Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Everest Organics Limited
(b)Name of the Company / Organisation EVEREST ORGANICS LIMITED
(c)Registered Address Sy no. 38,38A,39,40,40A & 45, Aroor (V), Sadasiva pet (M), Medak (Dist), Telangana,,Medak,Telangana-502299
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Dr S K Srihari Raju Dr S K Srihari Raju
(b)Designation (Owner/ Partner/ CEO) Managing Director
(c)Address Plot no 127 & 128, First floor, Amar cooperative society, near Durgam Cheruvu, Madhapur, Hyderabad,,Serilingampalle,Rangareddi,Telangana-500033
(d)Pin code 500033
(e)E-mail parvatisem@gmail.com
(f)STD Code. 8455(f)Telephone No. 250113
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
Minor Activity
(b)Category A
(c)Proposal Number IA/TG/IND2/88987/2016
(d)Master Proposal Number(Single Window) SW/88949/2018
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Sy. No 38, 38A,39,40A & 45
(b)Pincode 502291
(c)Bounded Latitudes (North)
From
Degree 173826.1
Minutes
Second
From
Degree 173843.9
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 775138.6
Minutes
Second
From
Degree 775149.8
Minutes
Second
(e)Survey of India Topo Sheet No. 56/G/14
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 565
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 11
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Telangana
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number J-11011/328/2016-IA.II(I)
(c)Date of Issue of TOR 09 Dec 2016
(f)Previous TOR Letter Copy of Previous TOR letter
(b)Date of Apply of EC 19 Dec 2018
(c)Date of Issue of EC 19 Dec 2018
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :15 Jun 2018
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :17 Jul 2018
Distance of Public Hearing Venue from the Proposed Project :0
Everest Organics Limited, Proposed site Premises
State :Telangana
District :Medak
Tehsil :Sadasivpet
Village :Aroor
100To Provide employment to locals, Prevent pollution from the industry and take measures to prevent pollutionOthersJoint Collector & Addl. District Magistrate
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Chennai
(iii)Letter No. EP/12.1/347/AP/1476
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Jul 28 2017 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Bulk drugs and Intermediates145.5935.71081.2Tons per Annum(TPA)Road
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Production capacity145.51081.21081.2Expansion
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 22 Nov 2017
(iv)Valid Upto 28 Feb 2022
(v)File No. TSPCB/RCP/SRD/CFO&HWA/HO/2017-2714
(vi)Application No. TSPCB/RCP/SRD/CFO&HWA/HO/2017-2714
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 8.5
(b) Funds Allocated for Environment Management (Capital) (in Crores) 3.0
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.4
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 1.28
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 20
(b)Existing quantity of raw material/fuel 20
(c)Total quantity of raw material/fuel 40
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)3-Iso butyl Glutaric anhydride98.5Tons per AnnumLocal MarketRoad500 Open MarketCopy of Linkage
(2.)3-chloro propionyl chloride25.79Tons per AnnumLocal MarketRoad500 Open MarketCopy of Linkage
(3.)1,4-dibromo butane21.16Tons per AnnumLocal MarketRoad500 Open MarketCopy of Linkage
(4.)2,3-Lutidine78.05Tons per AnnumLocal MarketRoad500 Open MarketCopy of Linkage
(5.)2-mercapto benzimidazole49.84Tons per AnnumLocal MarketRoad500 Open MarketCopy of Linkage
(6.)4-chloro 4-hydroxy benzophenone20.02Tons per AnnumLocal MarketRoad500 Open MarketCopy of Linkage
(7.)2,3-dichloroaniline13.12Tons per AnnumLocal marketRoad500 Open MarketCopy of Linkage
(8.)3,5-Lutidine224.53Tons per AnnumLocal MarketRoad500 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Jan 2017 To 31 Mar 2017
(b)Season Summer
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM2.5Micro Gram per Meter Cube34.216.733.8560
(2.)OthersNH3Micro Gram per Meter Cube32.418.232.11400
(3.)PM10Micro Gram per Meter Cube82.347.281.59100
(4.)NOxMicro Gram per Meter Cube21.312.321.1280
(5.)SO2Micro Gram per Meter Cube18.28.318.080
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA7.727.166.58.5
(2.)TDSmg/l12362945002000
(3.)Total Hardnessmg/l706.5106200600
(4.)Chloridesmg/l321.9446.82501000
(5.)TSSNA0000
(6.)Heavy MetalsPbmg/l0.0060.0010.010
(7.)Fluoridemg/l0.890.451.01.5
    14.3.     No. of Surface Water monitoring locations : 5
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHmg/l8.87.38B
(2.)BODmg/l9.74.3B
(3.)OthersTDSmg/l432194B
(4.)DOmg/l1.60.8B
(5.)CODmg/l10457B
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))63.243.475
(2.)Leq(Night)A-weighted decibels(dB(A))56.236.470
    14.5.     No. of Soil Sample Monitored locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pHOthersNA8.357.5
(2.)N(Nitrogen)Percent0.040.01
(3.)P(Phosphorus)Kilogram per hectare67.950.98
(4.)K(Potassium)Kilogram per hectare13266
(5.)Electric ConductivityOthersµmhos/cm373165
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 4 To 4
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 18 To 18
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater219.70Copy of Permission LetterPipelineTube WellGWD/T/2058/2015-1415 Jul 2015105
