1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | Balmukund Sponge and Iron Pvt. Ltd. (Mega Div.) | (b)Name of the Company / Organisation | BALMUKUND SPONGE AND IRON PRIVATE LIMITED | (c)Registered Address | Village: Manjhiladih, P.O. Gadisrirampur, District: Giridih, Jharkhand,,Giridih,Jharkhand-815302 | (d)Legal Status of the Company | Private | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | Prem Prasad Verma | (b)Designation (Owner/ Partner/ CEO) | Manager | (c)Address | Balmukund Sponge and Iron Private Limited. At: Bajrang Chok, Near Biswanath Nursing Home, Giridih, Jharkhand,815301,Giridih,Giridih,Jharkhand-815301 | (d)Pin code | 815301 | (e)E-mail | balmukundsponge2011@gmail.com | (f)STD Code. | 6532(f)Telephone No. | 250597 | (g)Fax No. | | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 3(a) Metallurgical industries (ferrous & non ferrous) 5(k) Induction/arc furnaces/cupola furnaces 5TPH or more
| Minor Activity | | (b)Category | A | (c)Proposal Number | IA/JH/IND/91108/2014 | (d)Master Proposal Number(Single Window) | SW/91092/2019 | (e)EAC concerned (for category A Projects only) | Industrial Projects - 1 | (f)Project Type | Modernization |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | Khata no.161,162 & Plot no.940, 941, 942, 943, 944 | (b)Pincode | 825322 | (c)Bounded Latitudes (North) | | From | | Degree | 24.117 | Minutes | | Second | | From | | Degree | 24.121 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 86.348 | Minutes | | Second | | From | | Degree | 86.352 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | 72L/8 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 295 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 1.3 | (j)Seismic Zone | 3 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Jharkhand | |
|
|
Details of State of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
NIL | |
|
6. | Details of Terms of Reference (ToR)/EC: | (a)MoEF&CC / SEIAA File Number | EC/SEIAA/2013-14/297/2014/1525 | (b)Date of Apply of TOR | 28 Apr 2014 | (c)Date of Issue of TOR / Standard ToR | 25 Jul 2014 | (d)Date of Apply of EC | 15 Mar 2015 | (e)Date of Issue of EC | 25 Aug 2015 | (f)Previous TOR Letter | Copy of Previous TOR letter | (g)Previous EC Letter | Copy of Previous EC letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | No | (b)Whether details of Public Hearing available? | Yes | (c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above | Yes | |
|
7.1. Details of Public Hearing |
---|
|
S. No. | Details of Advertisement | Details of Public Hearing | Venue | Location Details | No. of People Attended | Issues Raised | Designation of Presiding Officer | Other Designation of Presiding Officer |
---|
(1.) | | Copy of Public Hearing : | Copy of Public Hearing | Date : | 15 Dec 2018 | Distance of Public Hearing Venue from the Proposed Project : | 1.25 |
| Utkramit Madhya Vidyalaya, Kalhamanjho, Giridih | State : | Jharkhand | District : | Giridih | Tehsil : | Giridih | Village : | Kalhamanjho |
| 158 | Pollution Control
Borewell for irrigation
Construction and maintenance of road
Health facility | Others | Director, DRDO | |
8. | Details of Project Configuration/Product: | Details Not Applicable | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | (a)Details of certified report on compliance of earlier environmental clearance condition | (i)Certified Compliance By | Regional | (ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on | Ranchi | (iii)Letter No. | F. No.103/225/09/EPE/3094 | (iv)Status of Compliance | Partially Complied | (v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) | Copy of Certified Compliance Report | (vi)Date of site visit | Feb 20 2019 12:00AM | (b)Details of Capacity Expansion | |
|
S. No. | Product/Activity (Capacity/Area) | Quantity From | Quantity To | Total | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | Rolling Mill | 50 | 220 | 270 | Others | Tons/ day | Road | | |
