1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | DEVI CHEMSCIENCE PVT. LTD. (DCPL) | (b)Name of the Company / Organisation | DEVI CHEMSCIENCE PRIVATE LIMITED | (c)Registered Address | Plot No.C-174/1, Chincholi MIDC, Tal.Mohol, Dist. Solapur,,Solapur,Maharashtra-413255 | (d)Legal Status of the Company | Private | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | Ramsingh S Rawat | (b)Designation (Owner/ Partner/ CEO) | Director | (c)Address | Plot No.7, CTS 2224, Vatan Nagar, Talegaon- Chakan Road, Talegaon Dabhade, Dist. Pune 410507, MS.,,Mawal,Pune,Maharashtra-410507 | (d)Pin code | 410507 | (e)E-mail | vivekrawat@badrivishal.com | (f)STD Code. | 2114(f)Telephone No. | 224653 | (g)Fax No. | | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
| Minor Activity | 5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
| (b)Category | A | (c)Proposal Number | IA/MH/IND2/71771/2017 | (d)Master Proposal Number(Single Window) | SW/90055/2018 | (e)EAC concerned (for category A Projects only) | Industrial Projects - 2 | (f)Project Type | Fresh EC |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | Plot No. C-174/1, Chincholi MIDC, Tal.: Mohol, Dis | (b)Pincode | 413224 | (c)Bounded Latitudes (North) | | From | | Degree | 174605.84 | Minutes | | Second | | From | | Degree | 174611.58 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 754857.85 | Minutes | | Second | | From | | Degree | 754903.14 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | 47 O/9, 47 O/10, 47 O/13, 41 O/14 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 495 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 6.5 | (j)Seismic Zone | 3 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Maharashtra | |
|
|
Details of State(s) of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
(1.) | Maharashtra | Solapur | Mohol | | |
|
6. | Details of Terms of Reference (ToR): | (a)MoEF&CC / SEIAA File Number | IA-J-11011/580/2017-IA-II(I) | (b)Date of Apply of TOR | 22 Dec 2017 | (c)Date of Issue of TOR / Standard ToR | 05 Feb 2018 | (d)Previous TOR Letter | Copy of Previous TOR letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | Yes | (b)Reason | Project is located in notified MIDC Area | (c)Supporting Document | Copy of Supporting Document | |
|
8. | Details of Project Configuration/Product: | |
|
8.1. Project Configuration |
---|
S. No. | Plant/Equipment/Facility | Configuration | Remarks |
---|
(1.) | 5.275 MTPD | Bulk Drugs and Intermediate Manufacturing Unit | | |
8.2. Product |
---|
S. No. | Product/Activity (Capacity/Area) | Quantity | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | Metoprolol Succinate& Intermediates | 36 | Tons per Annum | | Road | | (2.) | Metoprolol Tartrate & Intermediates | 36 | Tons per Annum | | Road | | (3.) | Acetozolamide & Intermediates | 24 | Tons per Annum | | Road | | (4.) | Bambutetrol HCl & Intermediates | 0.3 | Tons per Annum | | Road | | (5.) | Defriprone & Intermediates | 2.4 | Tons per Annum | | Road | | (6.) | Dioctyl Calcium Sulfosuccinate & Intermediates | 12 | Tons per Annum | | Road | | (7.) | Dioctyl Potassium Sulfosuccinate & Intermediates | 12 | Tons per Annum | | Road | | (8.) | Dioctyl Sodium Sulfosuccinate & Intermediates | 600 | Tons per Annum | | Road | | (9.) | Levo Salbutamol Sulphate & Intermediates | 0.3 | Tons per Annum | | Road | | (10.) | Tiotropium Bromide & Intermediates | 0.06 | Tons per Annum | | Road | | (11.) | Moxifloxacin Hydrochloride | 12 | Tons per Annum | | Road | | (12.) | Pregabalin & Intermediate | 72 | Tons per Annum | | Road | | (13.) | Carbimazole & Intermediate | 12 | Tons per Annum | | Road | | (14.) | Methimazole & Intermediate | 6 | Tons per Annum | | Road | | (15.) | Carvedilol & Intermediate | 9 | Tons per Annum | | Road | | (16.) | Guaifenesin & Intermediates | 240 | Tons per Annum | | Road | | (17.) | (R)-Bambutetrol HCl &Intermediates | 0.3 | Tons per Annum | | Road | | (18.) | Levetiracetam & Intermediates | 60 | Tons per Annum | | Road | | (19.) | Bromohexine Hydrochloride & Intermediates | 48 | Tons per Annum | | Road | | (20.) | Clopidogrel Bisulfate & Intermediates | 24 | Tons per Annum | | Road | | (21.) | Permethrin & Intermediates | 24 | Tons per Annum | | Road | | (22.) | Quinaldic Acid | 72 | Tons per Annum | | Road | | (23.) | Diamyl Sodium sulfosuccinate and Solution | 360 | Tons per Annum | | Road | | (24.) | Ondansetron & Intermediate | 9 | Tons per Annum | | Road | | (25.) | Dorzolamide Hydrochloride & Intermediates | 0.3 | Tons per Annum | | Road | | (26.) | Formoterol Fumarate Dihydrate & Intermediates | 0.06 | Tons per Annum | | Road | | (27.) | Furosemide & Intermediates | 24 | Tons per Annum | | Road | | (28.) | Ipratropium Bromide & Intermediates | 0.06 | Tons per Annum | | Road | | (29.) | Methocarbamol & Intermediates | 60 | Tons per Annum | | Road | | (30.) | Salbutamol Sulphate & Intermediates | 36 | Tons per Annum | | Road | | (31.) | Salmetrol Xinafoate & Intermediates | 0.06 | Tons per Annum | | Road | | (32.) | Moxifloxacin Intermediate | 36 | Tons per Annum | | Road | | (33.) | Chlorphenesin & Intermediates | 72 | Tons per Annum | | Road | | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | Details Not Applicable | |
|
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | N/A | (iv)Valid Upto | N/A | (v)File No. | NA | (vi)Application No. | NA | (vii)Copy of Consent to operate valid as on date | NA | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 25 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 3.20 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 0.625 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 0.07 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | Yes | a)Protected areas notified under the wildlife (Protection) Act, 1972 | Yes | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 8640 | (b)Existing quantity of raw material/fuel | N/A | (c)Total quantity of raw material/fuel | 8640 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | Toluene | 25534.52 | Others | Kg/Batch | Market | Road | | 100 | Open Market | | Copy of Linkage | (2.) | Bromine | 1874 | Others | Kg/Batch | Open Market | Road | | 500 | Open Market | | Copy of Linkage | (3.) | ammonia solution | 488.5 | Others | Kg/Batch | Open Market | Road | | 500 | Open Market | | Copy of Linkage | (4.) | Acetic Acid | 825 | Others | Kg/Batch | Open Market | Road | | 500 | Open Market | | Copy of Linkage | (5.) | Coal | 8640 | Tons per Annum | | Open Market | Road | | 500 | Open Market | | Copy of Linkage | (6.) | Methanol | 21237.85 | Others | Kg/Batch | Open Market | Road | | 500 | Open Market | | Copy of Linkage | (7.) | Ethyl Acetate | 3311 | Others | Kg/Batch | Open Market | Road | | 500 | Open Market | | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 01 Feb 2018 To 30 Apr 2018 | (b)Season | Pre-Monsoon | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | PM2.5 | | Micro Gram per Meter Cube | 22.83 | 10.06 | 17.27 | 60 | (2.) | SO2 | | Micro Gram per Meter Cube | 29.9 | 9.66 | 17.27 | 80 | (3.) | Others | NH3 | Micro Gram per Meter Cube | 23.53 | 9.4 | 23.36 | 400 | (4.) | PM10 | | Micro Gram per Meter Cube | 73.16 | 44.4 | 60.21 | 100 | (5.) | NOx | | Micro Gram per Meter Cube | 38.63 | 14.1 | 38.54 | 80 | |
14.2. No. of Ground Water monitoring locations : 3 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | pH | | | NA | | 7.48 | 7.28 | 6.5 | 8.5 | (2.) | Chlorides | | | mg/l | | 364.59 | 256.63 | 250 | 250 | (3.) | Total Hardness | | | mg/l | | 301.97 | 231.78 | 200 | 200 | (4.) | Fluoride | | | mg/l | | 0.75 | 0.18 | 1 | 1 | (5.) | Heavy Metals | | Zink as Zn | mg/l | | 3.98 | 2.11 | 5 | 5 | (6.) | TSS | | | mg/l | | 80.12 | 55.41 | 100 | 200 | (7.) | TDS | | | mg/l | | 1578.51 | 962.57 | 500 | 500 | |
14.3. No. of Surface Water monitoring locations : 2 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | pH | | NA | | 7.43 | 7.28 | E | (2.) | DO | | mg/l | | 4.8 | 3.7 | E | (3.) | Others | Total Coli | Others | No./100 ml | 133 | 78 | B | (4.) | COD | | mg/l | | 28.47 | 25.96 | E | (5.) | BOD | | mg/l | | 10.46 | 9.72 | E | |
14.4. No. of Ambient Noise monitoring locations : 8 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Night) | A-weighted decibels(dB(A)) | 61.3 | 33.9 | 70 | (2.) | Leq(Day) | A-weighted decibels(dB(A)) | 68.7 | 47 | 75 | |
