Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Capacity Augmentation of Speciality Chemicals from 11000 TPA to 22000 TPA within existing plant at Konnagar, Hooghly district, West Bengal
(b)Name of the Company / Organisation NALCO WATER INDIA LIMITED KONNAGAR
(c)Registered Address NALCO Water India Limited 1, Lenin Sarani P.O. Konnagar District - Hooghly West Bengal,,Hooghly,West Bengal-712235
(d)Legal Status of the Company Others
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Sudhanya Sen
(b)Designation (Owner/ Partner/ CEO) Plantmanager
(c)Address NALCO Water India Limited 1 Lenin Sarani P O Konnagar District Hooghly West Bengal 712235,,Serampur Uttarpara,Hooghly,West Bengal-712235
(d)Pin code 712235
(e)E-mail ssen@ecolab.com
(f)STD Code. 33(f)Telephone No. 26740296
(g)Fax No. 26722287
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
Minor Activity
(b)Category A
(c)Proposal Number IA/WB/IND2/87601/2016
(d)Master Proposal Number(Single Window) SW/87353/2018
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Dag no 639, 640, 641 & 722
(b)Pincode 712235
(c)Bounded Latitudes (North)
From
Degree 224253.0
Minutes
Second
From
Degree 224353.30
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 882037.0
Minutes
Second
From
Degree 882037.75
Minutes
Second
(e)Survey of India Topo Sheet No. 79 B/5 B/6
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 14
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 0
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project West Bengal
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number J-11011/360/2016-IA-II(I)
(b)Date of Apply of TOR 06 Dec 2016
(c)Date of Issue of TOR / Standard ToR 28 Feb 2017
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :06 Jul 2018
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :09 Aug 2018
Distance of Public Hearing Venue from the Proposed Project :1
Ambedkar Bhawan, Jawarharlal Sarani, Konnagar
State :West Bengal
District :Hooghly
Tehsil :Serampur Uttarpara
Village :Konnagar
250Employment, Environment management and CSROthersAdditional District Magistrate
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Speciality ChemicalsExpansion from 11000 TPA to 22000 TPACapacity Augmentation of Speciality chemicals
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Water treatment chemicals, Industrial additives, oil field chemicals22000Tons per AnnumRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 27 Jun 2017
(iv)Valid Upto 31 Mar 2022
(v)File No. 292/PCB/HGY/R/85-97
(vi)Application No. C1109924
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 10
(b) Funds Allocated for Environment Management (Capital) (in Crores) 0.06
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.52
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.0011
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 450
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 450
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Polymers10OthersTPMKolkata portRoad25 LinkageCopy of Linkage
(2.)Organic Compounds200OthersTPMKolkata PortOthersSea route25 LinkageCopy of Linkage
(3.)Organic alcohol70OthersTPMKolkata portOthersSea route25 LinkageCopy of Linkage
(4.)Inorganic Acids120OthersTPMWB and MaharashtraRoad,OthersSea route40 MoUCopy of Linkage
(5.)Other inorganic compounds140OthersTPMWB, Gujarat, Maharashtra etcRoad40 MoUCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Dec 2016 To 28 Feb 2017
(b)Season Winter
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)SO2Nano Gram per Meter Cube14.68.413.880
(2.)NOxMicro Gram per Meter Cube18.311.517.680
(3.)PM10Micro Gram per Meter Cube45.818.744.1100
(4.)PM2.5Micro Gram per Meter Cube24.810.724.660
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA7.827.026.58.5
(2.)Fluoridemg/l1.10.71.51.0
(3.)Total Hardnessmg/l588402200600
(4.)Heavy MetalsIronmg/l0.080.010.30
(5.)TSSmg/l0000
(6.)Chloridesmg/l421.6317.51000250
(7.)TDSmg/l139710945002000
    14.3.     No. of Surface Water monitoring locations : 4
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA9.77.3A
(2.)BODmg/l2.52.0A
(3.)CODmg/l2512A
(4.)DOmg/l5.85.2A
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))58.344.575
(2.)Leq(Night)A-weighted decibels(dB(A))55.141.370
    14.5.     No. of Soil Sample Monitored locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pHOthersNA8.36.5
(2.)N(Nitrogen)Kilogram per hectare517.473.6
(3.)Electric ConductivityOthersmicromhos per cm50489
(4.)K(Potassium)Kilogram per hectare516.277.4
(5.)P(Phosphorus)Kilogram per hectare402.862.8
