Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Expansion cum Modification of 0.85 MTPA Integrated steel Plant with 184 MW power plant of M/s Super Smelters Ltd
(b)Name of the Company / Organisation SUPER SMELTERS LIMITED
(c)Registered Address 39, Shakespeare Sarani, 'PREMLATA', 3rd Floor, Kolkata-700017, West Bengal,,Burdwan,West Bengal-700017
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant BISHNU KUMAR BAJAJ
(b)Designation (Owner/ Partner/ CEO) DGM finance and Corporate Rela
(c)Address 39, Shakespeare Sarani, 'PREMLATA' 3rd Floor, Kolkata-700017, West Bengal,,Kanksa,Burdwan,West Bengal-700017
(d)Pin code 700017
(e)E-mail bishnu.bajaj@supershakti.in
(f)STD Code. 33(f)Telephone No. 22892734
(g)Fax No. 22892735
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity3(a) Metallurgical industries (ferrous & non ferrous)
Minor Activity
(b)Category A
(c)Proposal Number IA/WB/IND/30645/2008
(d)Master Proposal Number(Single Window) SW/85002/2018
(e)EAC concerned (for category A Projects only) Industrial Projects - 1
(f)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. 1950,1958,1959,1961,1966,2005,2028,2031,2032,2033,
(b)Pincode 713362
(c)Bounded Latitudes (North)
From
Degree 234031.59
Minutes
Second
From
Degree 234142.19
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 870535.51
Minutes
Second
From
Degree 870602.38
Minutes
Second
(e)Survey of India Topo Sheet No. F45D2
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 117
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 6.8
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project West Bengal
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number J-11011/86/2008-IA II (I)
(c)Date of Issue of TOR 02 Feb 2008
(f)Previous TOR Letter Copy of Previous TOR letter
(b)Date of Apply of EC 09 Nov 2018
(c)Date of Issue of EC 12 Feb 2019
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :30 May 2017
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :30 Jun 2017
Distance of Public Hearing Venue from the Proposed Project :4
Meeting hall, Borough-1
State :West Bengal
District :Burdwan
Tehsil :Kanksa
Village :Jamuria
51Steps for pollution control, Measures for green belt, Contribution for development of schools and roads, Employment to local youth, steps taken for health and sanitation, concern on ground water depleOthersDMDC
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Bhubaneswar
(iii)Letter No. 102-278/EPE/911
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Jun 14 2017 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Integrated Steel Plant8500000850000Tons per Annum(TPA)Road,Rail
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Sinter Plant01x60 m2 ,1x15 m21x60 m2, 1x15m2
(2.)Coal washey00.9 MTPA0.9 MTPA
(3.)AOD1x45 T01x45 T
(4.)Rolling Mill0.316 MTPA AS0.396 MTPA MS, 0.142 MTPA SS0.316 MTPA AS, 0.396 MTPA MS, 0.142 MTPA SS
(5.)CPP WHRB22 MW29 MW( 20 MW -DRI, 9 MW-BF & Coke Oven)51 MW
(6.)I/O beneficiation02 MTPA2 MTPA
(7.)Pellet Plant0.6 MTPA0.6 MTPA1.2 MTPA
(8.)MBF01x380 m3, 1x65 m31x380 m3, 1x65 m3
(9.)Lime Plant0120 TPD120 TPD
(10.)Oxygen Plant13 TPD107 TPD120 TPD
(11.)DRI Kilns2x100 TPD, 3x300 TPD2x500 TPD2x100 TPD, 3x300 TPD,2x500 TPD
(12.)IF2x25 T4x20 T, 2x25 T4x20 T, 4x25 T
(13.)SAF2x9 MVA (Fe-Cr)2x9 MVA (Fe-Cr), 1x9 MVA(Fe-Mn), 1x9 MVA(Si-Mn)4x9 MVA(Fe-Cr), 1x9 MVA(Fe-Mn), 1x9 MVA(Si-Mn)
(14.)CPP -FBC37 MW96 MW133 MW
(15.)Coke Oven00.5 MTPA0.5 MTPA
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 03 Jul 2017
(iv)Valid Upto 28 Feb 2019
(v)File No. CO109121
(vi)Application No. CO109121
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 2800.59
(b) Funds Allocated for Environment Management (Capital) (in Crores) 147.84
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 12.75