| (c)Details of Configuration | |
|
S. No. | Plant / Equipment / Facility | Existing Configuration | Proposed Configuration | Final configuration after expansion | Remarks |
---|
(1.) | Induction Furnace | 21240 TPA Billet | -- | 21240 TPA | No expansion | (2.) | Mini Blast Furnace | 39000TPA | -- | 39000TPA | No expansion | (3.) | Iron ore beneficiation plant | 94000TPA (266TPD) | -- | 94000TPA (266TPD) | No expansion | (4.) | Rolling mill | 16000TPA (50TPD) | 86400TPA (270TPD) | 86400TPA (270TPD) | New Hot rolling mill replace existing oil firedmill | (5.) | Induction Furnace(SMS with CCM) | 102660TPA (290TPD) | -- | 102660TPA (290TPD) | No expansion | |
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | 13 Aug 2018 | (iv)Valid Upto | 30 Jun 2020 | (v)File No. | JSPCB/HO/RNC/CTO-2335595/2018/1314 | (vi)Application No. | JSPCB/HO/RNC/CTO-2335595/2018/1314 | (vii)Copy of Consent to operate valid as on date | Copy of Consent to Operate | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 14 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 0.65 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 0.35 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 0.17 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | No | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 89856 | (b)Existing quantity of raw material/fuel | N/A | (c)Total quantity of raw material/fuel | 89856 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | Scrap | 1300 | Tons per Annum | | From nearby industries in Jharkhand | Road | | 50 | Open Market | | Copy of Linkage | (2.) | Silico Manganese | 186 | Tons per Annum | | In House | Road | | 1 | Captive | | Copy of Linkage | (3.) | Coke | 150 | Tons per Annum | | From nearby industries in Jharkhand | Road | | 50 | Open Market | | Copy of Linkage | (4.) | Aluminium Shots | 30 | Tons per Annum | | From nearby industries in Jharkhand | Road | | 50 | Open Market | | Copy of Linkage | (5.) | Coke | 30700 | Tons per Annum | | Dhanbad & Ramgarh | Road | | 250 | Open Market | | Copy of Linkage | (6.) | Dolomite | 4435 | Tons per Annum | | Bhutan | Road,Rail | | 1000 | Open Market | | Copy of Linkage | (7.) | Quartz | 1535 | Tons per Annum | | Near by mines | Road | | 250 | Open Market | | Copy of Linkage | (8.) | Sponge Iron | 97400 | Tons per Annum | | From nearby industries in Jharkhand | Road | | 50 | Open Market | | Copy of Linkage | (9.) | MS Billets | 17000 | Tons per Annum | | In House | Road | | 1 | Open Market | | Copy of Linkage | (10.) | Pig Iron | 36055 | Tons per Annum | | In House | Road | | 1 | Captive | | Copy of Linkage | (11.) | Iron ore | 76725 | Tons per Annum | | Chaibasa Mines | Road | | 200 | Open Market | | Copy of Linkage | (12.) | Limestone | 3400 | Tons per Annum | | Near by mines | Road | | 250 | Open Market | | Copy of Linkage | (13.) | Petcoke | 1410 | Tons per Annum | | Chaibasa, Barajamda & Dhanbad | Road | | 250 | Open Market | | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 01 Mar 2018 To 31 May 2018 | (b)Season | Pre-Monsoon | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | PM10 | | Micro Gram per Meter Cube | 90.9 | 51.1 | 90.56 | 100 | (2.) | NOx | | Micro Gram per Meter Cube | 39.4 | 15.2 | 39 | 80 | (3.) | PM2.5 | | Micro Gram per Meter Cube | 53.1 | 19.9 | 53 | 60 | (4.) | SO2 | | Micro Gram per Meter Cube | 25.0 | 8.2 | 20.0 | 80 | (5.) | Others | CO | Micro Gram per Meter Cube | 597.7 | 214 | 319 | 4000 | |
14.2. No. of Ground Water monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | pH | | | NA | | 7.2 | 6.5 | 8.5 | 8.5 | (2.) | TSS | | | mg/l | | 0 | 0 | 0 | 0 | (3.) | Fluoride | | | mg/l | | 0.55 | 0.22 | 1.0 | 1.5 | (4.) | Heavy Metals | | Zn | mg/l | | 0.09 | 0.039 | 5 | 15 | (5.) | Chlorides | | | mg/l | | 36 | 12 | 250 | 1000 | (6.) | Total Hardness | | | mg/l | | 216 | 40 | 200 | 600 | (7.) | Others | Total Alkalinity | | mg/l | | 189 | 42 | 200 | 600 | (8.) | TDS | | | mg/l | | 350 | 130 | 500 | 2000 | |