14.5. No. of Soil Sample Monitored locations : 8 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | N(Nitrogen) | Kilogram per hectare | | 689 | 282.6 | (2.) | pH | Others | NA | 7.54 | 7.05 | (3.) | P(Phosphorus) | Kilogram per hectare | | 406.9 | 191.8 | (4.) | K(Potassium) | Kilogram per hectare | | 254.6 | 177.5 | (5.) | Electric Conductivity | Millisiemens per Centimetre | | 0.9 | 0.17 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 0.5 To 12.8 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 0.0041 To 4 | (c)Whether Ground Water Intersection will be there ? | No | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | Surface | | 36 | 8 | Not Appliacble | Pipeline | | Jack Well | | MIDC/RO(ROS)/CHN/LMS/1134/20145827 | 12 Dec 2014 | 36 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | Stream I | 40 | 40 | ETP | Others | Water Loss in ETP operations | 34 | 6 | (2.) | Stream II | 3 | 3 | ETP | Others | Water Loss in ETP operations | 2 | 1 | (3.) | Domestic Effluent | 5.4 | 5.4 | STP | Others | Flushing | 5.4 | 0 | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 48.4 | (b)Total Discharged Water (Kilolitre per Day) | 7 | (c)Total Reused Water (Kilolitre per Day) | 41.4 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Ash | Bottom Ash | | 864 | Tons | 50 | Road | | Others | Sale to Brick Manufacturers | (2.) | Spent Catalyst | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 0.84 | Tons | 250 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (3.) | Salts Generated from MEE | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 24 | Tons | 20 | Road | | Authorized Recyclers | | (4.) | Plastic and Paper Waste | Plastic Waste | | 24 | Tons | 5 | Road | | Others | To sale | (5.) | Process Residue and Wastes | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | Scrap | 96 | Tons | 250 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (6.) | Spent Carbon | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 20.4 | Tons | 250 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (7.) | Spent Solvent | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 600 | Tons | 50 | Road | | Authorized Recyclers | | (8.) | ETP Sludge | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 60 | Tons | 250 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | PM10 | | Microgram per Meter Cube | 60.21 | 1 | 0.8 | 61.01 | 100 | (2.) | PM2.5 | | Microgram per Meter Cube | 17.27 | 1 | 0.2 | 17.47 | 60 | (3.) | SO2 | | Microgram per Meter Cube | 29.65 | 1 | 8 | 37.65 | 80 | (4.) | NOx | | Microgram per Meter Cube | 38.54 | 1 | 00 | 00 | 80 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | 1010 KVA D.G. Set | High Speed Diesel | 6.5 | 0.5 | SO2 | | 20 | (2.) | 2 TPH (2 Nos.) | 24 TPD/48 TPD | 30 | 0.3 | PM10 | | 800 | (3.) | Thermic Fluid Heater | Furnace oil | 18 | 0.3 | SO2 | | 400 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 1133 | (b)Source | M.E.D.CO LTD. | (c)Uploaded Copy of Agreement | Not Applicable | (d)Standby Arrangement (Details of DG Sets) | 1010 KVA | (e)Stack Height (in m) | 5 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 0 | (b)Private Land (ha.) | 1.63 | (c)Government Land (ha.) | 0 | (d)Revenue Land (ha.) | 0 | (e)Other Land (ha.) | 0 | Total Land (ha.) | 1.63 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 14754.60 | (b)Waste/Barren Land (ha.) | 1854.68 | (c)Grazing/ Community Land (ha.) | 1330 | (d)Surface Water Bodies (ha.) | 213 | (e)Settlements (ha.) | 00 | (f)Industrial (ha.) | 00 | (g)Forest (ha.) | 4587 | (h)Mangroves (ha.) | 00 | (i)Marine Area (ha.) | 00 | (j)Others (ha.) : Fallow Land | 8676.22 | Total (ha.) | 31415.5 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Built Up Area | | 0.73086 | | (2.) | Green belt | | 0.5382 | | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Critically Polluted Area | NA | 0 | There is no presence of any CPA, NPA, ESAs, ESZ corridor and wildlife corridors in 10 Km radius of project | (2.) | NPA | NA | 0 | There is no presence of any CPA, NPA, ESAs, ESZ corridor and wildlife corridors in 10 Km radius of project | (3.) | WLS | Great Indian Bustard | 0.65 | Letter w.r.t. distance of project site from Great Indian Bustard Bird Sanctuary is received from forest department, Solapur. Same was appended in Form I application submitted to MoEfCC, New Delhi | (4.) | ESZs | NA | 0 | There is no presence of any CPA, NPA, ESAs, ESZ corridor and wildlife corridors in 10 Km radius of project | (5.) | Wildlife Corridors | NA | 0 | There is no presence of any CPA, NPA, ESAs, ESZ corridor and wildlife corridors in 10 Km radius of project | (6.) | Corridors | NA | 0 | There is no presence of any CPA, NPA, ESAs, ESZ corridor and wildlife corridors in 10 Km radius of project | (7.) | ESAs | NA | 0 | There is no presence of any CPA, NPA, ESAs, ESZ corridor and wildlife corridors in 10 Km radius of project | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Forest | | NA | 0 | There is no forest land within 10 km from project site | (2.) | Defence Installations | | NA | 0 | There is no any defence installations within 10 km from project site | (3.) | Archaeological Sites | | NA | 0 | There is no archaeological sites within 10 km from project site | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | Selec | |
