Intersection will be there ? | No | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | Others | GIDC water | 6.5 | 7.5 | Copy of Permission Letter | Pipeline | | Others | Pipeline | GIDC/DEE/SRG 91 | 23 May 2018 | 10 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | Industrial | 2.8 | 5 | ETP | Others | Scrubbers | 2.8 | 00 | (2.) | Domestic | 0.8 | 0 | Septic tank | Others | septic tank | 0.8 | 00 | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 3.6 | (b)Total Discharged Water (Kilolitre per Day) | 0 | (c)Total Reused Water (Kilolitre per Day) | 3.6 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Discarded Containers | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 1 | Tons | 10 | Road | | Authorized Recyclers | | (2.) | Used Oil | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 0.05 | Tons | 10 | Road | | Others | Will be sold to Registered re-processers | (3.) | ETP waste | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 1 | Tons | 10 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (4.) | Phosphoric acid (60%) | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 1440 | Tons | 10 | Road | | Others | sell to users having rule 9 permission | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | PM2.5 | | NA | 0 | 0 | 0 | 01 | 011 | (2.) | NOx | | Microgram per Meter Cube | 23 | 0.010 | 3.42 | 27 | 80 | (3.) | SO2 | | Microgram per Meter Cube | 17.6 | 0.010 | 0.003 | 17.63 | 80 | (4.) | PM10 | | NA | 0 | 0 | 0 | 01 | 011 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | Steam Boiler | Natural Gas | 11 | 0.3 | NOx | | 3.42 | (2.) | steam boiler | natural gas | 11 | 0.3 | SO2 | | 0.003 | (3.) | D.G set | HSD | 11 | 0.15 | NOx | | 0 | (4.) | reactor | NA | 11 | 0.5 | Others | P2O5 | 0.007 | (5.) | D.G set | HSD | 11 | 0.15 | Others | PM | 0 | (6.) | D.G set | HSD | 11 | 0.15 | SO2 | | 0 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 125 | (b)Source | Dakshin Gujarat Vij Co. Ltd | (c)Uploaded Copy of Agreement | Not Applicable | (d)Standby Arrangement (Details of DG Sets) | 100 KVA | (e)Stack Height (in m) | 11 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 0 | (b)Private Land (ha.) | 0 | (c)Government Land (ha.) | 0 | (d)Revenue Land (ha.) | 0 | (e)Other Land (ha.) | 0.2351 | Total Land (ha.) | 0.2351 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 0.01623 | (b)Waste/Barren Land (ha.) | 0.004097 | (c)Grazing/ Community Land (ha.) | 0 | (d)Surface Water Bodies (ha.) | 0.002787 | (e)Settlements (ha.) | 0.001669 | (f)Industrial (ha.) | 0 | (g)Forest (ha.) | 0.002219 | (h)Mangroves (ha.) | 0 | (i)Marine Area (ha.) | 0 | (j)Others (ha.) : Range land | 0.004473 | Total (ha.) | 0.031475 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Green belt | | 0.05 | | (2.) | Others | Misc | 0.107125 | open area | (3.) | Main Plant | | 0.078 | production area | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Critically Polluted Area | NA | 0 | NA | (2.) | WLS | Dadra & Nagar Haveli WLS | 13.3 | Direction: SW | (3.) | ESAs | NA | 0 | NA | (4.) | Corridors | NA | 0 | NA | (5.) | NPA | NA | 0 | NA | (6.) | ESZs | NA | 0 | NA | (7.) | Wildlife Corridors | NA | 0 | NA | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Forest | | NA | 0 | NA | (2.) | Archaeological Sites | | Moti Mahal Fortwalls | 13.5 | Direction: N | (3.) | Defence Installations | | NA | 0 | NA | (4.) | Others | None | NA | 0 | NA | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
25. | Tree Cutting: | (a)No. of Trees Cut for the Project (if Forest Land not Involved) | 00 | (b)Details of Tree Cutting and Planting of Trees | Not Applicable | |
