Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) BPCL Jhansi-Augmentation of LPG Storage Capacity
(b)Name of the Company / Organisation BPCL JHANSI
(c)Registered Address Plot no. 5/6 sector 1, Noida,,Gautam Buddha Nagar,Uttar Pradesh-201301
(d)Legal Status of the Company Central PSU
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Nishant Kumar
(b)Designation (Owner/ Partner/ CEO) TM
(c)Address Village PO Ambabai, gwalier Road Jhansi UP,,Jhansi,Jhansi,Uttar Pradesh-284003
(d)Pin code 284003
(e)E-mail bpcljhansi2017@gmail.com
(f)STD Code. 141(f)Telephone No. 402915
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity6(b)Isolated storage & handling of hazardous chemicals (As per threshold planning
Minor Activity8(a) Building and Construction projects
(b)Category A
(c)Proposal Number IA/UP/IND2/69498/2017
(d)Master Proposal Number(Single Window) SW/90692/2019
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Bharat Petroleum Corp. Ltd, LPG Territory Office &
(b)Pincode 284003
(c)Bounded Latitudes (North)
From
Degree 253203
Minutes
Second
From
Degree 253220
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 783018
Minutes
Second
From
Degree 783032
Minutes
Second
(e)Survey of India Topo Sheet No. 54K/10
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 243
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 3.5
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Uttar Pradesh
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)Uttar PradeshJhansiJhansi
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number IA-J-11011/471/2017-IA-II(I)
(b)Date of Apply of TOR 16 Sep 2017
(c)Date of Issue of TOR / Standard ToR 26 Oct 2017
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :25 Oct 2018
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :28 Nov 2018
Distance of Public Hearing Venue from the Proposed Project :0.5
Elementary school, Pretampur, development block - Badgaon, Tehsil and Districtj Jhansi
State :Uttar Pradesh
District :Jhansi
Tehsil :Jhansi
Village :Ambabai
38Mainly following issues raised during Public Hearing:- 1. Will local villagers have any preference for available job opportunity? 2.In case of any onsite and offsite incident is there any provisionOthersAdditional District Magistrate (Administration),
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)LPG Storagemounded storage vessel450 MT to 1350 MT
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Mounded Storage Vessel1350OthersMTRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 14 Jan 2016
(iv)Valid Upto 31 Dec 2020
(v)File No. 5059/Air Pollution/16
(vi)Application No. NIL
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 26.11
(b) Funds Allocated for Environment Management (Capital) (in Crores) 0.12
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.2611
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.019
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? Yes
d)Inter-State boundaries and international boundaries Yes
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 00
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 0
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)70% Per Chloric Acid (Acid)00Tons per Annum00Road00 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Oct 2017 To 31 Dec 2017
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube89.365.0189.3100
(2.)PM2.5Micro Gram per Meter Cube55.935.155.660
(3.)NOxMicro Gram per Meter Cube29.917.129.980
(4.)OthersCOMili Gram per Meter Cube1.130.221.122
(5.)SO2Micro Gram per Meter Cube12.96.012.880
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TDSmg/l4984205002000
(2.)TSSmg/l00000000
(3.)Total Hardnessmg/l287230200600
(4.)Chloridesmg/l50.935.72501000
(5.)Fluoridemg/l000011.5
(6.)Heavy MetalsLeadmg/l00000.010.01
(7.)pHNA7.657.116.58.5
    14.3.     No. of Surface Water monitoring locations : 5
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA7.247.05A
(2.)DOmg/l6.25.9B
(3.)CODmg/l38.225.4C
(4.)BODmg/l6.45.2B
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))65.160.275
(2.)Leq(Night)A-weighted decibels(dB(A))48.942.370
    14.5.     No. of Soil Sample Monitored locations : 6
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pHOthersNA8.147.75
(2.)N(Nitrogen)Percent0.0930.084
(3.)P(Phosphorus)Milligram per Kilogram190.576.5
(4.)K(Potassium)Milligram per Kilogram340.7240.5
(5.)Electric ConductivityMillisiemens per Centimetre460.5320.9
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 15 To 5
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 16.07 To 2.47
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater1000 Not Appliacble PipelineTube WellNIL26 Jan 201710
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Cleaning & Washing0.85Physico-ChemicalGreen Belt Renewal Plant,OthersLandscape0.40.4
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 0.8
(b)Total Discharged Water (Kilolitre per Day) 0.4
(c)Total Reused Water (Kilolitre per Day) 0.4
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Solid WasteMunicipal Solid Waste8.2Tons00RoadOthersMunicipal Disposal
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube84.41.40.3784.77100
(2.)PM2.5Microgram per Meter Cube001400000000
(3.)SO2Microgram per Meter Cube10.91.40.01610.9280
