1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | A A Friction Materials Private Limited | (b)Name of the Company / Organisation | A A FRICTION MATERIALS PRIVATE LIMITED | (c)Registered Address | Flat no. 104,929/1, Naiwala, Faiz Road, Karol Bagh,New Delhi,Central,Delhi-110005 | (d)Legal Status of the Company | Private | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | Prashant Rathee | (b)Designation (Owner/ Partner/ CEO) | Director | (c)Address | Flat no. 104,929/1, Naiwala, Faiz Road, Karol Bagh,New Delhi,Karol Bagh,Central,Delhi-110005 | (d)Pin code | 110005 | (e)E-mail | pr@aafriction.com | (f)STD Code. | 11(f)Telephone No. | 28758433 | (g)Fax No. | | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 4(c) Asbestos milling and asbestos based products
| Minor Activity | | (b)Category | A | (c)Proposal Number | IA/HR/IND/67766/2017 | (d)Master Proposal Number(Single Window) | SW/90576/2019 | (e)EAC concerned (for category A Projects only) | Industrial Projects - 1 | (f)Project Type | Fresh EC |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | Plot no. 5, Sector – 7, IMT Manesar | (b)Pincode | 122051 | (c)Bounded Latitudes (North) | | From | | Degree | 28.374964 | Minutes | | Second | | From | | Degree | 28.375375 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 76.913275 | Minutes | | Second | | From | | Degree | 76.918358 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | 53 D/15 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 283 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 0 | (j)Seismic Zone | 4 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Haryana | |
|
|
Details of State(s) of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
(1.) | Haryana | Gurgaon | Manesar | | (2.) | Haryana | Gurgaon | Manesar | | |
|
6. | Details of Terms of Reference (ToR): | (a)MoEF&CC / SEIAA File Number | IA-J-11011/477/2017-IA-II(I) | (b)Date of Apply of TOR | 30 Aug 2017 | (c)Date of Issue of TOR / Standard ToR | 13 Oct 2017 | (d)Previous TOR Letter | Copy of Previous TOR letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | No | (b)Whether details of Public Hearing available? | Yes | (c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above | Yes | |
|
7.1. Details of Public Hearing |
---|
|
S. No. | Details of Advertisement | Details of Public Hearing | Venue | Location Details | No. of People Attended | Issues Raised | Designation of Presiding Officer | Other Designation of Presiding Officer |
---|
(1.) | | Copy of Public Hearing : | Copy of Public Hearing | Date : | 22 May 2018 | Distance of Public Hearing Venue from the Proposed Project : | 0 |
| at Project Site (Plot no. 5, Sector – 7, IMT Manesar) | State : | Haryana | District : | Gurgaon | Tehsil : | Manesar | Village : | Plot no. 5, Sector – 7, IMT Manesar |
| 137 | Employment, Socio economic activities, Air Pollution Control System etc. | Others | Additional Deputy Commissioner | |
8. | Details of Project Configuration/Product: | |
|
8.1. Project Configuration |
---|
S. No. | Plant/Equipment/Facility | Configuration | Remarks |
---|
(1.) | Asbestos based Brake Lining for Two-wheelers | 6,67,000 PCS/day | | |
8.2. Product |
---|
S. No. | Product/Activity (Capacity/Area) | Quantity | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | Asbestos based Brake Lining for commercial Vehicles | 5400 | Others | pcs/day | Road | | (2.) | Asbestos based Brake Lining for Two-wheelers | 667000 | Others | pcs/day | Road | | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | Details Not Applicable | |
|
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | 13 Oct 2017 | (iv)Valid Upto | 12 Oct 2020 | (v)File No. | NA | (vi)Application No. | Proposed project is Greenfield Project, hence CTO | (vii)Copy of Consent to operate valid as on date | NA | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 9.5 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 0.85 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 0.19 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 0.22 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | No | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 11500 | (b)Existing quantity of raw material/fuel | N/A | (c)Total quantity of raw material/fuel | 11500 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | Asbestos Fibre Chrysotile | 11500 | Others | kg/day | Kazakhistan (Mundra Port, Gujarat)) | Road,Rail,Others | by ship | 1100 | Others | NA | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 01 Oct 2018 To 31 Oct 2018 | (b)Season | Winter | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | PM2.5 | | Micro Gram per Meter Cube | 53.2 | 42.7 | 53.2 | 60 | (2.) | PM10 | | Micro Gram per Meter Cube | 89.8 | 72.4 | 89.5 | 100 | (3.) | SO2 | | Micro Gram per Meter Cube | 18.7 | 12.2 | 18.7 | 80 | (4.) | NOx | | Micro Gram per Meter Cube | 39.2 | 25.4 | 39.0 | 80 | (5.) | Others | Asbestos Fibre Count | NA | 0.034 | 0.02 | 0.034 | 0.1 | |
