Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Proposed 125 KLPD Grain based Distillery, 25KLPD Malt Spirit Plant and 4.5 MW Cogeneration Power Plant at Village Chiraura, Tehsil Akbarpur, District Kanpur Dehat, Uttar Pradesh
(b)Name of the Company / Organisation RAJASTHAN LIQUORS LIMITED
(c)Registered Address First Floor, 7/22D, Tilak Nagar, Kanpur (UP),,Kanpur Nagar,Uttar Pradesh-208002
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Ashutosh Tripathi
(b)Designation (Owner/ Partner/ CEO) CS
(c)Address First Floor, 7/22D, Tilak Nagar, Kanpur,,Kanpur,Kanpur Nagar,Uttar Pradesh-208002
(d)Pin code 208002
(e)E-mail csashutoshtripathi@gmail.com
(f)STD Code. 512(f)Telephone No. 3291280
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(g) Distilleries
Minor Activity
(b)Category A
(c)Proposal Number IA/UP/IND2/91819/2018
(d)Master Proposal Number(Single Window) SW/91812/2019
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. 774, 802, 777, 794, 795, 792, 793, 1034, 799, 801,
(b)Pincode 209304
(c)Bounded Latitudes (North)
From
Degree 26.41861111
Minutes
Second
From
Degree 26.4222222
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 80.1036111
Minutes
Second
From
Degree 80.10750000
Minutes
Second
(e)Survey of India Topo Sheet No. G44I/3, G44I/2
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 130
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 1.5
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Uttar Pradesh
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number J-11011/58/2018-IA-II(I)
(b)Date of Apply of TOR 16 Feb 2018
(c)Date of Issue of TOR / Standard ToR 24 Mar 2018
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :13 Oct 2018
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :14 Nov 2018
Distance of Public Hearing Venue from the Proposed Project :0
Project Site
State :Uttar Pradesh
District :Kanpur Dehat
Tehsil :Akbarpur
Village :Chiraura
175Construction of roads, storm water drainage system, benefits to farmers and EmploymentDistrict Magistrate
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Grain based Distillery125KLPD
(2.)Malt Spirit Plant25KLPD
(3.)Co-generation Power Plant4.5MW
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Extra Neutral Alcohol (ENA)125Kilo Litre per DayRoad
(2.)IMFL/CL Bottling Plant12000OthersCases per dayRoad
(3.)By Product DDGS73OthersTPDRoad
(4.)Malt Spirit25Kilo Litre per DayRoad
(5.)By Product CO2100OthersTPDRoad
(6.)Power4.5Mega Watt(MW)OthersThrough cables
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 175
(b) Funds Allocated for Environment Management (Capital) (in Crores) 20
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 2.6
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 1.45
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 127050
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 127050
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Barley for malting20300Tons per AnnumMalt SuppliersRoad500 MoUCopy of Linkage
(2.)Grains – Maize, jowar, broken rice106750Tons per AnnumGrain SuppliersRoad500 MoUCopy of Linkage
(3.)Boiler Fuel Biomass - Rice Husk87500Tons per AnnumLocal VendorsRoad500 OthersLocal VendorsCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Mar 2018 To 31 May 2018
(b)Season Summer
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube93.960.393.48100
(2.)PM2.5Micro Gram per Meter Cube51.925.951.660
(3.)NOxMicro Gram per Meter Cube25.212.024.7280
(4.)SO2Micro Gram per Meter Cube16.96.016.3980
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)Chloridesmg/l142.9326.952501000
(2.)pHNA8.187.596.58.5
(3.)TSSmg/l0000
(4.)Total Hardnessmg/l410.04124.44200600
(5.)Fluoridemg/l1.270.1911.5
(6.)TDSmg/l12124485002000
    14.3.     No. of Surface Water monitoring locations : 2
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA7.517.21E
(2.)DOmg/l5.605.40C
(3.)CODmg/l15.6011.02E
(4.)BODmg/l4.503.68E
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))64.552.5Industrial area - 75 & Residential area - 55
(2.)Leq(Night)A-weighted decibels(dB(A))53.242.1Industrial area - 70 & Residential Area - 45
    14.5.     No. of Soil Sample Monitored locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)N(Nitrogen)Kilogram per hectare137.9372.11
(2.)Electric ConductivityMillisiemens per Centimetre0.730.21
(3.)P(Phosphorus)Kilogram per hectare141.0446.71
(4.)K(Potassium)Kilogram per hectare120.3415.25
(5.)pH8.127.38
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 6.4 To 8.6
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 4 To 6
(c)Whether Ground Water Intersection will be there ? NA
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater13540Copy of Permission LetterPipelineTube WellApplication no -21-4/6607/UP/IND/201813 Dec 20181354
