Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) M/s. Hexane Pharmachem Industries
(b)Name of the Company / Organisation HEXANE PHARMACHEM INDUSTRIES
(c)Registered Address PLOT NO. 4, BLOCK NO. 253, VILL: NANANPUR, TALUKA : PRANTIJ, DISTRICT : SABARKANTHA,,Sabar Kantha,Gujarat-383210
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant NAVNEET PATEL PATEL
(b)Designation (Owner/ Partner/ CEO) PARTNER
(c)Address PLOT NO. 4, BLOCK NO. 253, VILLAGE NANANPUR, TALUKA PRANTIJ, DISTRICT SABARKANTHA,,Prantij,Sabar Kantha,Gujarat-383210
(d)Pin code 383210
(e)E-mail hexanepharmachem@gmail.com
(f)STD Code. 79(f)Telephone No. 27450694
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
Minor Activity
(b)Category A
(c)Proposal Number IA/GJ/IND2/64726/2017
(d)Master Proposal Number(Single Window) SW/84566/2018
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. plot no. 4, Block no 253 paiki 1
(b)Pincode 383210
(c)Bounded Latitudes (North)
From
Degree 72.949760
Minutes
Second
From
Degree 72.949861
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 23.524779
Minutes
Second
From
Degree 23.524990
Minutes
Second
(e)Survey of India Topo Sheet No. F43A14
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 135
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 4.6
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Gujarat
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)GujaratSabar KanthaPrantij
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number IA-J-11011/232/2017-IA-II(I)
(b)Date of Apply of TOR 16 May 2017
(c)Date of Issue of TOR / Standard ToR 01 Aug 2017
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :16 Aug 2018
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :18 Sep 2018
Distance of Public Hearing Venue from the Proposed Project :0
plot no. 4, block no. 253 paiki 1, Nananpur, Prantij, Sabarkantha
State :Gujarat
District :Sabar Kantha
Tehsil :Prantij
Village :nananpur
63employment of local people, safety of workers, CSR activity & environment protectionOthersAdditional District Magistrate
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)production plantmanufacturing of product
(2.)utility, fuel storage & stackutility area
(3.)ETP & solid waste storage areaeffluent treatment facility & waste storage
(4.)officeadministrative works
(5.)security cabinallocated area of security officer
(6.)Solvent & raw material storagesolvent & raw material storage
(7.)drying, grinding, packagingdryer, grinder & package area
(8.)finished good storageproduct storage area
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Cetyl Pyridinium Choride12Tons per AnnumRoad,Rail
(2.)Tetra Butyl Ammonium Chloride24Tons per AnnumRoad,Rail
(3.)Cetramide12Tons per AnnumRoad,Rail
(4.)Cetramide Strong Solution 40 %12Tons per AnnumRoad,Rail
(5.)Ethyl Triphenyl Phosphonium Bromide12Tons per AnnumRoad,Rail
(6.)Lauryl Pyridinium Chloride12Tons per AnnumRoad,Rail
(7.)Methyl Triphenyl Phosphonium Bromide36Tons per AnnumRoad,Rail
(8.)Tetra Butyl Ammonium Bromide (Powder)120Tons per AnnumRoad,Rail
(9.)Tetra Butyl Ammonium Bromide (Solution)300Tons per AnnumRoad,Rail
(10.)Tetra Butyl Ammonium Iodide12Tons per AnnumRoad,Rail
(11.)Tetra Methyl Ammonium Chloride24Tons per AnnumRoad,Rail
(12.)Tetra Octyl Ammonium Bromide24Tons per AnnumRoad,Rail
(13.)Tetra Ethyl Ammonium Bromide60Tons per AnnumRoad,Rail
(14.)Benzyl Tri Butyl Ammonium Chloride12Tons per AnnumRoad,Rail
(15.)Cetyl Dimethyl Benzyl Ammonium Bromide12Tons per AnnumRoad,Rail
(16.)Mesetronium Etho Sulphate12Tons per AnnumRoad,Rail
(17.)Methyl Triphenyl Phosphonium Chloride24Tons per AnnumRoad,Rail
(18.)Methyl Triphenyl Phosphonium Iodide12Tons per AnnumRoad,Rail
(19.)Tetra Phenyl Phosphonium Bromide12Tons per AnnumRoad,Rail
(20.)Benzyl Tri Methyl Ammonium Chloride (Powder)192Tons per AnnumRoad,Rail
(21.)Cetyl Trimethyl Ammonium Bromide12Tons per AnnumRoad,Rail
(22.)Cetyl Trimethyl Ammonium Chloride 30 %12Tons per AnnumRoad,Rail
(23.)Benzyl Triphenyl Phosphonium Chloride12Tons per AnnumRoad,Rail
(24.)Methyl Tributyl Ammonium Chloride 75 %60Tons per AnnumRoad,Rail
(25.)Methyl Trioctyl Ammonium Chloride 95 %12Tons per AnnumRoad,Rail
(26.)Phenyl Trimethyl Ammonium Chloride24Tons per AnnumRoad,Rail
(27.)Tetra Butyl Ammonium Hydrogen Sulphate24Tons per AnnumRoad,Rail
(28.)Tri Ethyl Benzyl Ammonium Chloride60Tons per AnnumRoad,Rail
(29.)Benzalkonium Chloride 50 %12Tons per AnnumRoad,Rail
(30.)Benzyl Tri Butyl Ammonium Bromide12Tons per AnnumRoad,Rail
(31.)Butyl Triphenyl Phosphonium Bromide24Tons per AnnumRoad,Rail
(32.)Butyl Triphenyl Phosphonium Chloride12Tons per AnnumRoad,Rail
(33.)Cetyl Dimethyl Benzyl Ammonium Chloride12Tons per AnnumRoad,Rail
(34.)Dodecyl Trimethyl Ammonium Chloride12Tons per AnnumRoad,Rail
(35.)Tri Ethyl Methyl Ammonium Chloride12Tons per AnnumRoad,Rail
(36.)Tri Ethyl Butyl Ammonium Bromide12Tons per AnnumRoad,Rail
