Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) The Proposed Capacity Enhancement by Increasing Pulp Production from 62,000 BD TPA to 90,000 BD TPA by upgrading the existing pulp mill without increasing the permitted paper production capacity of 1,
(b)Name of the Company / Organisation ORIENT PAPER MILLS
(c)Registered Address PO, Amlai Paper Mills, District Shadhol, Madhya Pradesh,,Shahdol,Madhya Pradesh-484117
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Ajay Gupta
(b)Designation (Owner/ Partner/ CEO) Chief Executive Officer
(c)Address PO, amlai Paper Mills, district Shadhol, Madhya Pradesh,,,Shahdol,Madhya Pradesh-484117
(d)Pin code 484117
(e)E-mail unit-amlai@orientpaperindia.com
(f)STD Code. 7652(f)Telephone No. 286273
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(i) Pulp & paper industry excluding manufacturing of paper from waste
Minor Activity
(b)Category A
(c)Proposal Number IA/MP/IND/49845/2016
(d)Master Proposal Number(Single Window) SW/85065/2018
(e)EAC concerned (for category A Projects only) Industrial Projects - 1
(f)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Jhagraha Village- 1370,1372, 1373, 1374, 1375, 137
(b)Pincode 484117
(c)Bounded Latitudes (North)
From
Degree 23.188036
Minutes
Second
From
Degree 23.199251
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 81.589983
Minutes
Second
From
Degree 81.596057
Minutes
Second
(e)Survey of India Topo Sheet No. 66 E/12
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 500
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 2.5
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Madhya Pradesh
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)Madhya PradeshShahdolSohagpur
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number J-11011/1142/2007-IA-II (I)
(c)Date of Issue of TOR 29 Jan 2016
(f)Previous TOR Letter Copy of Previous TOR letter
(b)Date of Apply of EC 17 Feb 2016
(c)Date of Issue of EC 28 Jan 2019
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :22 Sep 2018
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :23 Oct 2018
Distance of Public Hearing Venue from the Proposed Project :0
Project Site OPM Sikshan Sansthan
State :Madhya Pradesh
District :Shahdol
Tehsil :Sohagpur
Village :Amlai
202Additional CSR activities to be undertaken. Zero Liquid Discharge to River as per existing practices to be continued during post project scenarioDistrict Magistrate
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Bhopal
(iii)Letter No. 5-210/2008 (ENV)/1259
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Mar 14 2018 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Pulp Production620002800090000Tons per Annum(TPA)OthersCaptive Usage
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)In House pulp mill capacity62000 TPA28000 TPA100000The existing chlorine based bleaching technology will be replaced with ECF bleaching.
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 07 May 2018
(iv)Valid Upto 30 Apr 2019
(v)File No. AW-48319
(vi)Application No. /MPPCB/SDL
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 40
(b) Funds Allocated for Environment Management (Capital) (in Crores) 28
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.4
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 5
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 80000
(b)Existing quantity of raw material/fuel 160000
(c)Total quantity of raw material/fuel 240000
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Wood80000Tons per AnnumCaptive and Farm ForestryRoad0 CaptiveCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 16 Apr 2018 To 17 Jul 2018
(b)Season Pre-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM2.5Micro Gram per Meter Cube54.035.154.060
(2.)OthersOzoneMicro Gram per Meter Cube40.516.539.8180
(3.)SO2Micro Gram per Meter Cube17.65.916.380
(4.)PM10Micro Gram per Meter Cube93.570.393.4100
(5.)NOxMicro Gram per Meter Cube47.319.646.880
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA7.607.126.58.5
(2.)TSSmg/l0000
(3.)TDSmg/l5302285002000
(4.)Chloridesmg/l110.4038.102501000
(5.)Heavy MetalsLeadmg/l000.010.01
(6.)OthersNitratemg/l24.5224545
(7.)Fluoridemg/l0.750.4211.5
(8.)Total Hardnessmg/l275118200600
    14.3.     No. of Surface Water monitoring locations : 2
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)DOmg/l7.26.5C
(2.)BODmg/l00C
(3.)CODmg/l00C
(4.)OthersTurbidityOthersNTU1410C
(5.)pHNA7.367.21C
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))52.6148.1055
(2.)Leq(Night)A-weighted decibels(dB(A))43.6439.5245
    14.5.     No. of Soil Sample Monitored locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pHOthersNA8.427.63
(2.)N(Nitrogen)Kilogram per hectare358286
