Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Proposed Bulk Drugs & Intermediates Manufacturing Unit by Archimedis Laboratories Private Limited
(b)Name of the Company / Organisation ARCHIMEDIS LABORATORIES PRIVATE LIMITED
(c)Registered Address Survey No. 108 & 109, (Village) Jayanthipuram, (Mandal) Jaggayyapeta, (District) Krishna,,Krishna,Andhra Pradesh-521457
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant VenkateswaraReddy Maddireddy
(b)Designation (Owner/ Partner/ CEO) ManagingDirector
(c)Address 5-163/1, 2 nd Floor, Malleswari Nilayam, Chintalkunta, LB Nagar Post Hyderabada,,Uppal kalan,Rangareddi,Telangana-500074
(d)Pin code 500074
(e)E-mail archimedismlpl@gmail.com
(f)STD Code. 40(f)Telephone No. 23070602
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
Minor Activity
(b)Category A
(c)Proposal Number IA/AP/IND2/84787/2018
(d)Master Proposal Number(Single Window) SW/84784/2018
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Sy No: 108 & 109, Jayanthipuram (V) Jaggayyapet (M
(b)Pincode 521457
(c)Bounded Latitudes (North)
From
Degree 16.846
Minutes
Second
From
Degree 16.849
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 80.136
Minutes
Second
From
Degree 80.137
Minutes
Second
(e)Survey of India Topo Sheet No. 65 D/1
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 51
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 3.3
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Andhra Pradesh
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number F No.IA-J-11011/9/2018-IA-II(I)
(b)Date of Apply of TOR 03 Jan 2018
(c)Date of Issue of TOR / Standard ToR 05 Feb 2018
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :27 Sep 2018
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :27 Oct 2018
Distance of Public Hearing Venue from the Proposed Project :0
Proposed Project Site, Sy No: 108 & 109, Jayanthipuram (V) Jaggayyapet (M), Krishna District, Andhra Pradesh
State :Andhra Pradesh
District :Krishna
Tehsil :Jaggayyapeta
Village :Jayanthipuram
79Main Issues raised during PH is Employment, CSR activities, Green belt, Rain Water Harvesting and Pollution prevention.District Magistrate
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)RO SystemCapacity: 100 KLD
(2.)Coal fired boilersCapacity : 8 TPH & 4 TPH
(3.)MEE SystemCapacity: 85 KLD
(4.)Biological Treatment PlantCapacity: 110 KLD
(5.)DG setCapacity:500 KVA & 1000 KVA
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Ketorolac tromethamine5OthersTons per Month (TPM)Road
(2.)Olmesartan medoxomil4OthersTons per Month (TPM)Road
(3.)Itraconazole4OthersTons per Month (TPM)Road
(4.)Duloxetine Hydrochloride2OthersTons per Month (TPMRoad
(5.)Sumatriptan Succinate1OthersTons per Month (TPM)Road
(6.)Zolmitriptan1OthersTons per Month (TPM)Road
(7.)Mesalamine (or) Mesalazine4OthersTons per Month (TPM)Road
(8.)Celecoxib4OthersTons per Month (TPM)Road
(9.)Rosuvastatin4OthersTons per Month (TPM)Road
(10.)Dabigatran2OthersTons per Month (TPM)Road
(11.)Emtricitabine4OthersTons per Month (TPM)Road
(12.)4-Dimethyl amino butytalde diethyl acetal5OthersTons per Month (TPM)Road
(13.)Pentaprazole Sodium9OthersTons per Month (TPM)Road
(14.)Imatinib Mesylate2OthersTons per Month (TPM)Road
(15.)Sitagliptin Phosphate Monohydrate2OthersTons per Month (TPM)Road
(16.)Velpatasvir2OthersTons per Month (TPM)Road
(17.)Lansprazole1OthersTons per Month (TPM)Road
(18.)Pregabalin4OthersTons per Month (TPM)Road
(19.)2,4- Dihydro-4-(4-4 hydroxy phenyl )-1-piperazinyl ) -2-(1-methyl propyl )-3H-1,2,4-Triazole-3-one(Itraconazole intermediate)10OthersTons per Month (TPM)Road
(20.)Cis -2-[2,4-Di chloro Phenyl]-2-[1H-1,2,4-Triazole -1-yl methyl]-1,3 Dioxalane-4yl Methyl ] Methane Sulfonate (Itraconazole intermediate)5OthersTons per Month (TPM)Road
(21.)2-[3-methyl -4-(2,2,2-trifluoroethoxy)-2-pyridinyl ] 5methylthio -1H-benzimidazole(Lansoprazole Sulfide Intermediate )5OthersTons per Month (TPM)Road
(22.)4-Chloro-1 hydroxy butane sulphonic acid sodium salt5OthersTons per Month (TPM)Road
(23.)4-Chloro Butyralde Diethyl acetal5OthersTons per Month (TPM)Road
(24.)Cis -2-[2,4-Di Chloro Phenyl] -2-[1H-1,2,4-Triazole -1-yl Methyl ]-1,3 Dioxalane -4 yl Methanol(Itraconazole intermediate)4OthersTons per Month (TPM)Road