(4.)NOxMicrogram per Meter Cube27.91.413.5841.4880
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)DG76 L/Hr.40.10PM100.021
(2.)DG76L/Hr.40.10SO20.069
(3.)DG76L/Hr.40.10NOx0.654
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 200
(b)Source DVVNL
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 380
(e)Stack Height (in m) 4
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 00
(b)Private Land (ha.) 00
(c)Government Land (ha.) 26
(d)Revenue Land (ha.) 00
(e)Other Land (ha.) 00
    Total Land (ha.) 26
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 10587.83
(b)Waste/Barren Land (ha.) 00
(c)Grazing/ Community Land (ha.) 00
(d)Surface Water Bodies (ha.) 1200.5
(e)Settlements (ha.) 1070.57
(f)Industrial (ha.) 00
(g)Forest (ha.) 3826.47
(h)Mangroves (ha.) 00
(i)Marine Area (ha.) 00
(j)Others (ha.) : Open Land & Fallow Land 14729.36
    Total (ha.) 31414.73
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Main Plant2.96Plant area, office area & All covered Area
(2.)Green belt3.56Landscape Area
(3.)OthersRoad & Paved Area4.0Road & Open area
Total (ha.) 10.52
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNone00None
(2.)NPANone00None
(3.)ESZsNone00None
(4.)CorridorsNone00None
(5.)Wildlife CorridorsNone00None
(6.)WLSNone00None
(7.)ESAsNone00None
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Archaeological SitesNone00NA
(2.)ForestNONE00NA
(3.)Defence InstallationsNONE00NA
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) Not Applicable
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 10.52
(b)Land yet to be acquired(Ha) 00
(c)Status of Land acquisition if not acquired NIL
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 00
(b)No. of Households 00
(c)No. of PDFs (Project Displaced Families) 00
(d)No. of PAFs (Project Affected Families) 00
(e)Funds Allocated for R&R(in INR) (in Lacs) 00
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Pahuj Reservoir
(ii)Direction of Water Bodies in Buffer Area South East
(iii)Distance of Water Bodies in Buffer Area 3.54
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 0
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 0
(e)No. of working days 0
(f)Total Manpower 0
32.
Green Belt in Ha:
(a)Total Area of Green Belt 3.56
(b)Percentage of Total Project Area 13.69
(c)No. of Plants to be Planted 250
(d)Funds Allocated for Plantation 80000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)EnvironmentalThe augmented capacity will help reduce waiting time and overcome the congestion of traffic, in various regions in the state of U.P. Thus, proposed Expansion will directly or indirectly reduce the consumption of natural resources such as wood and coal which will eventually help in saving the environment.
(2.)FinancialThere will be an additional central excise, and other applicable taxes through the proposed storage capacity augmentation. This will contribute to the regional/central revenue and will be further put in public expenditure.
(3.)SocialThere will be a positive impact on the indirect employment of the region. • Transporters (Trucks and logistics) contract with BPCL for distribution purpose will increase and this would result in the additional employment by the transporter (in-contract). • Due to gas transportation activity, petty food joints and & others en-route (fruits and vegetable markets) will be benefitted, to full fill the need of associated people.
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? Yes
(b)Details of Direction Issued Under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act Consent To Operate
(c)Uploaded Copy of Direction Issued Under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act Copy of Direction Issued
(d)Compliance status of the directions Complied With
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. QCI/NABET/ENV/ACO/17/0336
(ii)Name of the EIA Consultant Gaurang Environmental Solutions Pvt. Ltd.
(iii)Address 501, Paris Point, Near Collectorate Circle, Bani Park, Jaipur
(iv)Mobile No. 9782074776
(v)Landline No. 0140402911
(vi)Email Id gaurangenviro@gmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 22 Jan 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAThe project/activity is covered under category B of item 6(b) of the schedule to the EIA Notification, 2006 and requires appraisal/approval at State level. Please submit your proposal accordingly. 11 Jan 2019
2.NAThe correction have been made as per the instruction received 31 Jan 2019
3.NA- Applicability of general conditions needs to be confirmed with the authentic supporting documents. - Status of EC for the present LPG storage capacity of 450 MT, and the compliance status thereof. - CTO for the present LPG storage. 02 Feb 2019
4.NAThe correction have been made as per the instruction received 06 Feb 2019
5.NAAs requested earlier also, please inform whether the CTO issued in 1996 mentions about present LPG storage capacity of 450 MT. How the same shall be established. 09 Feb 2019
6.NAThe correction have been made as per the instruction received 12 Feb 2019
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantNishant Kumar
DesignationTM
Name of Company (Applicant Name should not be given here)BPCL JHANSI
AddressPlot no. 5/6 sector 1, Noida