1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | Marki-Mangli Coal Block-III mine | (b)Name of the Company / Organisation | B S ISPAT LIMITED | (c)Registered Address | Kh. No. 97, 101, 190, Village Salori Yensa, Post Chinor, Taluka Warora, District Chandrapur, M.S.,,Chandrapur,Maharashtra-442914 | (d)Legal Status of the Company | Private | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | Bhawani Prasad Mishra | (b)Designation (Owner/ Partner/ CEO) | ManagingDirector | (c)Address | Khasra No. 97, 101, 190, Village Salori Yensa, Post Chinora, Taluka Warora, District Chandrapur, M.S.,,Warora,Chandrapur,Maharashtra-442914 | (d)Pin code | 442914 | (e)E-mail | bp.misra@bsilindia.com | (f)STD Code. | 22(f)Telephone No. | 39167386 | (g)Fax No. | | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 1(a) Mining of minerals
| Minor Activity | 1(a) Mining of minerals
| (b)Category | A | (c)Proposal Number | IA/MH/CMIN/31533/2015 | (d)Master Proposal Number(Single Window) | SW/91479/2019 | (e)EAC concerned (for category A Projects only) | Coal Mining | (f)Project Type | Fresh EC |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | List attached | (b)Pincode | 445304 | (c)Bounded Latitudes (North) | | From | | Degree | 19.799766 | Minutes | | Second | | From | | Degree | 19.830188 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 78.782123 | Minutes | | Second | | From | | Degree | 78.844844 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | 56 I/13 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 226 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 5 | (j)Seismic Zone | 2 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Maharashtra | |
|
|
Details of State(s) of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
(1.) | Maharashtra | Yavatmal | Zari-Jamani | | (2.) | Maharashtra | Yavatmal | Zari-Jamani | | |
|
6. | Details of Terms of Reference (ToR): | (a)MoEF&CC / SEIAA File Number | J-11015/425/2007-IA-II(M) | (b)Date of Apply of TOR | 06 Oct 2015 | (c)Date of Issue of TOR / Standard ToR | 01 Feb 2016 | (d)Previous TOR Letter | Copy of Previous TOR letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | No | (b)Whether details of Public Hearing available? | Yes | (c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above | Yes | |
|
7.1. Details of Public Hearing |
---|
|
S. No. | Details of Advertisement | Details of Public Hearing | Venue | Location Details | No. of People Attended | Issues Raised | Designation of Presiding Officer | Other Designation of Presiding Officer |
---|
(1.) | | Copy of Public Hearing : | Copy of Public Hearing | Date : | 03 Nov 2018 | Distance of Public Hearing Venue from the Proposed Project : | 0 |
| Project Site | State : | Maharashtra | District : | Yavatmal | Tehsil : | Zari-Jamani | Village : | Mukutban |
| 600 | Pollution control measures, Employment, Cost of the land etc. | Others | Additional District Magistrate | |
8. | Details of Project Configuration/Product: | |
|
8.1. Project Configuration |
---|
S. No. | Plant/Equipment/Facility | Configuration | Remarks |
---|
(1.) | Explosive magazine | 5 tonne | As per aproved MP | (2.) | Mining project with necessary site services | - | As per approved Mining Plan | |
8.2. Product |
---|
S. No. | Product/Activity (Capacity/Area) | Quantity | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | Coal Mining (275 Ha ML and 07 Ha for road / nala diversion) | 210000 | Tons per Annum | | Road | | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | Details Not Applicable | |
|