14.2. No. of Ground Water monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | pH | | | NA | | 7.8 | 7.0 | 6.5 | 8.5 | (2.) | TSS | | | mg/l | | 0.4 | 0.12 | 0 | 0 | (3.) | Total Hardness | | | mg/l | | 377 | 143 | 300 | 600 | (4.) | Fluoride | | | mg/l | | 0.88 | 0.38 | 1.0 | 1.5 | (5.) | Heavy Metals | | Fe | mg/l | | 0.19 | 0.12 | 0.3 | 1.0 | (6.) | Chlorides | | | mg/l | | 388 | 77 | 250 | 1000 | (7.) | TDS | | | mg/l | | 1369 | 249 | 500 | 2000 | (8.) | Others | Flouride | | mg/l | | 0.73 | 0.42 | 1.0 | 1.5 | |
14.3. No. of Surface Water monitoring locations : 2 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | pH | | NA | | 7.4 | 7.1 | A | (2.) | DO | | mg/l | | 4.9 | 3.8 | A | (3.) | BOD | | mg/l | | 12 | 1.8 | A | (4.) | COD | | mg/l | | 25 | 4.2 | A | (5.) | Others | TDS | mg/l | | 679 | 402 | A | |
14.4. No. of Ambient Noise monitoring locations : 9 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Night) | A-weighted decibels(dB(A)) | 62.2 | 38.2 | 70 | (2.) | Leq(Day) | A-weighted decibels(dB(A)) | 68.9 | 51.7 | 75 | |
14.5. No. of Soil Sample Monitored locations : 8 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | N(Nitrogen) | Kilogram per hectare | NA | 148.2 | 85.9 | (2.) | K(Potassium) | Kilogram per hectare | | 222.6 | 155.9 | (3.) | Electric Conductivity | Milliequivalents per 100 Gram | | 464.5 | 150.3 | (4.) | pH | Others | NA | 8.0 | 7.2 | (5.) | P(Phosphorus) | Kilogram per hectare | | 69.5 | 24.5 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 3.05 To 77.55 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 3.3 To 79.7 | (c)Whether Ground Water Intersection will be there ? | No | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | Others | HSIIDC | 17.5 | 0 | Copy of Permission Letter | Pipeline | | Others | HSIIDC | Nil | 05 Jan 2019 | 17.5 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | Sanitary wastewater | 1.6 | 1.6 | Septic Tank followed by Subsurface dispersion | Others | Septic Tank followed by Subsurface dispersion | 0 | 1.6 | (2.) | Scrubber blowdown | 0.1 | 0.1 | Settling tank | Reuse within the Plant & Recycling | | 0.1 | | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 1.7 | (b)Total Discharged Water (Kilolitre per Day) | 1.6 | (c)Total Reused Water (Kilolitre per Day) | 0.1 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Recyclable (Lining) | Industrial Waste | | 0.15 | Tons | 0 | Others | resued in process | Others | reused after grinding | (2.) | Friction Dust | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 0.5 | Tons | 0 | Others | reused in the process | Others | reused in the process | (3.) | Waste oil | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 0.168 | Kilolitre | 0 | Road | | Authorized Recyclers | | (4.) | Packaging Material (Bag) | Industrial Waste | | 0.10 | Tons | 0 | Others | reused in the process | Others | reused in the process | (5.) | Chemical residue from Wet scrubber | Industrial Waste | | 0.001 | Tons | 0 | Others | resued in the process | Others | reused in the process | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | NOx | | Microgram per Meter Cube | 1786 | 300 | 0.05 | 1786.05 | 2000 | (2.) | PM2.5 | | Microgram per Meter Cube | 89.8 | 300 | 0.12 | 89.92 | 100 | (3.) | PM10 | | Microgram per Meter Cube | 18.7 | 300 | 0.2 | 18.9 | 80 | (4.) | SO2 | | Microgram per Meter Cube | 39.2 | 300 | 0.50 | 39.7 | 80 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | DG Set (2x500 kva) | Diesel | 7 | 0.25 | SO2 | | 2.1 | (2.) | DG Set (2x500 kva) | Diesel | 7 | 0.25 | NOx | | 1.8 | (3.) | Thermic Fluid Heater | HSD | 30 | 0.3 | SO2 | | 0.03 | (4.) | Thermic Fluid Heater | HSD | 30 | 0.3 | NOx | | 0.06 | (5.) | Thermic Fluid Heater | HSD | 30 | 0.3 | PM10 | | 0.016 | (6.) | DG Set (2x500 kva) | Diesel | 7 | 0.25 | PM10 | | 0.01 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 1110.05 | (b)Source | Dakshin Haryana Bijli Vitran Nigam | (c)Uploaded Copy of Agreement | Copy of Agreement | (d)Standby Arrangement (Details of DG Sets) | 2 x 500 KVA | (e)Stack Height (in m) | 7 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 0 | (b)Private Land (ha.) | 0 | (c)Government Land (ha.) | 