(3.)P(Phosphorus)Kilogram per hectare19.3414.35
(4.)K(Potassium)Kilogram per hectare337206
(5.)Electric ConductivityMillisiemens per Centimetre0.4800.360
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 13.75 To 3.03
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 1.66 To 17.86
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Surface172253Copy of Permission LetterPipelineIntake WellLetter from MPWRD dated 9th Sep 201009 Sep 201036000
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Overall Plant926520500Biological Treatment PlantOthersLand Irrigation2509015
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 9265
(b)Total Discharged Water (Kilolitre per Day) 9015
(c)Total Reused Water (Kilolitre per Day) 250
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Fly ashFly Ash54400Tons200RoadOthersCement/brick manufacturing
(2.)Lime gritIndustrial Waste5100Tons0OthersNot ApplicableOthersFilling low lying areas within the mill
(3.)Spent OilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1700Kilolitre500RoadAuthorized Recyclers
(4.)Wood DustIndustrial Waste5100Tons0OthersNot ApplicableOthersAs fuel in boilers
(5.)Lime SludgeIndustrial Waste20400Tons0OthersNot ApplicableOthersReburnt in limekiln
(6.)ETP sludge from primary clarifierHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1700Tons100RoadOthersFor board manufacturing
(7.)ETP sludge from secondary clarifierHazardous Waste (as per Hazardous and Other Waste Management rules 2016)340Tons0OthersNot ApplicableOthersAs fuel in boilers
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube93.510.6594.15100
(2.)Others(Specify)AmmoniaMicrogram per Meter Cube19.2000180
(3.)PM2.5Microgram per Meter Cube54.510.6555.1560
(4.)SO2Microgram per Meter Cube15.2911.0516.3480
(5.)NOxMicrogram per Meter Cube42.8910.7543.6480
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)Chemical Recovery BoilerBlack Liquor Solids433PM103
(2.)Chemical Recovery BoilerBlack Liquor Solids433SO22
(3.)Chemical Recovery BoilerBlack Liquor Solids433NOx1
(4.)Lime KilnFurnace Oil501.8PM100.612
(5.)Lime kilnFurnace Oil501.8NOx0.51
(6.)Lime KilnFurnace Oil501.8SO20.2
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 37000
(b)Source Captive Power Plant
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) Not Applicable
(e)Stack Height (in m) 86
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 598.53
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 598.53
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 0
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 598.53
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Not applicable 0
    Total (ha.) 598.53
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Main Plant0No additional land requirement
Total (ha.) 0
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNA0Not applicable
(2.)ESAsNA0NA
(3.)ESZsNA0NA
(4.)CorridorsNA0NA
(5.)WLSNA0NA
(6.)NPANA0NA
(7.)Wildlife CorridorsNA0NA
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestBurhar, Maikal and Mauhari8South Western Side
(2.)Defence InstallationsNA0NA
(3.)OthersNot ApplicableNA0NA
(4.)Archaeological SitesNA0NA
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 598.53
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired Not Applicable
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area Sone River 2.3 km East
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Semra Dam
(ii)Direction of Water Bodies in Buffer Area North West
(iii)Distance of Water Bodies in Buffer Area 8.9
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 0
(c)Temporary Employment- During Construction 100
(d)Temporary Employment- During Operation 0
(e)No. of working days 340
(f)Total Manpower 100
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt2560256
(2.)Percentage of Total Project Area43043
(3.)No. of Plants5000000500000
(4.)Funds Allocated50050
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialCorporate Environment Responsibility for community development
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 1
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1518/SA 037
(ii)Name of the EIA Consultant Cholamandalam MS Risk Services Limited
(iii)Address Parry House, 3rd Floor, No.2, NSC Bose Road, Chennai- 600001
(iv)Mobile No. 967700377
(v)Landline No. 0443044562
(vi)Email Id bhaskarvs@cholams.murugappa.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 1
(ix)Validity of Accreditation 16 Nov 2018
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File NA
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantAjay Gupta
DesignationChief Executive Officer
Name of Company (Applicant Name should not be given here)ORIENT PAPER MILLS
AddressPO, Amlai Paper Mills, District Shadhol, Madhya Pradesh