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | N/A | (iv)Valid Upto | N/A | (v)File No. | NA | (vi)Application No. | NA | (vii)Copy of Consent to operate valid as on date | NA | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 147.1 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 8.46 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 2.942 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 0.45 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | No | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 144 | (b)Existing quantity of raw material/fuel | N/A | (c)Total quantity of raw material/fuel | 144 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | Diesel | 4320 | Others | kiloliter per annum | Nearby fuel station | Road | | 3 | Others | Purchase as per requirement | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 06 Mar 2016 To 03 Jun 2016 | (b)Season | Summer | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 9 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | PM10 | | Micro Gram per Meter Cube | 54.7 | 42.2 | 54.3 | 100 | (2.) | NOx | | Micro Gram per Meter Cube | 25.9 | 16.7 | 25.9 | 100 | (3.) | PM2.5 | | Micro Gram per Meter Cube | 29.7 | 19.5 | 29.4 | 60 | (4.) | SO2 | | Micro Gram per Meter Cube | 19.4 | 12.4 | 18.5 | 100 | |
14.2. No. of Ground Water monitoring locations : 5 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | pH | | | NA | | 8.3 | 7.2 | 6.5 | 8.5 | (2.) | Total Hardness | | | mg/l | | 376 | 320 | 200 | 600 | (3.) | Chlorides | | | mg/l | | 129 | 59.6 | 250 | 1000 | (4.) | Fluoride | | | mg/l | | 1 | 0.2 | 1 | 1.5 | (5.) | Heavy Metals | | Arsenic | mg/l | | 0 | 0 | 0.01 | 0.05 | (6.) | TDS | | | mg/l | | 991 | 596 | 500 | 2000 | (7.) | TSS | | | mg/l | | 4 | 1 | 0 | 0 | |
14.3. No. of Surface Water monitoring locations : 6 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | DO | | mg/l | | 6.5 | 6.4 | C | (2.) | BOD | | mg/l | | 7.3 | 7.0 | C | (3.) | pH | | NA | | 8.5 | 7.9 | C | (4.) | COD | | mg/l | | 27 | 13 | C | |
14.4. No. of Ambient Noise monitoring locations : 9 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Day) | A-weighted decibels(dB(A)) | 53.8 | 41.7 | 55 | (2.) | Leq(Night) | A-weighted decibels(dB(A)) | 47.7 | 38.8 | 45 | |
14.5. No. of Soil Sample Monitored locations : 3 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | P(Phosphorus) | Kilogram per hectare | | 124.7 | 29.5 | (2.) | Electric Conductivity | Others | Micro-second per cm | 200 | 75 | (3.) | K(Potassium) | Kilogram per hectare | | 266.5 | 122.5 | (4.) | pH | | | 8.25 | 7.96 | (5.) | N(Nitrogen) | Kilogram per hectare | | 793.3 | 326.7 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 15.1 To 4.4 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 0.5 To 10.6 | (c)Whether Ground Water Intersection will be there ? | Yes | (d)Upload Copy of Central Ground Water Authority Letter | Copy of Central Ground Water Authority Letter | (e)Letter No. | NOC awaited hence copy of application attached | (f)Date of Issue | 20 Jun 2016 | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | GroundWater | | 2678 | 0.5 | Copy of Permission Letter | Pipeline | | Others | Mine water & Tubewell water | NOC awaited hence copy of application attached | 20 Jun 2016 | 2678 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | Domestic Water | 10 | 15 | STP | Green Belt Renewal Plant | | 10 | | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 10 | (b)Total Discharged Water (Kilolitre per Day) | 0 | (c)Total Reused Water (Kilolitre per Day) | 10 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Overburden | Others | Overburden | 2239111 | Tons | 1 | Road | | Others | Concurrent backfilling | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | PM10 | | Microgram per Meter Cube | 54.1 | 2 | 1.41 | 56.11 | 100 | (2.) | PM2.5 | | Microgram per Meter Cube | 29.7 | 2 | 0.09 | 29.8 | 60 | (3.) | SO2 | | Microgram per Meter Cube | 19.4 | 0.1 | 0.02 | 19.42 | 80 | (4.) | NOx | | Microgram per Meter Cube | 25.9 | 0.1 | 0.04 | 25.94 | 80 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | NA | NA | 0 | 0 | Others | NA | NA | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 100 | (b)Source | MSEGCL | (c)Uploaded Copy of Agreement | Copy of Agreement | (d)Standby Arrangement (Details of DG Sets) | 1 | (e)Stack Height (in m) | 0 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 0 | (b)Private Land (ha.) | 