14.3. No. of Surface Water monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | pH | | NA | | 7.6 | 6.6 | C | (2.) | DO | | mg/l | | 7.3 | 6.5 | C | (3.) | Others | Chloride | mg/l | | 36 | 6 | C | (4.) | COD | | mg/l | | 20 | 5 | C | (5.) | BOD | | mg/l | | 6 | 1 | C | |
14.4. No. of Ambient Noise monitoring locations : 8 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Day) | A-weighted decibels(dB(A)) | 72.3 | 50.2 | 75 | (2.) | Leq(Night) | A-weighted decibels(dB(A)) | 68.5 | 37.3 | 70 | |
14.5. No. of Soil Sample Monitored locations : 8 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | pH | | | 7.7 | 5.2 | (2.) | N(Nitrogen) | Kilogram per hectare | | 420 | 114 | (3.) | K(Potassium) | Kilogram per hectare | | 564 | 60 | (4.) | Electric Conductivity | Millisiemens per Centimetre | | 103 | 18.8 | (5.) | P(Phosphorus) | Kilogram per hectare | | 8.8 | 2.02 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 12 To 9 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 3 To 6 | (c)Whether Ground Water Intersection will be there ? | No | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | GroundWater | | 69 | 0.5 | Copy of Permission Letter | Pipeline | | Others | Borewell | 21-4(166)/MER/CGWA/2013-396 | 04 Mar 2014 | 120 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | MBF | 200 | 200 | Settling | Reuse within the Plant & Recycling | | 200 | | (2.) | Beneficiation Plant | 500 | 500 | Settling | Reuse within the Plant & Recycling | | 500 | | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 700 | (b)Total Discharged Water (Kilolitre per Day) | 0 | (c)Total Reused Water (Kilolitre per Day) | 700 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Pig Slag | Industrial Waste | | 77795 | Tons | 1 | Road | | Others | sold to cement plant | (2.) | Rolling mill end cutting | Industrial Waste | | 1560 | Tons | 1 | Road | | Co-Processing | | (3.) | Fines | Industrial Waste | | 20000 | Tons | 1 | Road | | Co-Processing | | (4.) | Induction furnace slag | Industrial Waste | | 4781 | Tons | 1 | Road | | Others | 8% recovered and land filling | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | PM10 | | Microgram per Meter Cube | 85.6 | 0.1 | 0.29 | 85.9 | 100 | (2.) | PM2.5 | | Microgram per Meter Cube | 35.8 | 0.1 | 0.2 | 36.2 | 60 | (3.) | NOx | | Microgram per Meter Cube | 33.8 | 0.1 | 0.43 | 34.3 | 80 | (4.) | SO2 | | Microgram per Meter Cube | 22.3 | 0.1 | 0.4 | 22.72 | 80 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | MBF | Coal/ Coke | 30 | 1.0 | PM10 | | 0.222 g/s | (2.) | Induction Furnace | Electricity | 29 | 0.6 | PM10 | | 0.083g/s | (3.) | Induction Furnace | Electricity | 29 | 0.6 | SO2 | | 0.016mg/Nm3 | (4.) | MBF | Coal/Coke | 30 | 1 | SO2 | | 0.069mg/Nm3 | (5.) | Induction Furnace | Electricity | 29 | 0.6 | NOx | | 0.052mg/Nm3 | (6.) | MBF | Coal/Coke | 30 | 1 | NOx | | 0.042 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 24720 | (b)Source | Damodar Valley Corporation | (c)Uploaded Copy of Agreement | Copy of Agreement | (d)Standby Arrangement (Details of DG Sets) | 350 KVA | (e)Stack Height (in m) | 3.0 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 0.0 | (b)Private Land (ha.) | 10.66 | (c)Government Land (ha.) | 0.0 | (d)Revenue Land (ha.) | 0.0 | (e)Other Land (ha.) | 0.0 | Total Land (ha.) | 10.66 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 0 | (b)Waste/Barren Land (ha.) | 0 | (c)Grazing/ Community Land (ha.) | 0.0 | (d)Surface Water Bodies (ha.) | 0.0 | (e)Settlements (ha.) | 0.0 | (f)Industrial (ha.) | 10.66 | (g)Forest (ha.) | 0.0 | (h)Mangroves (ha.) | 0.0 | (i)Marine Area (ha.) | 0.0 | (j)Others (ha.) : Nil | 0.0 | Total (ha.) | 10.66 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Main Plant | | 5.66 | | (2.) | Others | New Rolling Mill | 0.752 | | (3.) | Green belt | | 3.52 | | (4.) | Built Up Area | | 0.724 | | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | NPA | Nil | 0 | More