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Ground water138.7150Zero liquid dischargeReuse within the Plant & Recycling138.7
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 138.7
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 138.7
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Distillation bottom residueHazardous Waste (as per Hazardous and Other Waste Management rules 2016)36Tons50RoadCo-Processing
(2.)Organic residueHazardous Waste (as per Hazardous and Other Waste Management rules 2016)519.6Tons50RoadCo-Processing
(3.)Waste oilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)0.216Kilolitre50RoadAuthorized Recyclers
(4.)Process and ETP SludgeHazardous Waste (as per Hazardous and Other Waste Management rules 2016)488.4Tons50RoadTreatment, Storage and Disposal Facility(TSDF)
(5.)Inorganic saltsHazardous Waste (as per Hazardous and Other Waste Management rules 2016)248.4Tons50RoadTreatment, Storage and Disposal Facility(TSDF)
(6.)MEE saltsHazardous Waste (as per Hazardous and Other Waste Management rules 2016)2473.2Tons50RoadTreatment, Storage and Disposal Facility(TSDF)
(7.)Off- Specification productsHazardous Waste (as per Hazardous and Other Waste Management rules 2016)12Tons50RoadCo-Processing
(8.)Spent carbonHazardous Waste (as per Hazardous and Other Waste Management rules 2016)86.4Tons50RoadCo-Processing
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube65.33.21.32166.62100
(2.)PM2.5Microgram per Meter Cube26.23.20.65226.85260
(3.)NOxMicrogram per Meter Cube20.23.24.40824.60880
(4.)SO2Microgram per Meter Cube15.23.23.35918.55980
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)8 TPH coal fired boilerCoal301.0NOx1.95
(2.)1000 KVA DG SetDiesel201.0PM100.04
(3.)8 TPH Coal Fired BoilerCoal301.0PM100.56
(4.)8 TPH Coal Fired BoilerCoal301.0SO21.46
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 1885
(b)Source TSCPDCL
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 1 X125, 2 X 380, 1 x 1000 KVA
(e)Stack Height (in m) 30
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 13.35
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 13.35
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 26314
(b)Waste/Barren Land (ha.) 3595.4
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 364.2
(e)Settlements (ha.) 1199.2
(f)Industrial (ha.) 0
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : 0 0
    Total (ha.) 31472.800000000003
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Built Up Area4.04
(2.)Green belt8.9
(3.)OthersOpen area0.4
Total (ha.) 13.34
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)ESAsNone0None
(2.)ESZsNone0None
(3.)CorridorsNone0None
(4.)Wildlife CorridorsNone0None
(5.)WLSNone0None
(6.)NPANone0None
(7.)Critically Polluted AreaNone0None
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Archaeological SitesNone0None
(2.)Defence InstallationsNone0None
(3.)ForestNone0None
(4.)OthersNoneNone0None
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 13.35
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired Already acquired and in possession of the company
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area Lakshminarayan Cheruvu is at distance of 0.45 Km from site in North direction
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 100
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 50
(e)No. of working days 365
(f)Total Manpower 150
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt22.0022
(2.)Percentage of Total Project Area66.6066.6
(3.)No. of Plants10021121
(4.)Funds Allocated05.05
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialProvides employment to 150 people
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. S.No 122, Rev 71 dated 12th November, 2018
(ii)Name of the EIA Consultant Pridhvi Envirotech Private Limited
(iii)Address 184/C, Lawn House, Vengal rao Nagar, Hyderabad
(iv)Mobile No. 9849023662
(v)Landline No. 4040179770
(vi)Email Id pvr@pridhvienviro.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 01 Jun 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAPlease inform about EC for the present production of 145.5 TPA, and the compliance status thereof. 29 Dec 2018
2.NAThe correction have been made as per the instruction received 31 Dec 2018
3.NA- Entry at column 6 of form-2 to be made as per the EC dated 15/7/2005. Also, please submit a copy of the said EC to examine the consistency of products details vis-a-vis the CTO issued and the present proposal. - State Ground Water Department has restricted the water requirement to 105 KLD. How the proposed requirement of 219.7 KLD (shown in column 15) shall be met. - 06 Jan 2019
4.NAThe correction have been made as per the instruction received 10 Jan 2019
5.NAPlease refer our observations dated 6/1/2019. It is to inform that entries at column 6 of Form-2 are yet to be corrected. Also, copies of the EC dated 15/7/2005 followed by corrigendum dated 13/4/2006, are yet to be uploaded. It is also requested to inform acceptance status of the proposal for ground water withdrawal of 125 cum/day. 17 Jan 2019
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantDr S K Srihari Raju Dr S K Srihari Raju
DesignationManaging Director
Name of Company (Applicant Name should not be given here)EVEREST ORGANICS LIMITED
AddressSy no. 38,38A,39,40,40A & 45, Aroor (V), Sadasiva pet (M), Medak (Dist), Telangana