262.5 | (c)Government Land (ha.) | 19.5 | (d)Revenue Land (ha.) | 0 | (e)Other Land (ha.) | 0 | Total Land (ha.) | 282 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 90 | (b)Waste/Barren Land (ha.) | 19.5 | (c)Grazing/ Community Land (ha.) | 0 | (d)Surface Water Bodies (ha.) | 0 | (e)Settlements (ha.) | 10 | (f)Industrial (ha.) | 0 | (g)Forest (ha.) | 0 | (h)Mangroves (ha.) | 0 | (i)Marine Area (ha.) | 0 | (j)Others (ha.) : Private land | 162.5 | Total (ha.) | 282 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Main Plant | | 0 | - | (2.) | Township | | 0 | - | (3.) | Ash Pond | | 0 | - | (4.) | OB Dump Area | | 20 | 13 Ha for external dump and 7 Ha for soil dump | (5.) | Safety Zone | | 7 | - | (6.) | Tailing Pond | | 0 | - | (7.) | Desalination Plant | | 0 | - | (8.) | Built Up Area | | 15.5 | - | (9.) | Quarry Area | | 128 | 59 Ha Void and 69 Ha back filled | (10.) | Green belt | | 111.5 | By rounding off in available format | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Critically Polluted Area | none | 0 | Not within 15 Km radius | (2.) | NPA | none | 0 | Not within 15 Km radius | (3.) | ESAs | none | 0 | Not within 15 Km radius | (4.) | ESZs | none | 0 | Not within 15 Km radius | (5.) | Wildlife Corridors | none | 0 | Not within 15 Km radius | (6.) | WLS | Tipeshwar wildlife sanctuary | 30 | more than 15 km radius | (7.) | Corridors | none | 0 | Not within 15 Km radius | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Archaeological Sites | | None | 0 | Not within 15 Km radius | (2.) | Others | Interstate Boundary | Maharashtra Telangana Border | 6 | Maharashtra Telangana Border | (3.) | Defence Installations | | None | 0 | Not within 15 Km radius | (4.) | Forest | | Reserved forest | 0.5 | Besides this there are 7 RF within buffer zone | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
25. | Tree Cutting: | (a)No. of Trees Cut for the Project (if Forest Land not Involved) | Not Applicable | (b)Details of Tree Cutting and Planting of Trees | Not Applicable | |
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 62.42 | (b)Land yet to be acquired(Ha) | 219.58 | (c)Status of Land acquisition if not acquired | Under process | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 0 | (b)No. of Households | 0 | (c)No. of PDFs (Project Displaced Families) | 0 | (d)No. of PAFs (Project Affected Families) | 0 | (e)Funds Allocated for R&R(in INR) (in Lacs) | 0 | (f)Status of R&R | Yet To Start | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | Yes | (i)Details of Schedule-I Species | Peacock, Panther, Slothbear | (b)Whether conservation plan for Schedule-I Species has been prepared ? | No | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | Yes | (i)Details of Water Bodies in Core Area | Water logged mined out pit will be reclaimed and seasonal nala | (b)Whether there is Diversion Required ? | Yes | (i)Details of Diversion Required | Seasonal nala | (ii)Details of Study Conducted | Yes | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | Yes | (i)Details of Water Bodies in Buffer Area | Penganga River | (ii)Direction of Water Bodies in Buffer Area | South | (iii)Distance of Water Bodies in Buffer Area | 5 | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 0 | (b)Permanent Employment-During Operation | 288 | (c)Temporary Employment- During Construction | 0 | (d)Temporary Employment- During Operation | 0 | (e)No. of working days | 300 | (f)Total Manpower | 288 | |
|
32. | Green Belt in Ha: | (a)Total Area of Green Belt | 204 | (b)Percentage of Total Project Area | 72.34 | (c)No. of Plants to be Planted | 408000 | (d)Funds Allocated for Plantation | 17500000 | (e)Uploaded Green Belt plan | Copy of Green Belt Plan | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Environmental | Improving green belt, backfilling of existing pit /OB and its reclaimation. | (2.) | Social | Direct employment to 288 eligible persons preferable local persons besides creating indirect employment opportunities.