(25.)Pentaprazole chloro compound (2-Chloromethyl-3,4-Dimethoxy-Pyridine)10OthersTons per Month (TPM)Road
(26.)Almotriptan Malate1OthersTons per Month (TPM)Road
(27.)(S)-(-)-3-(Dimethyl amino )-1-(2-Thienyl)-1-praponal10OthersTons per Month (TPM)Road
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 30
(b) Funds Allocated for Environment Management (Capital) (in Crores) 1.1
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.6
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.20
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 274
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 274
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Tetra hydrofuran78.33Otherskg/dayDomesticRoad0 Open MarketCopy of Linkage
(2.)Maltol274Otherskg/dayDomesticRoad0 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Mar 2018 To 31 May 2018
(b)Season Summer
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube70.1548.2368.88100
(2.)PM2.5Micro Gram per Meter Cube30.5914.5228.9260
(3.)SO2Micro Gram per Meter Cube16.309.5815.1580
(4.)OthersCOMili Gram per Meter Cube0.760.190.742
(5.)NOxMicro Gram per Meter Cube23.1913.7822.3380
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA8.377.328.50
(2.)Total Hardnessmg/l670295200600
(3.)Fluoridemg/l0011.5
(4.)Heavy MetalsLeadmg/l000.010
(5.)TSSNA0000
(6.)Chloridesmg/l31094.22501000
(7.)TDSmg/l983.4467.55002000
    14.3.     No. of Surface Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)DOmg/l5.24.8E
(2.)BODmg/l19.29.2E
(3.)pHNA8.377.32E
(4.)CODmg/l7428E
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))62.346.575
(2.)Leq(Night)A-weighted decibels(dB(A))52.138.970
    14.5.     No. of Soil Sample Monitored locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)K(Potassium)Kilogram per hectare386294
(2.)Electric ConductivityOthersµ mhos14298.6
(3.)pHOthersNA7.306.75
(4.)N(Nitrogen)Kilogram per hectare172112
(5.)P(Phosphorus)Kilogram per hectare5948
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 1.52 To 11.2
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 0.21 To 9.06
(c)Whether Ground Water Intersection will be there ? Yes
(d)Upload Copy of Central Ground Water Authority Letter Copy of Central Ground Water Authority Letter
(e)Letter No. 1588/Hg-II/2018
(f)Date of Issue 20 Aug 2018
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater2590Copy of Permission LettermodeOthersWithin the Plant SiteTube Well1588/Hg-II/201820 Aug 2018269
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Scrubbing system5110ZLD SystemOthersTreatment Losses3.51.5
(2.)Process66110ZLD SystemOthersTreatment Losses49.8716.13
(3.)Boiler Blow down10110ZLD SystemOthersTreatment Losses8.931.07
(4.)Cooling towers bleed off12110ZLD SystemOthersTreatment Losses10.721.28
(5.)Domestic2.8110ZLD SystemOthersTreatment Losses2.50.3
(6.)Washings10110ZLD SystemOthersTreatment Losses8.931.07
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 105.8
(b)Total Discharged Water (Kilolitre per Day) 21.35
(c)Total Reused Water (Kilolitre per Day) 84.45
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Organic Solid WasteHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1352.52Tons10RoadOthersSent to Cement Industries
(2.)Spent CarbonHazardous Waste (as per Hazardous and Other Waste Management rules 2016)38.88Tons10RoadOthersSent to Cement Industries
(3.)Organic Evaporate Liquid from MEE StripperHazardous Waste (as per Hazardous and Other Waste Management rules 2016)374.4Tons10RoadOthersSent to Cement Industries
(4.)ETP SludgeHazardous Waste (as per Hazardous and Other Waste Management rules 2016)360Tons600RoadTreatment, Storage and Disposal Facility(TSDF)
(5.)Inorganic Solid WasteHazardous Waste (as per Hazardous and Other Waste Management rules 2016)131.76Tons600RoadTreatment, Storage and Disposal Facility(TSDF)
(6.)MEE SaltsHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1783.44Tons600RoadTreatment, Storage and Disposal Facility(TSDF)
(7.)Used OilsHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1Kilolitre50RoadAuthorized Recyclers
(8.)Ash From BoilerOthersAsh from boiler6048Tons50RoadOthersSent to Brick Manufacturers
(9.)Solvent Distillation ResidueHazardous Waste (as per Hazardous and Other Waste Management rules 2016)422.64Tons10RoadOthersSent to Cement Industries