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 0.235125 | (b)Land yet to be acquired(Ha) | 0 | (c)Status of Land acquisition if not acquired | NA | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 0 | (b)No. of Households | 0 | (c)No. of PDFs (Project Displaced Families) | 0 | (d)No. of PAFs (Project Affected Families) | 0 | (e)Funds Allocated for R&R(in INR) (in Lacs) | 0 | (f)Status of R&R | Completed | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | No | (b)Whether conservation plan for Schedule-I Species has been prepared ? | No | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | No | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | Yes | (i)Details of Water Bodies in Buffer Area | River Daman Ganga | (ii)Direction of Water Bodies in Buffer Area | West | (iii)Distance of Water Bodies in Buffer Area | 7.6 | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 30 | (b)Permanent Employment-During Operation | 15 | (c)Temporary Employment- During Construction | 20 | (d)Temporary Employment- During Operation | 10 | (e)No. of working days | 300 | (f)Total Manpower | 75 | |
|
32. | Green Belt in Ha: | (a)Total Area of Green Belt | 0.05 | (b)Percentage of Total Project Area | 21.27 | (c)No. of Plants to be Planted | 125 | (d)Funds Allocated for Plantation | 50 | (e)Uploaded Green Belt plan | Copy of Green Belt Plan | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Social | • The proposed project will provide potential growth opportunity for the on-going business of the company.
• Local market is also showing strong growth potential.
• It will increase the demand of local employment.
• The company will employ about 75 people to fulfill its need to handle the plant.
• Local people will get some contracts of supply and services to get indirect income.
• Company will contribute in improving education and health facilities in nearby area. | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details : NOT APPLICABLE |
35. Sector Specific Details For Industrial Projects - 2 |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | NABET/EIA/1720/ RA 051 | (ii)Name of the EIA Consultant | Eco Chem Sales and Services | (iii)Address | Office floor, Ashoka Pavilion ’A’ New Civil Road, Surat, 395001 | (iv)Mobile No. | 9825123805 | (v)Landline No. | 261223163 | (vi)Email Id | eco@ecoshripad.com | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | Industrial Projects - 2 | (ix)Validity of Accreditation | 29 Feb 2020 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought: |
---|
Sno. | EDS Letter | Remarks | Date of EDS |
---|
1. | NA | Please inform/clarify the following:-
- Whether the proposed products namely, Aluminium Phosphide, Zinc Phosphide and Magnesium Phosphide, shall be used only as technically grade pesticides. The same needs to be confirmed along with the supporting documents.
- Notification status for GIDC Sarigam showing the project site.
- Applicability of the CRZ Notification, 2018.
- | 26 Jan 2019 | 2. | NA | The correction have been made as per the instruction received | 07 Feb 2019 | 3. | NA | In continuation to our earlier observations and your reply thereto, please inform/clarify the following:-
- Proposed products, whether technical grade pesticides. The same has not been clarified.
- Proposed products are reflected as raw materials also.
- Applicability of the EIA Notification, 2006 for the by-products and formulation products. | 15 Feb 2019 | 4. | NA | The correction have been made as per the instruction received | 18 Feb 2019 | 5. | NA | In view of formulation products and by-product not covered under the domain of the EIA Notification, 2006, the products details against column 8.2 of Form-2 needs to be corrected accordingly. | 02 Mar 2019 | 6. | NA | The correction have been made as per the instruction received | 08 Mar 2019 | |
Additional Detail Sought: |
---|
Sno. | ADS Letter | Remarks | Date of ADS |
---|
1. | ADS Reply Letter | Consequences Analysis Studies Report is attached as Annexure II. | 30 Jul 2019 | 2. | NA | Deferred | 17 May 2019 | |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | Bhargav Desai | Designation | Director | Name of Company (Applicant Name should not be given here) | INTEGRATED CHEMISOL PVT LTD | Address | Plot No.4924,Notified industrial area,GIDC Sarigam,Ta:Umbergaon |
|