Various CSR/CER activities in adjoining villages will help in improving social status. | (3.) | Financial | Capital cost of 147.10 crores improves 8.46 Cr for environmental protection, 0.9087 Cr as capital cost of CSR activities and 0.136 Cr as recurring CSR cost.
The project will contribute to state through various taxes. | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details For Coal Mining |
|
1. No. of Mineral(s) to be Mined : 1 |
---|
S. No. | Mineral(s) to be Mined | Major or Minor Mineral |
---|
(1.) | Coal | Major | |
|
2. | Mine Capacity in ROM (Run of Mine) | 210000 | |
|
|
4. | Mining Plan: | (a)Approval Letter No. | CPAM – 34011/38/2017 | (b)Date of Approval | 10 Apr 2018 | (c)Approved Letter | Copy of Approved Letter | (d)Approved By State Mining and Geology Department | Coal | (e)Approved Mining Lease Area | 275 | (f)Approved Capacity | 210000 | |
|
5. | Technical Details: | (a)Total Geological Reserves (Million Ton) | 6.19 | (b)Mineable Reserves (Million Ton) | 4.42 | (c)Extractable Reserves(Million Ton) | 3.65 | (d)Percent(%) of Extraction | 58.96 | (e)Grade of Coal /Ore /Mineral | D to E | (f)Stripping Ratio | 1 : 6.9 | (g)Category of Gaseousness (Only for Coal Mining, Others may Write NA) | Non gaseous | (h)Average Gradient(Degree) | 7.5 to 8 | (i)Mining Method | Opencast | (j)Life of Mine (Years) | 18 | |
|
6. | Details of Beneficiations: | (a)Whether it is proposed to install beneficiation plant/Coal washery within the mining lease area | No | (b)Whether it is proposed to install crusher within the mining lease area | No | |
|
7. | Details of Seams: | (a)Whether details of seam applicable | Yes | (b)No. of seams | 1 | (c)Thickness of seams to be worked on | 3.05 | (d)Maximum Thickness of Seams (metres) | 5.1 | |
|
8. | Details of Mining Lease: | (a)Mining Lease Area (in Hectare) | 275 | (b)Whether obtained Letter of Intent (LOI) from the state government ? | Yes | (i)Copy of Letter of Intent | Copy of Letter of Intent | (ii)Date of issue of LOI | 23 Sep 2015 | (iii)Validity of LOI | 20 | (iv)Reference No. of LOI | MMN-0615/C.R.62/IND-9 | (c)Whether Lease Deed Executed ? | No | (i)Reason thereof | Environment Clearance awaited | (d)Whether Lease Deed Renewed ? | No | (i)Reason thereof | Lease yet to be executed | |
|
9. | OB (Over Burden) Management: | (a) Details of External Dumps: | (i)No. of OB Dumps | | (ii)Total Area (in Hectare) | | (iii)Height (in meter) | | (iv)Quantity (in Million Cubic meter) | | (v)No. of year back fill up | | (b) Details of Internal Dumps: | (i)No. of Internal Dumps | | (ii)Total Area (in Hectare) | | (iii)Height (in meter) | | (iv)Quantity (in Million Cubic meter) | | |
|
10. | Details of Topsoil Management: | (a)Quantity of Topsoil excavated during the entire life of the mine (in Million Cubic metre) | 3 | (b)Quantity of Topsoil proposed for utilization for reclamation during the entire life of the mine (in Million Cubic metre) | 3 | (c)Quantity of Topsoil proposed for utilization for other activities during the entire life of the mine (in Million Cubic metre) | 0 | |
|
11. | Details of Final Mine Void: | (a)Area (in Hectare) | | (b)Depth (in meter) | | (c)Volume (in Million Cubic meter) | | |
|
12. | Details of Quarry: | (a)Final Void of 59 (hectare) at a Depth of 60 meter which is Proposed to be Converted into a Water Body. | (b)Total Quarry Area (ha) | 128 | |