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)NOxMicrogram per Meter Cube22.330.59.4731.8080
(2.)PM10Microgram per Meter Cube68.880.50.4569.33100
(3.)PM2.5Microgram per Meter Cube28.920.50.3129.2360
(4.)Others(Specify)SPMMicrogram per Meter Cube68.880.50.75969.639100
(5.)SO2Microgram per Meter Cube15.150.54.69419.84480
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)4.0 TPH BoilerCoal300.4SO21.48 gm/Sec
(2.)8.0 TPH BoilerCoal340.5SO22.95 gm/Sec
(3.)8.0 TPH BoilerCoal340.5PM100.156 gm/Sec
(4.)4.0 TPH BoilerCoal300.4NOx4.86 gm/Sec
(5.)8.0 TPH BoilerCoal340.5NOx9.70 gm/Sec
(6.)4.0 TPH BoilerCoal300.4PM100.078 gm/Sec
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 2000
(b)Source Andhra Pradesh Southern Power Distribution Corpora
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 500 KVA & 1000 KVA
(e)Stack Height (in m) 10
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 4.702
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 4.702
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 17210
(b)Waste/Barren Land (ha.) 6000
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 2323.0
(e)Settlements (ha.) 1632.0
(f)Industrial (ha.) 596.0
(g)Forest (ha.) 3642
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : NA 0
    Total (ha.) 31403
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Built Up Area1.1536
(2.)Green belt1.7287
(3.)OthersRoads & Open Area1.8201
Total (ha.) 4.7024
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)WLSNot Present0NA
(2.)NPANot Present0NA
(3.)Wildlife CorridorsNot Present0NA
(4.)ESZsNot Present0NA
(5.)Critically Polluted AreaNot Present0NA
(6.)CorridorsNot Present0NA
(7.)ESAsNot Present0NA
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Archaeological SitesNone0None
(2.)Defence InstallationsNone0None
(3.)ForestJaggayyapeta Extension R.F0.390.52 km (S), 0.39 km (N) of Project Site
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 4.702
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Chillakallu Major canal - 2.10 km (WNW)
(ii)Direction of Water Bodies in Buffer Area West
(iii)Distance of Water Bodies in Buffer Area 2.1
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 10
(b)Permanent Employment-During Operation 70
(c)Temporary Employment- During Construction 5
(d)Temporary Employment- During Operation 15
(e)No. of working days 30
(f)Total Manpower 100
32.
Green Belt in Ha:
(a)Total Area of Green Belt 1.728
(b)Percentage of Total Project Area 36.75
(c)No. of Plants to be Planted 2592
(d)Funds Allocated for Plantation 500000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)FinancialArchimedis Laboratories Pvt. Ltd will spend about 2.5% (Rs. 75 Lakhs) for CSR & 2% (Rs. 60Lakhs) for CER activities like potable water supply & educational aid and conduct medical camps & Self Help Skill Training to the nearby villages.
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1821/RA0100
(ii)Name of the EIA Consultant Rightsource Industrial Solutions Private Limited
(iii)Address Rightsource Industrial Solutions Pvt Limited Plot No: 203, H.No:5-36/203, Prashanthi Nagar, IDA, Kukatpally, Hyderabad – 500072.
(iv)Mobile No. 9885560011
(v)Landline No. 0402306070
(vi)Email Id Info@rightsource.co.in
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 25 Feb 2021
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAPlease confirm whether such polluting units are allowed by SPCB at the identified project site in non-industrial area. 12 Nov 2018
2.NAThe correction have been made as per the instruction received 16 Nov 2018
3.NA- In continuation to our earlier observations, please confirm whether all the products (27 nos) with total production capacity of 115 TPM are actually covered under synthetic organic chemicals and thus requiring prior environmental clearance. - Plan to achieve ZLD and disposal of hazardous waste. 01 Dec 2018
4.NAThe correction have been made as per the instruction received 26 Dec 2018
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantVenkateswaraReddy Maddireddy
DesignationManagingDirector
Name of Company (Applicant Name should not be given here)ARCHIMEDIS LABORATORIES PRIVATE LIMITED
AddressSurvey No. 108 & 109, (Village) Jayanthipuram, (Mandal) Jaggayyapeta, (District) Krishna