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
25. | Tree Cutting: | (a)No. of Trees Cut for the Project (if Forest Land not Involved) | 0 | (b)Details of Tree Cutting and Planting of Trees | Not Applicable | |
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 1.6 | (b)Land yet to be acquired(Ha) | 0 | (c)Status of Land acquisition if not acquired | 0 | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 0 | (b)No. of Households | 0 | (c)No. of PDFs (Project Displaced Families) | 0 | (d)No. of PAFs (Project Affected Families) | 0 | (e)Funds Allocated for R&R(in INR) (in Lacs) | 0 | (f)Status of R&R | Completed | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | No | (b)Whether conservation plan for Schedule-I Species has been prepared ? | No | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | Yes | (i)Details of Water Bodies in Core Area | Sina River | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | No | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 10 | (b)Permanent Employment-During Operation | 30 | (c)Temporary Employment- During Construction | 40 | (d)Temporary Employment- During Operation | 40 | (e)No. of working days | 365 | (f)Total Manpower | 120 | |
|
32. | Green Belt in Ha: | (a)Total Area of Green Belt | 0.5381 | (b)Percentage of Total Project Area | 33.01 | (c)No. of Plants to be Planted | 800 | (d)Funds Allocated for Plantation | 1200000 | (e)Uploaded Green Belt plan | Copy of Green Belt Plan | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Social | 1. Employment generation
2. Improvement in the Physical & Social Infrastructure
3. Upliftment of local peoples | (2.) | Financial | 1. The community that resides in the nearby areas will be benefited directly or indirectly by this project
2. After establishment, the industry will meet the national interest of economical growth through sustainable development, | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details : NOT APPLICABLE |
35. Sector Specific Details For Industrial Projects - 2 |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | NABET/EIA/1518/SA 063 | (ii)Name of the EIA Consultant | Equinox Environments India Pvt. Ltd. | (iii)Address | F-11, Namdev Nest, 1160-B, āEā Ward, Sykes Extension, Opposite Kamala College | (iv)Mobile No. | 9657865122 | (v)Landline No. | 0231253123 | (vi)Email Id | eia@equinoxenvi.com | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | Industrial Projects - 2 | (ix)Validity of Accreditation | 21 Oct 2018 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought: |
---|
Sno. | EDS Letter | Remarks | Date of EDS |
---|
1. | NA | Please inform/clarify the following:-
- Accreditation of the EIA consultant is valid only up to 21/10/2018. How the present proposal is admissible.
- Notification of Chincholi Industrial area by the State Government of Maharashtra along with the supporting documents.
- Proposed fresh water requirement of 36 cum/day needs to be reworked out in view of production capacity of the plant is limited to 5.275 TPD. Also, there is no permission letter/file attached showing surface water supply of 36 cum/day.
- Applicability of general conditions to be confirmed along with the supporting documents. | 06 Jan 2019 | 2. | NA | The correction have been made as per the instruction received | 27 Jan 2019 | 3. | NA | - As observed earlier also regarding accreditation of EIA consultant, please inform the present status duly endorsed by NABET.
- Project site is reported to be at 0.65 km from the Bird Sanctuary. As such, wildlife clearance is very much relevant and there is a need for clarification from the regulatory authorities/SPCB to allow such polluting units so close to the Sanctuary.
- Present status of ESZ for the Bird Sanctuary. | 02 Feb 2019 | 4. | NA | The correction have been made as per the instruction received | 28 Feb 2019 | |
Additional Detail Sought: |
---|
Sno. | ADS Letter | Remarks | Date of ADS |
---|
1. | ADS Reply Letter | NA | 05 Jul 2019 | 2. | NA | Deferred | 17 May 2019 | |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | Ramsingh S Rawat | Designation | Director | Name of Company (Applicant Name should not be given here) | DEVI CHEMSCIENCE PRIVATE LIMITED | Address | Plot No.C-174/1, Chincholi MIDC, Tal.Mohol, Dist. Solapur |
|