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 5
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 5857650
(b)Existing quantity of raw material/fuel 0
(c)Total quantity of raw material/fuel 5857650
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Iron Ore fines2040000Tons per AnnumBarbilRail253 LinkageCopy of Linkage
(2.)Chrome Ore140000Tons per AnnumSukindaRail326 LinkageCopy of Linkage
(3.)Dolomite92800Tons per AnnumSundergarhRail358 LinkageCopy of Linkage
(4.)Iron ore650000Tons per AnnumBarbilRail253 LinkageCopy of Linkage
(5.)Coking coal715000Tons per AnnumSouth AfricaOthersship531 LinkageCopy of Linkage
(6.)Mn ore70000Tons per AnnumBarbilRail253 LinkageCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Dec 2016 To 28 Feb 2017
(b)Season Winter
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube80.458.480.3100
(2.)SO2Micro Gram per Meter Cube3020.93080
(3.)NOxMicro Gram per Meter Cube20.812.820.880
(4.)OthersCOMicro Gram per Meter Cube458.2333457.62000
(5.)PM2.5Micro Gram per Meter Cube38.627.438.560
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TDSmg/l4212875002000
(2.)Total Hardnessmg/l260128300600
(3.)Fluoridemg/l0.420.2811.5
(4.)Chloridesmg/l88.9261.22501000
(5.)Heavy MetalsZincmg/l0.0050.002515
(6.)pHNA7.126.5378.5
(7.)TSSmg/l0000
    14.3.     No. of Surface Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA8.16.8C
(2.)CODmg/l4.53C
(3.)OthersTDSmg/l558285C
(4.)BODmg/l3.02.0C
(5.)DOmg/l8.44.6C
    14.4.     No. of Ambient Noise monitoring locations : 6
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))46.641.655
(2.)Leq(Night)A-weighted decibels(dB(A))39.130.245
    14.5.     No. of Soil Sample Monitored locations : 6
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pHOthersNA6.716.21
(2.)N(Nitrogen)Percent0.450.32
(3.)P(Phosphorus)Percent0.170.12
(4.)K(Potassium)Percent0.300.22
(5.)Electric ConductivityOthersmicromhos/cm320302
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 2.23 To 4.23
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 1.82 To 2.3
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater33757.3Copy of Permission LetterPipelineOthersfrom river bed through Submersible Pump066267,066266,06626924 Apr 20123375
(2.)Surface89760Copy of Permission LetterPipelineOthersThrough Asansol Durgapur Development AuthorityCEO2.12.0805 Jan 20102350
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Industrial46295000ETPReuse within the Plant & Recycling4629
(2.)Domestic230250STPGreen Belt Renewal Plant230
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 4859
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 4859
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Coal washery middling & rejectsIndustrial Waste405000Tons0Conveyor BeltCo-Processing
(2.)BF Dust & SludgeIndustrial Waste219840Tons0Conveyor BeltCo-Processing
(3.)CPPFly Ash351792Tons0RoadOthersOwn brick Manufacturing plant
(4.)CPPBottom Ash239904Tons0RoadOthersOwn brick manufacturing plant
(5.)Fe-Cr SlagIndustrial Waste63800Tons0RoadOthersRoad construction after TCLP test
(6.)IF slagIndustrial Waste93500Tons1RoadOthersOwn low land filling
(7.)DolcharIndustrial Waste10800Tons0Conveyor BeltCo-Processing
(8.)AOD slagIndustrial Waste55920Tons4.3RoadAuthorized Recyclers
(9.)Fe-Mn slagIndustrial Waste24700Tons0Conveyor BeltCo-Processing
(10.)Si-Mn slagIndustrial Waste13800Tons4.3RoadAuthorized Recyclers
(11.)DRIFly Ash106760Tons10RoadOthersDump in Open cast pit of ECL
(12.)BF slagIndustrial Waste137400Tons3RoadAuthorized Recyclers
(13.)I/O tailingsIndustrial Waste751190Tons10RoadOthersDump in Open cast pit of ECL
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)SO2Microgram per Meter Cube304.003080
(2.)PM2.5Microgram per Meter Cube38.550.53960
(3.)NOxMicrogram per Meter Cube17.66.516.534.180
