1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | Construction of new link National Highway 133B (Design Chainage km.0.000) starts at proposed Sahibganj Bypass and meet at Ch.200.870 of NH-80 (new name NH-33) (Design Chainage 1.800 of NH 133B) and en | (b)Name of the Company / Organisation | National Highways Authority of India | (c)Registered Address | G-5 & 6, Sector-10, Dwarka, New DElhi-110075,G-5 & 6, Sector-10, Dwarka, New DElhi-110075,South West,Delhi-110075 | (d)Legal Status of the Company | Central Government | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | Dr Biswajit Mukhopadhyay | (b)Designation (Owner/ Partner/ CEO) | General Manager | (c)Address | G-5 & 6, Sector-10, Dwarka, New DElhi-110075,G-5 & 6, Sector-10, Dwarka, New DElhi-110075,,New Delhi,Delhi-110075 | (d)Pin code | 110075 | (e)E-mail | biswajit@nhai.org | (f)STD Code. | 11(f)Telephone No. | 25074200 | (g)Fax No. | 25093543 | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 7(f) Highways
| Minor Activity | 2(b) Mineral beneficiation
| (b)Category | A | (c)Proposal Number | IA/BR/NCP/89734/2018 | (d)Master Proposal Number(Single Window) | SW/89729/2018 | (e)EAC concerned (for category A Projects only) | INFRA-1 | (f)Project Type | Fresh EC |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | Bihar & Jharkhand | (b)Pincode | 816109 | (c)Bounded Latitudes (North) | | From | | Degree | 25.237224 | Minutes | | Second | | From | | Degree | 25.351638 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 87.597527 | Minutes | | Second | | From | | Degree | 87.655865 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | 72 O/8, 72 O/12 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 54 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 0 | (j)Seismic Zone | 4 | |
|
5. | (a)Number of States in which Project will be Executed | 2 | (c)Main State of the project | Bihar | |
|
|
Details of State of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
NIL | |
|
6. | Details of Terms of Reference (ToR): | (a)Whether TOR is mandatory for submitting application | Yes | (b)MoEF&CC / SEIAA File Number | 10-62/2018-IA.III | (c)Date of Apply of TOR | 24 Aug 2018 | (d)Date of Issue of TOR / Standard ToR | 08 Oct 2018 | (e)Previous TOR Letter | Copy of Previous TOR letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | No | (b)Whether details of Public Hearing available? | Yes | (c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above | Yes | |
|
7.1. Details of Public Hearing |
---|
|
S. No. | Details of Advertisement | Details of Public Hearing | Venue | Location Details | No. of People Attended | Issues Raised | Designation of Presiding Officer | Other Designation of Presiding Officer |
---|
(1.) | | Copy of Public Hearing : | Copy of Public Hearing | Date : | 10 Nov 2018 | Distance of Public Hearing Venue from the Proposed Project : | 1 |
| Manihari | State : | Bihar | District : | Katihar | Tehsil : | Manihari | Village : | Manihari |
| 60 | Asked for the information regarding present land value and amount to be given for resettlement and rehabilitation.
Asked for the information regarding steps will be taken by government for the contro | Others | Additional Collector | (2.) | | Copy of Public Hearing : | Copy of Public Hearing | Date : | 20 Nov 2018 | Distance of Public Hearing Venue from the Proposed Project : | 0 |
| Ambadiha | State : | Jharkhand | District : | Sahibganj | Tehsil : | Mandro | Village : | Ambadiha |
| 74 | The Construction of bridge is good work. In the construction of 4 lane road there are 5 grave yards, 3 mosques are going to be affected. The alignment can be change to so that they will not get affect | Others | Additional Collector | |
8. | Details of Project Configuration/Product: | |
|
8.1. Project Configuration |
---|
S. No. | Plant/Equipment/Facility | Configuration | Remarks |
---|
(1.) | Highway Project including Bridge | 15.885 km | | |
8.2. Product |
---|
S. No. | Product/Activity (Capacity/Area) | Quantity | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | Water | 440617 | Others | KL | Road | | (2.) | Borrow Earth | 1682300 | Others | cubic meter | Road | | (3.) | Granular material/Moorum | 638200 | Others | Cubic Meter | Road | | (4.) | Aggregate | 1113800 | Others | Cubic meter | Road | | (5.) | Stone | 86920 | Others | cubic meter | Road | | (6.) | Coarse Sand | 497350 | Others | cubic meter | Road | | (7.) | Cement | 272730 | Others | cubic meter | Road | | (8.) | Bitumen | 16870 | Others | Mt. | Road | | (9.) | Strands | 21520 | Others | Mt. | Road | | (10.) | Emulsion | 470 | Others | Mt. | Road | | (11.) | Structural Steel | 8730 | Others | Mt. | Road | | (12.) | HYSD Steel | 61930 | Others | Metric Tonnes | Road | | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | Details Not Applicable | |