than 10 Km from project site | (2.) | ESAs | Nil | 0 | More than 10 Km from project site | (3.) | WLS | Parashnath Wild Life Sanctuary | 25 | More than 10 Km from project site | (4.) | ESZs | Nil | 0 | More than 10 Km from project site | (5.) | Corridors | Nil | 0 | More than 10 Km from project site | (6.) | Critically Polluted Area | NA | 0 | More than 10 Km from project site | (7.) | Wildlife Corridors | Nil | 0 | More than 10 Km from project site | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Forest | | Gangapur Forest | 1.5 | Protected Forest | (2.) | Defence Installations | | Nil | 0 | No defence installation within 10 Km of the project site | (3.) | Archaeological Sites | | Ushri fall | 2.0 | Tourist place | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
25. | Tree Cutting: | (a)No. of Trees Cut for the Project (if Forest Land not Involved) | 0 | (b)Details of Tree Cutting and Planting of Trees | Not Applicable | |
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 10.66 | (b)Land yet to be acquired(Ha) | 0 | (c)Status of Land acquisition if not acquired | Land already acquired | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 0 | (b)No. of Households | 0 | (c)No. of PDFs (Project Displaced Families) | 0 | (d)No. of PAFs (Project Affected Families) | 0 | (e)Funds Allocated for R&R(in INR) (in Lacs) | 0 | (f)Status of R&R | Completed | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | No | (b)Whether conservation plan for Schedule-I Species has been prepared ? | No | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | No | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | Yes | (i)Details of Water Bodies in Buffer Area | Ushri River | (ii)Direction of Water Bodies in Buffer Area | East | (iii)Distance of Water Bodies in Buffer Area | 1.5 | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 0 | (b)Permanent Employment-During Operation | 89 | (c)Temporary Employment- During Construction | 0 | (d)Temporary Employment- During Operation | 0 | (e)No. of working days | 330 | (f)Total Manpower | 89 | |
|
|
S. No. | Description | Existing | Proposed | Total |
---|
(1.) | Total Area of Green Belt | 5.7 | 3.0 | 8.7 | (2.) | Percentage of Total Project Area | 22 | 11 | 33 | (3.) | No. of Plants | 10000 | 10000 | 20000 | (4.) | Funds Allocated | 5.0 | 5.0 | 10 | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Social | benefit direct and indirectly | (2.) | Environmental | Pollution control, water sprinkling, plantation | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details : NOT APPLICABLE |
35. Sector Specific Details For Industrial Projects - 1 |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | NABET/EIA/1619/RA0086 | (ii)Name of the EIA Consultant | Kalyani Laboratories Private Limited | (iii)Address | Plot No. 78/944, Millenium City, Pahala, Bhubaneswar | (iv)Mobile No. | 9437306091 | (v)Landline No. | 0674297405 | (vi)Email Id | kalyanilab@yahoo.co.in | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | Industrial Projects - 1 | (ix)Validity of Accreditation | 31 May 2019 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought: |
---|
Sno. | EDS Letter | Remarks | Date of EDS |
---|
1. | NA | i. Closure report on the observed non-compliances from Regional Office of the MoEF&CC shall be furnished.
ii. CGWA water abstraction permission is of 4.3.2014 and already expired on 3.3.2016. Renewed water abstraction permission may be furnished. Possibility to use surface water in place of Ground water may also be submitted. | 18 Jun 2019 | 2. | NA | The correction have been made as per the instruction received | 26 Aug 2019 | |
Additional Detail Sought : NIL |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | Prem Prasad Verma | Designation | Manager | Name of Company (Applicant Name should not be given here) | BALMUKUND SPONGE AND IRON PRIVATE LIMITED | Address | Village: Manjhiladih, P.O. Gadisrirampur, District: Giridih, Jharkhand |
|