|
13. | Details of Transportation: | (a)In Pit/Underground to Surface | Haul road | (b)Surface to Siding/Loading | Road transport | (c)Transportation / Conveyor Details | Road transport | |
|
|
14. Details of Land Usage (Pre-Mining) |
---|
S. No. | LAND USE | Other LAND USE | WITHIN ML AREA (Hectare) | OUTSIDE ML AREA (Hectare) | TOTAL (Hectare) |
---|
(1.) | FOREST LAND | | 0 | 0 | 0 | (2.) | GRAZING LAND | | 0 | 0 | 0 | (3.) | OTHERS(Specify) | Excavated, Infrastructure, Dumps, Undisturbed | 162.5 | 0 | 162.5 | (4.) | AGRICULTURE LAND | | 90 | 0 | 90 | (5.) | WASTE LAND | | 19.5 | 0 | 19.5 | (6.) | SURFACE WATER BODIES | | 0 | 0 | 0 | (7.) | SETTLEMENTS | | 10 | 0 | 10 | |
TOTAL | 282 | 0 | 282 | |
|
15. Details of Land Usage (Post-Mining) |
---|
S. No. | LAND USE | Other LAND USE | Plantation (ha) | Water Body (ha) | Public Use (ha) | Undisturbed (ha) | Total |
---|
(1.) | EXCAVATION/QUARRY | | 69 | 59 | 0 | | 128 | (2.) | TOP SOIL STORAGE | | 7 | 0 | 0 | | 7 | (3.) | INTERNAL OB DUMPS | | 69 | 0 | 0 | | 69 | (4.) | BUILT UP AREA (COLONY/OFFICE) | | 0 | 0 | 0 | | 0 | (5.) | Other | Infrastructure and Populated area | 11 | 0 | 14 | | 25 | (6.) | VIRGIN AREA | | 0 | 0 | 0 | | 0 | (7.) | ROADS | | 0 | 0 | 5 | | 5 | (8.) | GREEN BELT | | 35 | 0 | 0 | | 35 | (9.) | EXTERNAL OB DUMPS | | 13 | 0 | 0 | | 13 | |
TOTAL | 204 | 59 | 19 | 0 | 282 | |
16. | Details of Reclamation: | Total Afforestation Plan shall be Implemented Covering of Mining.This will Include: | (a)External OB Dump(in hectare) | 20 | (b)Internal Dump(in hectare) | 69 | (c)Quarry(in hectare) | 128 | (d)Safety Zone(in hectare) | 7 | (e)Final Void of 59 (hectare) at a Depth of 60 meter which is Proposed to be Converted into a Water Body. | (f)Density of Tree Plantation per ha (in no.) | 2000 | (g)Others in ha (such as Excavation Area along ML Boundary, along Roads and Infrastructure, Embankment Area and in Township Located Outside the Lease etc) | 19 | (h)Total afforestation plant (in hectare) | 204 | |
|
17. | Status of progressive Mining Closure Plan: | Details Not Applicable | |
|
18. Details of Actual Coal/ ORE Production vis-a-vis Sanctioned Capacity since the Inception: |
---|
S. No. | Financial Year | Sanctioned Capacity as per EC (MTPA) | Sanctioned Capacity as per CTO | Sanctioned Capacity as per approved mining plan | Actual Production | Excess Production Beyond the EC / CTO/ Mining Plan Sanctioned Capacity (MTPA) |
---|
(1.) | 2019 | 0 | 0 | 0 | 0 | 0 | |
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | NABET/EIA/1720/RA 0105 | (ii)Name of the EIA Consultant | Srushri Seva Private Limited | (iii)Address | Harihar Niwas, Giripeth, Near Adiwasi Bhavan, Nagpur | (iv)Mobile No. | 9422108095 | (v)Landline No. | 2542426 | (vi)Email Id | srspl15@gmail.com | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | Coal Mining | (ix)Validity of Accreditation | 15 May 2020 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought : NIL |
Additional Detail Sought : NIL |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | Bhawani Prasad Mishra | Designation | ManagingDirector | Name of Company (Applicant Name should not be given here) | B S ISPAT LIMITED | Address | Kh. No. 97, 101, 190, Village Salori Yensa, Post Chinor, Taluka Warora, District Chandrapur, M.S. |
|