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 0.4 To 18.69
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 0.39 To 14.75
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater1100Copy of Permission LettermodeOthersBorewellTube Well06011 Nov 2018110
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Industrial32100Activated sludge processReuse within the Plant & Recycling32
(2.)Domestic18100Activated Sludge processReuse within the Plant & Recycling18
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 50
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 50
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Spent oilIndustrial Waste0.24Kilolitre10RoadAuthorized Recyclers
(2.)ETP sludgeIndustrial Waste12Tons10RoadAuthorized Recyclers
(3.)Polymeric wasteIndustrial Waste240Tons10RoadAuthorized Recyclers
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube45.810.8046.6100
(2.)PM2.5Microgram per Meter Cube24.810.3825.1860
(3.)NOxMicrogram per Meter Cube118.310.8019.180
(4.)SO2Microgram per Meter Cube14.611.1515.780
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)Steam generator-1Diesel150.4SO2107 mg/nm3
(2.)DG set-1Diesel320.35NOx108 mg/nm3
(3.)Steam Generator-2Diesel150.4SO297 mg/nm3
(4.)DG set-1Diesel320.35SO2145 mg/nm3
(5.)Steam generator-1Diesel150.4PM1072 mg/nm3
(6.)Steam generator-1Diesel150.4NOx78 mg/nm3
(7.)DG set-IDiesel320.35PM1044
(8.)Steam generator-2Diesel150.4PM1065
(9.)Steam generator-2Diesel150.4NOx64
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 2000000
(b)Source Calcutta Electricity supply corporation
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 1
(e)Stack Height (in m) 32
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 2.02
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 2.02
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 0
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 2.02
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Nil 0
    Total (ha.) 2.02
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Main Plant3.35nil
(2.)Green belt0.65Nil
(3.)OthersVacant area1Nil
Total (ha.) 5
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNil0Nil
(2.)WLSNil0Nil
(3.)ESAsNil0Nil
(4.)CorridorsNil0Nil
(5.)Wildlife CorridorsNil00
(6.)NPANil0Nil
(7.)ESZsNil0Nil
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestNil0Nil
(2.)Archaeological SitesNil0Nil
(3.)Defence InstallationsNil0Nil
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 2.02
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Hooghly river
(ii)Direction of Water Bodies in Buffer Area East
(iii)Distance of Water Bodies in Buffer Area 1.3
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 11
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 22
(e)No. of working days 365
(f)Total Manpower 33
32.
Green Belt in Ha:
(a)Total Area of Green Belt 0.65
(b)Percentage of Total Project Area 32.18
(c)No. of Plants to be Planted 1500
(d)Funds Allocated for Plantation 50000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.       Project Benefits
S. No. Type of Project BenefitsDetails of Project Benefits
NIL
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1619/RA0043
(ii)Name of the EIA Consultant Vimta Labs Limited
(iii)Address Vimta Labs Limited, IDA, Phase-II, Cherlapally
(iv)Mobile No. 9000711309
(v)Landline No. 0402726414
(vi)Email Id janardhan@vimta.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 19 Nov 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File NA
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAPlease inform/clarify the following:- - Status of EC for the present industrial operations having production of specialty chemicals of 11000 TPA, and the compliance status thereof. - The consultant is not accredited for preparing the EIA/EMP report for the said project covered under category A of item 5(f) of the schedule to the EIA Notification, 2006. - Status of clearance for ground water withdrawal of 110 cum/day to cater to the proposed expansion. - CTO shows the present production of 1000 TPM. As such, the information given in column 9(b) of Form-2 needs to be confirmed. 16 Dec 2018
2.NAThe correction have been made as per the instruction received 24 Dec 2018
3.NARequest for withdrawal of the proposal accepted. 30 Dec 2018
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantSudhanya Sen
DesignationPlantmanager
Name of Company (Applicant Name should not be given here)NALCO WATER INDIA LIMITED KONNAGAR
AddressNALCO Water India Limited 1, Lenin Sarani P.O. Konnagar District - Hooghly West Bengal