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Industrial waste water treated in CPU549600aerobic treatment, anaerobic treatment, filtration System and RO plantReuse within the Plant & Recycling549
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 549
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 549
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Fly AshFly Ash28000Tons50RoadOthersSupplied to Brick manufacturers
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube84.501084.78100
(2.)NOxMicrogram per Meter Cube20.801024.2780
(3.)PM2.5Microgram per Meter Cube43.41043.6860
(4.)SO2Microgram per Meter Cube12.301015.0880
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)Boiler 40 TPHRice Husk /Coal551.4PM1050
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 3750
(b)Source 4.5 MW Co-generation Power Plant
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 2x1000 KVA
(e)Stack Height (in m) 9
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 7.3520
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 7.3520
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 28464.07
(b)Waste/Barren Land (ha.) 952.44
(c)Grazing/ Community Land (ha.) 836.13
(d)Surface Water Bodies (ha.) 346.59
(e)Settlements (ha.) 882.35
(f)Industrial (ha.) 692.85
(g)Forest (ha.) 482.88
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : NA 0
    Total (ha.) 32657.309999999998
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Main Plant3.92
(2.)Green belt2.42
(3.)OthersParking area and open area1.01
Total (ha.) 7.35
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNot Applicable0No CPA within 10 km radius
(2.)ESAsNot Applicable0No ESAs within 10 km radius
(3.)ESZsNot Applicable0No ESZs within 10 km radius
(4.)NPANot Applicable0No NPA within 10 km radius
(5.)CorridorsNot Applicable0No Corridors within 10 km radius
(6.)Wildlife CorridorsNot Applicable0No Corridors within 10 km radius
(7.)WLSNot Applicable0No WLS within 10 km radius
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestNot Applicable0No Forest within 10 km radius
(2.)Archaeological SitesNot Applicable0No Archaeological sites within 10 km radius
(3.)Defence InstallationsNot Applicable0No Defence installation within 10 km radius
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 7.35
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired Already acquired by Company
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Rind Nadi
(ii)Direction of Water Bodies in Buffer Area South West
(iii)Distance of Water Bodies in Buffer Area 1.5
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 15
(b)Permanent Employment-During Operation 90
(c)Temporary Employment- During Construction 120
(d)Temporary Employment- During Operation 360
(e)No. of working days 350
(f)Total Manpower 585
32.
Green Belt in Ha:
(a)Total Area of Green Belt 2.42
(b)Percentage of Total Project Area 32.92
(c)No. of Plants to be Planted 3630
(d)Funds Allocated for Plantation 5000000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialEmployment generation and CSR Activities
(2.)EnvironmentalZero Liquid Discharge Project and Greenbelt development
(3.)FinancialRevenue generation
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1619/RA 0069
(ii)Name of the EIA Consultant J.M. EnviroNet Pvt. Ltd.
(iii)Address 202-A, ABW Tower, MG Road, IFFCO Chowk, Sector 25, Gurugram (Haryana) – 122001
(iv)Mobile No. 9015209362
(v)Landline No. 9015209362
(vi)Email Id jmenviron@hotmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 18 May 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAPlease inform/clarify the following:- - Whether the proposed distillery/industrial unit is in conformity with permitted land use of the area. The same needs to be confirmed along with supporting documents. - Out of total area 7.35 ha, an area of 2.13 ha is under agricultural use. What is the status of its acquisition. - Application submitted to CGWB for ground water withdrawal of 1354 cum/day along with the present status. 26 Jan 2019
2.NAThe correction have been made as per the instruction received 08 Mar 2019
3.NATo consider the proposal, there has to be substantive progress in respect of change of land use of 2.13 ha from agricultural to industrial, and the permission from CGWA for ground water withdrawal of 1354 cum/day (presently under verification stage). 24 Mar 2019
4.NAThe correction have been made as per the instruction received 29 Mar 2019
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterADS Reply attached. We request your good self to kindly consider our proposal for further proceedings. 04 Jun 2019
2.NA

Deferred

17 May 2019
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantAshutosh Tripathi
DesignationCS
Name of Company (Applicant Name should not be given here)RAJASTHAN LIQUORS LIMITED
AddressFirst Floor, 7/22D, Tilak Nagar, Kanpur (UP)