Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) E.I.D. PARRY (INDIA) LIMITED
(b)Name of the Company / Organisation D. KUMARA SWAMY
(c)Registered Address NIL
(d)Legal Status of the Company NIL
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant
(b)Designation (Owner/ Partner/ CEO) GENERAL MANAGER (ENGINEERING)
(c)Address NIL
(d)Pin code 587207
(e)E-mail Vvsnmurthy.Kotni@parry.murugappa.com
(f)STD Code. (f)Telephone No.
(g)Fax No. 25341609
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(g) Distilleries
5(j) Sugar Industry
Minor Activity
(b)Category B1
   Reason for Applying at Ministry Other
   Other Reason for Applying at Ministry SEIAA CONSTITUTED
(c)Proposal Number IA/KA/IND2/89860/2016
(d)Master Proposal Number(Single Window) SW/89813/2018
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. 29, 32/1, 32/2, 33/1/B, 33/1A, 36, 27/2, 27/3,28/1
(b)Pincode 587207
(c)Bounded Latitudes (North)
From
Degree 16.27
Minutes
Second
From
Degree 16.28
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 75.92
Minutes
Second
From
Degree 75.93
Minutes
Second
(e)Survey of India Topo Sheet No. 47 P /15
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 540
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 2.7
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Karnataka
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number J-11011/358/2016-IA-II(I)
(b)Date of Apply of TOR 03 Dec 2016
(c)Date of Issue of TOR / Standard ToR 28 Feb 2017
(d)Date of Apply of EC 22 Feb 2015
(e)Date of Issue of EC 31 Dec 2015
(f)Previous TOR Letter Copy of Previous TOR letter
(g)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :26 Jul 2018
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :29 Aug 2018
Distance of Public Hearing Venue from the Proposed Project :0
plant site
State :Karnataka
District :Bagalkot
Tehsil :Bagalkot
Village :Nagarl & Nainegali
212environmental pollution problems due to proposed DistilleryDeputy Commissioner
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Bangalore
(iii)Letter No. NIL
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Mar 1 2018 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)DISTILLERY06060Kilo Litre per Day(KLD)Road,Pipe Conveyor
(2.)POWER FROM INCINERATION BOILER033Mega Watt(MW)Pipe Conveyor
(3.)SUGAR475027507500Tons Crushed per Day(TCD)Road
(4.)CO-GENERATION POWER PLANT151934Mega Watt(MW)Road,Conveyor Belt
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)BOILER94 TPH110 TPH94 TPH & 110 TPH
(2.)INCINERATION BOILER--25 TPH25 TPH
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 28 Oct 2016
(iv)Valid Upto 30 Jun 2021
(v)File No. 10040
(vi)Application No. AW-301290
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 351
(b) Funds Allocated for Environment Management (Capital) (in Crores) 20
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 2.88
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 2
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 230
(b)Existing quantity of raw material/fuel 0
(c)Total quantity of raw material/fuel 230
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Coal160200Tons per AnnumindonesiaRoad400 e-auctionCopy of Linkage
(2.)Sugar cane1350000Tons Crushed per DayLOCAL AREASRoad70 OthersTHROUGH FARMERSCopy of Linkage
(3.)Bagasse405000Tons per AnnumcaptiveConveyor Belt0 CaptiveCopy of Linkage
(4.)Molasses raw material for distillery82800Tons per Annumcaptive and other group unitsRoad,Pipe Conveyor100 CaptiveCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Dec 2016 To 28 Feb 2017
(b)Season Winter
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM2.5Micro Gram per Meter Cube39.923.539.960
(2.)PM10Micro Gram per Meter Cube66.439.366.4100
(3.)NOxMicro Gram per Meter Cube19.212.119.280
(4.)SO2Micro Gram per Meter Cube16.911.916.980
(5.)OthersCOMicro Gram per Meter Cube6104106102000
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TDSmg/l21478065002000
(2.)Chloridesmg/l12104152501000
(3.)Fluoridemg/l1.10.511.5
(4.)Heavy Metalsleadmg/l0.0080.0050.050.05
(5.)Total Hardnessmg/l950515300600
(6.)Othersalkalinitymg/l175135200600
(7.)TSSOthersNTU21.1510
(8.)pHNA7.87.26.58.5
    14.3.     No. of Surface Water monitoring locations : 2
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)CODmg/l108C
(2.)DOmg/l6.26.1C
(3.)BODmg/l54C
(4.)Otherschloridesmg/l142136C
(5.)pHNA8.48.2C
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))544855
(2.)Leq(Night)A-weighted decibels(dB(A))464145
    14.5.     No. of Soil Sample Monitored locations : 6
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)P(Phosphorus)Kilogram per hectare3528
(2.)K(Potassium)Kilogram per hectare7548
(3.)pHOtherspH7.67.3
(4.)Electric ConductivityOthersMicro siemens / cm165135
(5.)N(Nitrogen)Kilogram per hectare275230
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 0.41 To 14.55
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 0.36 To 11.3
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Surface13282.7Copy of Permission LetterPipelineJack Well117 / kbn / 200724 Mar 20081500
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)CO-GEN POWER PLANT143150NEUTRALIZATIONReuse within the Plant & Recycling143
(2.)DISTILLERY UNIT480500CONCENTRATION FOLLOWED BY INCINERATIONReuse within the Plant & Recycling4800
(3.)SUGAR PLANT7401600ETPReuse within the Plant & Recycling,Green Belt Renewal Plant740
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 1363