|
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | N/A | (iv)Valid Upto | N/A | (v)File No. | NA | (vi)Application No. | NA | (vii)Copy of Consent to operate valid as on date | NA | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 2598 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 24.599 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 2 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 12.2995 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | Yes | d)Inter-State boundaries and international boundaries | Yes | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 800000 | (b)Existing quantity of raw material/fuel | N/A | (c)Total quantity of raw material/fuel | 800000 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | Granular material/Moorum | 638200 | Others | cum | Sahibganj and Katihar | Road | | 20 | Open Market | | Copy of Linkage | (2.) | Coarse Sand | 497350 | Others | cum | Sahibganj and Katihar | Road | | 20 | Open Market | | Copy of Linkage | (3.) | Cement | 272730 | Others | cum | Sahibganj and Katihar | Road | | 50 | Open Market | | Copy of Linkage | (4.) | Strands | 21520 | Others | Mt. | Jamshedpur | Road,Rail | | 500 | Open Market | | Copy of Linkage | (5.) | Aggregate | 1113800 | Others | cum | Sahibganj and Katihar | Road | | 20 | Open Market | | Copy of Linkage | (6.) | Borrow Earth | 1682300 | Others | cum | Sahibganj and katihar | Road | | 10 | Open Market | | Copy of Linkage | (7.) | Water | 440617 | Others | KL | River Ganga | Road | | 0 | Open Market | | Copy of Linkage | (8.) | Stone | 86920 | Others | cum | Sahibganj and Katihar | Road | | 20 | Open Market | | Copy of Linkage | (9.) | Emulsion | 470 | Others | Mt. | Sahibganj and Katihar | Road,Rail | | 50 | Open Market | | Copy of Linkage | (10.) | Bitumen | 16870 | Others | Mt | Kolkata | Road,Rail | | 500 | Open Market | | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 01 Apr 2017 To 17 Jun 2017 | (b)Season | Summer | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 3 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | PM10 | | Micro Gram per Meter Cube | 70.3 | 38.9 | 68.0 | 100 | (2.) | SO2 | | Micro Gram per Meter Cube | 6.8 | 4.2 | 6.7 | 80 | (3.) | Others | CO | Micro Gram per Meter Cube | 1700 | 1000 | 1600 | 4000 | (4.) | PM2.5 | | Micro Gram per Meter Cube | 41.5 | 20.7 | 39.5 | 60 | (5.) | NOx | | Micro Gram per Meter Cube | 26.48 | 11.4 | 25.1 | 80 | |
14.2. No. of Ground Water monitoring locations : 04 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | pH | | | NA | | 7.89 | 7.32 | 6.5 | 8.5 | (2.) | TSS | | | mg/l | | 0 | 0 | 0 | 0 | (3.) | TDS | | | mg/l | | 885 | 428 | 500 | 2000 | (4.) | Heavy Metals | | Iron | mg/l | | 0.12 | 0.08 | 0.3 | 0.3 | (5.) | Chlorides | | | mg/l | | 190.1 | 100 | 250 | 1000 | (6.) | Total Hardness | | | mg/l | | 460 | 200 | 200 | 600 | (7.) | Fluoride | | | mg/l | | 1.12 | 0.5 | 1 | 1.5 | |
14.3. No. of Surface Water monitoring locations : 03 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | pH | | NA | | 7.98 | 7.93 | C | (2.) | COD | | mg/l | | 14 | 12 | C | (3.) | Others | Colour | Others | Hazen | 08 | 06 | C | (4.) | BOD | | mg/l | | 04 | 03 | C | (5.) | DO | | mg/l | | 6.1 | 5.2 | C | |
14.4. No. of Ambient Noise monitoring locations : 04 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Day) | A-weighted decibels(dB(A)) | 64.1 | 47.5 | 65 | (2.) | Leq(Night) | A-weighted decibels(dB(A)) | 51.4 | 37.1 | 55 | |
14.5. No. of Soil Sample Monitored locations : 03 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | N(Nitrogen) | Milligram per Kilogram | | 289 | 246 | (2.) | Electric Conductivity | Millisiemens per Centimetre | | 106 | 88 | (3.) | pH | Others | NA | 8.06 | 7.96 | (4.) | P(Phosphorus) | Milligram per Kilogram | | 84 | 68 | (5.) | K(Potassium) | Milligram per Kilogram | | 156 | 139 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 12 To 4.6 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 2.85 To 7.93 | (c)Whether Ground Water Intersection will be there ? | NA | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | Surface | | 1 | 1 | Not Appliacble | Pipeline | | Others | River | NA | 10 Nov 2018 | 1 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | Domestic | 1 | 2 | Bio-toilets | Reuse within the Plant & Recycling | | 1 | 0 | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 1 | (b)Total Discharged Water (Kilolitre per Day) | 0 | (c)Total Reused