(4.)PM10Microgram per Meter Cube805.00.4680.46100
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)PelletCoal & BF gas321.5PM100.105
(2.)PelletCoal & BF gas321.5SO28.79
(3.)Sinter 60 m2Coal552.0PM100.010
(4.)Sinter 60 m2Coal552SO224.6
(5.)Sinter 60m2Coal552NOx16.8
(6.)Sinter 15m2Coal361.0NOx4.2
(7.)DRI 500 TPDCoal482.2PM100.03
(8.)2x25 T IFELectricity301.8PM100.02
(9.)2x20 T IFElectricity301.8PM100.015
(10.)380m3 MBFCoke301.6PM100.061
(11.)65 m3 MBFCoke300.8PM100.011
(12.)Sinter 15m2Coal361.0SO26.15
(13.)8 mW CFBCCoal & Char401.5PM100.005
(14.)8 MW CFBCCoke & Char401.5SO28.67
(15.)Lime PlantCoal402.4NOx10.5
(16.)stack attached to travelling grate of pellet plantNA301.5PM100.048
(17.)DRI 500 TPDCoal482.2SO215.65
(18.)Lime plantCoal402.4PM100.2
(19.)DRI II 500 TPDCoal482.2SO215.65
(20.)Sinter 15m2Coal361.0PM100.003
(21.)DRI II 500 TPDCoal482.2PM100.03
(22.)2x20 T IFElectricity301.8PM100.015
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 184.11
(b)Source Own generation(165.6 MW) and DVC supply (18.4 MW)
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 500x2
(e)Stack Height (in m) 8
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 0
(c)Government Land (ha.) 116.72
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 116.72
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 14378
(b)Waste/Barren Land (ha.) 4686
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 2220
(e)Settlements (ha.) 3816
(f)Industrial (ha.) 1535
(g)Forest (ha.) 595
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Mining, Infrastructure 3994
    Total (ha.) 31224
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Green belt38.02
(2.)Water Reservoir4.95
(3.)Othersrailway siding4.20
(4.)Main Plant62.65
(5.)Area for Solid Waste Management5.20
(6.)Township1.7
Total (ha.) 116.72
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)ESAsNA0Not found
(2.)ESZsNA0Not found
(3.)CorridorsNA0Not found
(4.)Critically Polluted AreaNA0Not found
(5.)NPANA0Not found
(6.)WLSNA0Not found
(7.)Wildlife CorridorsNA0Not found
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestNA0Not Found
(2.)Defence InstallationsNA0Not Found
(3.)Archaeological SitesNA0Not Found
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 116.72
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Ajay river
(ii)Direction of Water Bodies in Buffer Area North
(iii)Distance of Water Bodies in Buffer Area 7.3
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 200
(b)Permanent Employment-During Operation 300
(c)Temporary Employment- During Construction 1000
(d)Temporary Employment- During Operation 500
(e)No. of working days 360
(f)Total Manpower 2000
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt14.4824.2738.75
(2.)Percentage of Total Project Area12.420.733.1
(3.)No. of Plants240805930083380
(4.)Funds Allocated9685472434650025315047
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)EnvironmentalGreen belt creation, Water harvesting
(2.)SocialEmployment Generation, Infrastructural development
(3.)FinancialRevenue Generation
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 1
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. 77
(ii)Name of the EIA Consultant Global Tech Enviro Experts Pvt Ltd
(iii)Address C-23, BJB Nagar Bhubaneswar
(iv)Mobile No. 9437033487
(v)Landline No. 0674243685
(vi)Email Id global1experts@gmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 1
(ix)Validity of Accreditation 23 Nov 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File NA
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantBISHNU KUMAR BAJAJ
DesignationDGM finance and Corporate Rela
Name of Company (Applicant Name should not be given here)SUPER SMELTERS LIMITED
Address39, Shakespeare Sarani, 'PREMLATA', 3rd Floor, Kolkata-700017, West Bengal
Print