0 | (d)Revenue Land (ha.) | 0 | (e)Other Land (ha.) | 0.405 | Total Land (ha.) | 0.405 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 0 | (b)Waste/Barren Land (ha.) | 0 | (c)Grazing/ Community Land (ha.) | 0 | (d)Surface Water Bodies (ha.) | 0 | (e)Settlements (ha.) | 0 | (f)Industrial (ha.) | 0.4050 | (g)Forest (ha.) | 0 | (h)Mangroves (ha.) | 0 | (i)Marine Area (ha.) | 0 | (j)Others (ha.) : 0 | 0 | Total (ha.) | 0.405 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Built Up Area | | 0.243 | | (2.) | Green belt | | 0.1336 | | (3.) | Others | Open area & others | 0.0284 | | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | WLS | Nil | 0 | None within 10 Kms. radius | (2.) | NPA | Sultanpur National Park | 8.9 | NA | (3.) | ESZs | Nil | 0 | None within 10 Kms. radius | (4.) | Corridors | Nil | 0 | None within 10 Kms. radius | (5.) | ESAs | Nil | 0 | None within 10 Kms. radius | (6.) | Critically Polluted Area | Nil | 0 | None within 10 Kms. radius | (7.) | Wildlife Corridors | Nil | 0 | None within 10 Kms. radius | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Others | National Park | Sultanpur National Park | 8.9 | None within 10 Kms. radius | (2.) | Archaeological Sites | | Nil | 0 | None within 10 Kms. radius | (3.) | Forest | | Nil | 0 | None within 10 Kms. radius | (4.) | Defence Installations | | Nil | 0 | None within 10 Kms. radius | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
25. | Tree Cutting: | (a)No. of Trees Cut for the Project (if Forest Land not Involved) | 0 | (b)Details of Tree Cutting and Planting of Trees | Not Applicable | |
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 0.4050 | (b)Land yet to be acquired(Ha) | 0 | (c)Status of Land acquisition if not acquired | 0.4050 ha. is taken in lease | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 0 | (b)No. of Households | 0 | (c)No. of PDFs (Project Displaced Families) | 0 | (d)No. of PAFs (Project Affected Families) | 0 | (e)Funds Allocated for R&R(in INR) (in Lacs) | 0 | (f)Status of R&R | Completed | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | Yes | (i)Details of Schedule-I Species | Peacock | (b)Whether conservation plan for Schedule-I Species has been prepared ? | Yes | (i)Uploaded copy of conservation plan | Copy of conservation plan | (ii)Fund Provision made | 11 Lakhs | (iii)Period of Implementation | 5 Years | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | Yes | (i)Uploaded copy of approval | Copy of approval | (ii)Letter No. | 3162 | (iii)Date of issue | 04 Jan 2019 | (iv)Recommendation | NA | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | No | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | Yes | (i)Details of Water Bodies in Buffer Area | Bhadshapur Stream | (ii)Direction of Water Bodies in Buffer Area | North East | (iii)Distance of Water Bodies in Buffer Area | 9.2 | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 0 | (b)Permanent Employment-During Operation | 50 | (c)Temporary Employment- During Construction | 50 | (d)Temporary Employment- During Operation | 200 | (e)No. of working days | 365 | (f)Total Manpower | 300 | |
|
32. | Green Belt in Ha: | (a)Total Area of Green Belt | 0.13 | (b)Percentage of Total Project Area | 32.10 | (c)No. of Plants to be Planted | 200 | (d)Funds Allocated for Plantation | 300000 | (e)Uploaded Green Belt plan | Copy of Green Belt Plan | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Social | With the implementation of the proposed plant, the socio-economic status of the local people will improve substantially | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details : NOT APPLICABLE |
35. Sector Specific Details For Industrial Projects - 1 |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | NABET/ EIA/ 1619/ RA 026 | (ii)Name of the EIA Consultant | PIONEER ENVIRO LABORATORIES & CONSULTANTS PVT. LTD | (iii)Address | 6-3-652, Flat # 7-3, Dhruvatara Apartments, Amrutha Estates, Erramanjil, Somajiguda, Hyderabad- 500082 | (iv)Mobile No. | 9440677333 | (v)Landline No. | 0402331427 | (vi)Email Id | pelcpl@yahoo.co.in | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | Industrial Projects - 1 | (ix)Validity of Accreditation | 22 Jun 2019 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought : NIL |
Additional Detail Sought : NIL |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | Prashant Rathee | Designation | Director | Name of Company (Applicant Name should not be given here) | A A FRICTION MATERIALS PRIVATE LIMITED | Address | Flat no. 104,929/1, Naiwala, Faiz Road, Karol Bagh |
|