Water (Kilolitre per Day) | 1 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Surplus Earth | Construction & Demolition Waste | | 646174 | Tons | 5 | Road | | Others | Low lying areas | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | PM2.5 | | Microgram per Meter Cube | 29.2 | 1 | 39.73 | 39.73 | 60 | (2.) | NOx | | Microgram per Meter Cube | 5.28 | 1 | 7.18 | 7.18 | 80 | (3.) | Others(Specify) | CO | Microgram per Meter Cube | 1320 | 1 | 1570 | 1570 | 4000 | (4.) | PM10 | | Microgram per Meter Cube | 54.6 | 1 | 74.29 | 74.29 | 100 | (5.) | SO2 | | Microgram per Meter Cube | 16.75 | 1 | 22.79 | 22.79 | 80 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | DG Set | Diesel | 15 | 0.25 | PM10 | | 30 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 500 | (b)Source | DG Sets | (c)Uploaded Copy of Agreement | Not Applicable | (d)Standby Arrangement (Details of DG Sets) | 500 KvA | (e)Stack Height (in m) | 10 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 0 | (b)Private Land (ha.) | 59.34 | (c)Government Land (ha.) | 0 | (d)Revenue Land (ha.) | 0 | (e)Other Land (ha.) | 0 | Total Land (ha.) | 59.34 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 34 | (b)Waste/Barren Land (ha.) | 5.34 | (c)Grazing/ Community Land (ha.) | 20 | (d)Surface Water Bodies (ha.) | 0 | (e)Settlements (ha.) | 0 | (f)Industrial (ha.) | 0 | (g)Forest (ha.) | 0 | (h)Mangroves (ha.) | 0 | (i)Marine Area (ha.) | 0 | (j)Others (ha.) : FALLOW | 0 | Total (ha.) | 59.34 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Green belt | | 4.8195 | NA | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Critically Polluted Area | None | 0 | None | (2.) | WLS | None | 0 | None | (3.) | NPA | None | 0 | None | (4.) | Corridors | None | 0 | None | (5.) | Wildlife Corridors | None | 0 | None | (6.) | ESZs | None | 0 | None | (7.) | ESAs | Vikramshila Gangetic Dolphin Wild Life Sanctuary | 40 | Presence of Gangetic Dolphins | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Forest | | None | 0 | None | (2.) | Others | Gangetic Dolphins | Gangetic Dolphins | 0 | Adequate mitigation and management measures suggested in EMP | (3.) | Archaeological Sites | | None | 0 | None | (4.) | Defence Installations | | None | 0 | None | |
|
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 58.212 | (b)Land yet to be acquired(Ha) | 1.188 | (c)Status of Land acquisition if not acquired | Almost complete | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 15 | (b)No. of Households | 0 | (c)No. of PDFs (Project Displaced Families) | 0 | (d)No. of PAFs (Project Affected Families) | 101 | (e)Funds Allocated for R&R(in INR) (in Lacs) | 4922 | (f)Status of R&R | Completed | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | Yes | (i)Details of Schedule-I Species | Gangetic Dolphin | (b)Whether conservation plan for Schedule-I Species has been prepared ? | Yes | (i)Uploaded copy of conservation plan | Copy of conservation plan | (ii)Fund Provision made | 147.7 Lakhs | (iii)Period of Implementation | 6 Years | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | Yes | (i)Uploaded copy of approval | Copy of approval | (ii)Letter No. | 1998 | (iii)Date of issue | 30 Nov 2018 | (iv)Recommendation | Preparation of Gangetic Dolphin Conservation plan | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | Yes | (i)Details of Water Bodies in Core Area | River Ganga | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | Yes | (i)Uploaded copy of permission | Copy of permission | (ii)Letter No. | TE-14015/02/2018/NMCG | (iii)Date of issue | 29 Nov 2018 | (iv)Recommendation | Competent Authority at the National Mission for C | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | Yes | (i)Details of Water Bodies in Buffer Area | River Ganga | (ii)Direction of Water Bodies in Buffer Area | North West | (iii)Distance of Water Bodies in Buffer Area | 0 | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 300 | (b)Permanent Employment-During Operation | 25 | (c)Temporary Employment- During Construction | 2650 | (d)Temporary Employment- During Operation | 25 | (e)No. of working days | 2190 | (f)Total Manpower | 3000 | |
|
32. | Green Belt in Ha: | (a)Total Area of Green Belt | 5 | (b)Percentage of Total Project Area | 8.43 | (c)No. of Plants to be Planted | 15303 | (d)Funds Allocated for Plantation | 13662000 | (e)Uploaded Green Belt plan | Copy of Green Belt Plan | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Social | There will be improvements in economic growth of the surrounding areas due to establishment of more shops, industries, institutions, MNCs and other organizations.