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 1363
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)FILTER CAKEIndustrial Waste60000Tons10RoadOthersGIVEN TO FARMERS TO USE AS MANURE
(2.)ETP SLUDGEIndustrial Waste60Tons0RoadOthersUSED AS MANURE FOR GREENBELT DEVELOPMENT
(3.)ASH (BAGASSE AS RAW MATERIAL)Industrial Waste9000Tons10RoadOthersGIVEN TO FARMERS TO USE AS MANURE
(4.)MOLASSESIndustrial Waste67500Tons0Pipe ConveyorOthersUSED AS RAW MATERIAL IN DISTILLERY
(5.)ASH (COAL AS RAW MATERIAL)Industrial Waste14240Tons30RoadOthersGIVEN TO BRICK MANUFACTURERS
(6.)BAGASSEIndustrial Waste405000Tons0Conveyor BeltOthersUSED AS RAW MATERIAL FOR CO-GEN POWER PLANT
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube66.413002.568.9100
(2.)SO2Microgram per Meter Cube16.9130025.242.180
(3.)NOxMicrogram per Meter Cube19.2130014.934.180
(4.)Others(Specify)COMicrogram per Meter Cube6105005.5615.52000
(5.)PM2.5Microgram per Meter Cube39.913001.541.460
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)110 TPH BOILERCOAL863.5PM105.9
(2.)25 TPH BOILERCONCENTRATED SPENT WASH601.5SO225.5
(3.)25 TPH BOILERCONCENTRATED SPENT WASH601.5NOx4.5
(4.)94 TPH BOILERCOAL743.4SO273.1
(5.)94 TPH BOILERCOAL743.4NOx27.5
(6.)110 TPH BOILERCOAL863.5NOx29.5
(7.)94 TPH BOILERCOAL743.4PM105.5
(8.)110 TPH BOILERCOAL863.5SO2114.6
(9.)25 TPH BOILERCONCENTRATED SPENT WASH601.5PM100.9
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 10000
(b)Source CAPTIVE
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 2 X 1000
(e)Stack Height (in m) 15
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 71.74
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 71.74
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 0
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 71.74
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : 0 0
    Total (ha.) 71.74
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Built Up Area33.2
(2.)Green belt24.3
(3.)OthersINTERNAL ROADS, PARKING AREA AND OTHERS14.24
Total (ha.) 71.74
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)WLSNIL0NIL WITHIN 10 KM RADIUS
(2.)NPANIL0NIL WITHIN 10 KM RADIUS
(3.)ESZsNIL0NIL WITHIN 10 KM RADIUS
(4.)Wildlife CorridorsNIL0NIL WITHIN 10 KM RADIUS
(5.)Critically Polluted AreaNIL0NIL WITHIN 10 KM RADIUS
(6.)ESAsNIL0NIL WITHIN 10 KM RADIUS
(7.)CorridorsNIL0NIL WITHIN 10 KM RADIUS
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestUNNAMED4.5FOREST
(2.)Archaeological SitesNIL0NIL WITHIN 10 KM RADIUS
(3.)Defence InstallationsNIL0NIL WITHIN 10 KM RADIUS
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 71.74
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired ACQUIRED
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area KRISHNA RIVER
(ii)Direction of Water Bodies in Buffer Area North
(iii)Distance of Water Bodies in Buffer Area 2.7
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 100
(b)Permanent Employment-During Operation 200
(c)Temporary Employment- During Construction 100
(d)Temporary Employment- During Operation 100
(e)No. of working days 360
(f)Total Manpower 500
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt20.423.8824.3
(2.)Percentage of Total Project Area28.21.830
(3.)No. of Plants30000600036000
(4.)Funds Allocated0.50.10.6
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)Financialprovides employment
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET / EIA / 1619 / RA 026
(ii)Name of the EIA Consultant PIONEER ENVIRO LABORATORIES & CONSULTANTS PVT. LTD
(iii)Address HYDERABAD
(iv)Mobile No. 9000380040
(v)Landline No. 0402331427
(vi)Email Id info@pioneerenvirolabs.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 22 Jun 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAPlease inform/clarify/provide the following:- - Establishment of existing sugar plant (4750 TCD) prior to inception of the EIA Notification, 1994/2006 along with supporting documents. - Increase in fresh water requirement due to the proposed expansion of sugar plant, setting up distillery of 60 KLPD, and the status of clearance for surface water withdrawal. - How the products mentioned in the CTO are compatible with the present capacity of sugar plant (4750 TCD). 05 Jan 2019
2.NAThe correction have been made as per the instruction received 23 Jan 2019
3.NAThe correction have been made as per the instruction received 23 Jan 2019
4.NAAs requested earlier also, please inform present status of your request dated 24/2/2018 to the State Govt of Karnataka for surface water withdrawal of 1328 cum/day from Krishna river. 02 Feb 2019
5.NAThe correction have been made as per the instruction received 14 May 2019
6.NAGiven the substantial quantity of surface water required of 1328 cum/day, please inform some progress on your request dated 24/2/2018. 18 May 2019
7.NAThe correction have been made as per the instruction received 02 Oct 2019
8.NAThe project covered under category B. You are requested to submit the proposal at respective SEIAA/SEAC. 03 Nov 2019
9.NAThe correction have been made as per the instruction received 18 Nov 2019
10.NAAs per Ministry’s Notification dated 13th June, 2019, proposal comes under category B and requires appraisal at SEIAA/SEAC. Please submit proposal at SEIAA/SEAC. 05 Dec 2019
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of Applicant
DesignationGENERAL MANAGER (ENGINEERING)
Name of Company (Applicant Name should not be given here)D. KUMARA SWAMY