Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Proposed Expansion of Cement Clinker Capacity (1.75 MTPA to 1.88 MTPA) at Village Lumshnong, Tehsil Khliehriat, District East Jaintia Hills, Meghalaya by Star Cement Meghalaya Ltd.,
(b)Name of the Company / Organisation STAR CEMENT MEGHALAYA LIMITED
(c)Registered Address Village Lumshnong, Tehsil Khliehriat, District East Jaintia Hills, Meghalaya,,East Jaintia Hills,Meghalaya-793210
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Pankaj Kejriwal
(b)Designation (Owner/ Partner/ CEO) Director
(c)Address 281, Deepali, Pitampura, New Delhi-110034,,Saraswati Vihar,North West,Delhi-110034
(d)Pin code 110034
(e)E-mail girisamk@starcement.co.in
(f)STD Code. 3655(f)Telephone No. 27033821
(g)Fax No. 278217
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity3(b) Cement plants
Minor Activity3(b) Cement plants
(b)Category A
(c)Proposal Number IA/ML/IND/89661/2018
(d)Master Proposal Number(Single Window) SW/89659/2018
(e)EAC concerned (for category A Projects only) NIL
(f)Project Type Expansion under para 7(ii)
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Patta No.15 of 2008-2009
(b)Pincode 793210
(c)Bounded Latitudes (North)
From
Degree 25.168528
Minutes
Second
From
Degree 25.183164
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 92.385361
Minutes
Second
From
Degree 92.405853
Minutes
Second
(e)Survey of India Topo Sheet No. 83 C/8
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 474
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 128.75
(j)Seismic Zone 5
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Meghalaya
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR)/EC: Not Applicable
4.
Whether the Project Exempted from Public Hearing? Details Not Applicable
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Shillong
(iii)Letter No. Ref.RO-MOEFCC/CEC/12/2018
(iv)Status of Compliance Partially Complied
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Dec 10 2018 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Clinker17500001300001880000Tons per Annum(TPA)Road
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Clinker PlantProduction of clinker for cement manufacturingProduction of clinker for cement manufacturingProduction of clinker for cement manufacturing
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 30 Jan 2018
(iv)Valid Upto 31 Jan 2019
(v)File No. MPCB/TB-115-2009/2017-2018/84
(vi)Application No. MPCB/TB-115-2009/2017-2018/84
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 5
(b) Funds Allocated for Environment Management (Capital) (in Crores) 0.25
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.05
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.05
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? Yes
c)Notified Eco-sensitive areas Yes
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 234800
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 234800
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Limestone2410000Tons per AnnumBrishyrnot/KhubRoad,Conveyor Belt2 CaptiveCopy of Linkage
(2.)Coal283800Tons per AnnumWapungRoad,Rail26 Open MarketCopy of Linkage
(3.)Mill Scale65000Tons per AnnumGuwahatiRoad230 Open MarketCopy of Linkage
(4.)Shale580000Tons per Annum135th KM stoneRoad7 Open MarketCopy of Linkage
16.
Baseline Data Not Applicable
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 0.77 To 2.86
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 0.57 To 1.40
(c)Whether Ground Water Intersection will be there ? NA
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Surface18000Copy of Permission LetterPipelineOthersPump houseAID(J)223/2008-09/16 Jun 20094900
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic waste water120400STP based on MBBR technologyOthersGreen belt & dust suppression1200
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 120
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 120
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Used or Spent OilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)5.125Kilolitre568RoadAuthorized Recyclers
(2.)STP SludgeOthersSTP Sludge35.64Tons0RoadCo-Processing
(3.)Municipal wasteMunicipal Solid Waste400.95Tons0RoadOthersutilized internally
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)SO2Microgram per Meter Cube6.4006.480
(2.)PM2.5Microgram per Meter Cube30.10030.160
(3.)PM10Microgram per Meter Cube71.30071.3100
(4.)NOxMicrogram per Meter Cube16.80016.880
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)RABHNA453OthersPM19.7
(2.)RABHNA453SO291.6
(3.)Coal MillCoal371.2SO23.4
(4.)Coal MillCoal371.2NOx2.5
(5.)Cooler ESPNA302.8OthersPM24.1
(6.)Cooler ESPNA302.8SO2BDL
(7.)Cooler ESPNA302.8NOxBDL
(8.)RABHNA453NOx119.9
(9.)Coal MillCoal371.2OthersPM22.6
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 15000
(b)Source Meghalaya Power Ltd.
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 0
(e)Stack Height (in m) 0
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 75
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 75
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 0
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 0
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Plant area 75
    Total (ha.) 75
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Main Plant0No additional land is required for expansion
Total (ha.) 0
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNA0NA
(2.)NPANA0NA
(3.)Wildlife CorridorsNA0NA
(4.)ESZsNarpuh Wildlife Sanctuary3.17from ESZ boundary
(5.)CorridorsNA0NA
(6.)WLSNarpuh Wildlife Sanctuary3.17From ESZ boundary
(7.)ESAsNA0NA
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestNarpuh Reserve Forest9.0in SE direction
(2.)Archaeological SitesNA0NA
(3.)Defence InstallationsNA0NA
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 75
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired NA
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species Asian Leopard Cat, Hog Badger, Assam Bamboo Partridge, Hoolock gibbon, Family Hylobatiedae, Serow and Slow Loris
(b)Whether conservation plan for Schedule-I Species has been prepared ? Yes
(i)Uploaded copy of conservation plan Copy of conservation plan
(ii)Fund Provision made 115 Lakh
(iii)Period of Implementation NA
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? Yes
(i)Uploaded copy of approval Copy of approval
(ii)Letter No. MFG.16/50/CMCL/Vol-II/3007
(iii)Date of issue 09 Dec 2015
(iv)Recommendation NA
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area Umtyrngai Nallah-adjacent to the plant premises
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? Yes
(i)Uploaded copy of permission Copy of permission
(ii)Letter No. AID(J)223/2008-09/
(iii)Date of issue 16 Jun 2009
(iv)Recommendation NA
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Um-Lunar River- 3.0 Km E, Lubha River- 4.5 Km SE
(ii)Direction of Water Bodies in Buffer Area South East
(iii)Distance of Water Bodies in Buffer Area 3.0
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 170
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 0
(e)No. of working days 330
(f)Total Manpower 170
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt25025
(2.)Percentage of Total Project Area33033
(3.)No. of Plants44920044920
(4.)Funds Allocated95095
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)EnvironmentalReduction in energy consumption and better control of fugitive dust.
(2.)SocialIncreased in indirect employment due to additional transportation.
(3.)FinancialReduction in overhead expanses will increase revenue per ton and Government will benefit from addition of tax collection.
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 1
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. 117
(ii)Name of the EIA Consultant Perfact Enviro Solutions Pvt. Ltd.
(iii)Address 5th Floor, NN Mall, Mangalam Palace, Sector 3, Rohini, New Delhi-110085
(iv)Mobile No. 9818346370
(v)Landline No. 0114928137
(vi)Email Id info@perfactgroup.in
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 1
(ix)Validity of Accreditation 27 May 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAKindly resubmit the application afresh along with the certified compliance report from Regional office - Shillong and detailed technical documentation inter-alia including proposed process modifications, impact prediction, pollution load assessment etc., 23 Jan 2019
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantPankaj Kejriwal
DesignationDirector
Name of Company (Applicant Name should not be given here)STAR CEMENT MEGHALAYA LIMITED
AddressVillage Lumshnong, Tehsil Khliehriat, District East Jaintia Hills, Meghalaya