Improvement in economic and social welfare of nearby people.
Increase in access to markets, jobs, education and health services. | (2.) | Environmental | Three rows of avenue plantations are proposed on both side of the road at most of the sections as per IRC SP 21, 2009. Avenue plants proposed in the region are Albizzia lebeck, Albizzia proeera, Butea monosperma, Bauhinia variegata, Cassia fistula, Cassia siamea, Cedrela toona, Chikrassia tabularis, Calistemon lanceolatus, Dalbergia sissoo, Emblica officinalis, Ficus sp, Gravellea robusta, Hardwickia pinnata, Lagerstroemia, thorii, Lagerstroemea floriginea, Morusalba, Mangifera indica, Pterosp | (3.) | Financial | The proposed project stretch across river Ganga will reduce travel distance from approx. 180 km to approx. 15 km and it will enhance the traffic and goods transport to northern and north-eastern region. It will also provide connectivity between Jharkhand State and Bihar State.
Project road will reduce transportation cost for both freight and passengers and increase in road safety. | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details For INFRA-1 |
|
1. | Details of Building Construction: | (a)Maximum Height of the Building (Meters) | 3 | (b)Total No. of Flats to be Build | 1 | (c)No. of Buildings | 1 | (d)Total plot area (sqm) | 953100 | (e)Total built up area (sqm) | 714825 | |
|
2. | Foreshore Facilities and/or Marine Disposal: | (a)Whether Project Involves Foreshore Activities and/or marine Disposal? | No | |
|
3. | Rain Water Harvesting: | (a)No. of Storage | 1 | (b)Capacity | 0 | (c)No. of Recharge Pits | 40 | (d)Capacity | 736182 | |
|
4. | Parking: | (a)Details of 4 Wheeler/ 2 Wheeler Parking | 4 Bus bays/ bus shelters | |
|
5. | Energy Saving Measures: | (a)Source/Mode | LED Lights on Bridges and Approaches | (b)Percentage | 40 | (c)Quantity | 750 | |
|
|
7. Type of Industries to be established with Industrial Estate as per their category A/B |
---|
S. No. | Type of Industry | No. of Units | Category A/B |
---|
NIL | |
8. | Length of the alignment | 15.885 | |
|
9. | Details Bridges/ROB/Interchanges,Flyovers,Vehicle Underpass and Pedestrian Underpass | (a)Total No. of Bridges | 12 | (b)Total No. of ROB | 2 | (c)Total No. of Interchanges | 0 | (d)Total No. of Flyovers | 0 | (e)Total No. of Vehicle Underpass | 3 | (f)Total No. of Pedestrian Underpass | 1 | (g)Details of other utilities rail and road corridors | 0 | |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | NABET/EIA/1518/RA0061 | (ii)Name of the EIA Consultant | Aarvee Associates Architects Engineers and Consult | (iii)Address | 8-2-5, Ravula Residency, Srinagar Colony Main Road, Hyderabad | (iv)Mobile No. | 9490623700 | (v)Landline No. | 0402373763 | (vi)Email Id | aarvee@aarvee.net | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | INFRA-1 | (ix)Validity of Accreditation | 16 Feb 2018 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought: |
---|
Sno. | EDS Letter | Remarks | Date of EDS |
---|
1. | NA | Form 2 is not visible. Please upload again. | 09 Jan 2019 | 2. | NA | The correction have been made as per the instruction received | 10 Jan 2019 | |
Additional Detail Sought : NIL |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | Dr Biswajit Mukhopadhyay | Designation | General Manager | Name of Company (Applicant Name should not be given here) | National Highways Authority of India | Address | G-5 & 6, Sector-10, Dwarka, New DElhi-110075 |
|