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. not applicable
(vi)Application No. not applicable
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 3.60
(b) Funds Allocated for Environment Management (Capital) (in Crores) 0.4
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.072
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.31
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 202.56
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 202.56
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)tri phenyl phosphine105.96Tons per Annumlocal suppliers/tradersRoad,Rail460 Open MarketCopy of Linkage
(2.)Benzyl chloride175.56Tons per Annumlocal trader/supplierRoad,Rail300 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 23 Sep 2017 To 22 Dec 2017
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)SO2Micro Gram per Meter Cube31.695.7031.3780
(2.)NOxMicro Gram per Meter Cube45.559.4145.3080
(3.)PM10Micro Gram per Meter Cube81.3650.1281.04100
(4.)PM2.5Micro Gram per Meter Cube58.4324.9758.3660
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)Chloridesmg/l18362.42501000
(2.)OthersTurbidityOthersNTU5.62.815
(3.)Fluoridemg/l0.850.311.5
(4.)Heavy MetalsMagnesiummg/l82.611.730100
(5.)pHNA7.967.38.58.5
(6.)TSSmg/l1161600
(7.)TDSmg/l12963245002000
(8.)Total Hardnessmg/l82098200600
    14.3.     No. of Surface Water monitoring locations : 6
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA8.958.15B
(2.)DOmg/l5.23.9B
(3.)CODmg/l97.912B
(4.)BODmg/l28.86.9B
(5.)OthersTDSmg/l1620208B
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))47.334.245
(2.)Leq(Day)A-weighted decibels(dB(A))57.340.655
    14.5.     No. of Soil Sample Monitored locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)P(Phosphorus)Milligram per Kilogram5.360.52
(2.)Electric ConductivityMillisiemens per Centimetre3.5200.235
(3.)K(Potassium)Milliequivalents per 100 Gram26.349.32
(4.)N(Nitrogen)OthersNOT MEASURED00
(5.)pHOthersNot applicable8.417.11
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 4.68 To 41.40
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 1.73 To 41.00
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater29.50Copy of Permission LetterPipelineOthersborewell21-4/3517/GJ/IND/201815 Feb 201829.5
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)domestic00total 1.6 KLD domestic effluent will be generated & will be disposed off into soak pit via septic tankOthersseptic tank / soak pit00
(2.)Industrial010total 8.3 KLD wastewater will be generated & treated in ETP followed by condenser system, so 5.4 KLD condensate will be reused in inudustrial processReuse within the Plant & Recycling0
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 0
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 0
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)process waste (organic)Hazardous Waste (as per Hazardous and Other Waste Management rules 2016)116.76Tons300RoadOtherscommon hazardous waste incineration facility
(2.)ETP sludge + evaporation residueHazardous Waste (as per Hazardous and Other Waste Management rules 2016)60Tons300RoadTreatment, Storage and Disposal Facility(TSDF)
(3.)catalyst wasteHazardous Waste (as per Hazardous and Other Waste Management rules 2016)2.4Tons300RoadOthersCHWIF
(4.)off-specification productHazardous Waste (as per Hazardous and Other Waste Management rules 2016)0Tons300RoadOthersCHWIF
(5.)discarded containersHazardous Waste (as per Hazardous and Other Waste Management rules 2016)21.6Tons0RoadAuthorized Recyclers
(6.)process waste (inorganic)Hazardous Waste (as per Hazardous and Other Waste Management rules 2016)72.96Tons300RoadTreatment, Storage and Disposal Facility(TSDF)
(7.)used oilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)0.048Tons0RoadAuthorized Recyclers
(8.)date expired product / raw materialHazardous Waste (as per Hazardous and Other Waste Management rules 2016)0Tons300RoadOthersCHWIF
(9.)distillation residueHazardous Waste (as per Hazardous and Other Waste Management rules 2016)19.68Tons300RoadOthersCHWIF
(10.)spent charcoal + spent carbonHazardous Waste (as per Hazardous and Other Waste Management rules 2016)31.92Tons300RoadOthersCommon Hazardous waste incineration facility
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM2.5NA00000
(2.)NOxMicrogram per Meter Cube45.551.630.0645.6180
(3.)PM10Microgram per Meter Cube81.361.630.1581.51100
(4.)SO2Microgram per Meter Cube31.691.630.0331.7280
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)stack attached with Boilerwhite coal / briquettes301.0PM100.77
(2.)stack attached with boilerwhite coal / briquetters301.0SO20.03
(3.)stack attached with boilerwhite coal / briquettes301.0NOx0.16
(4.)process stack attached with process room-60.5OthersVOC-
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 235
(b)Source UGVCL
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) DG set of 60 KVA
(e)Stack Height (in m) 10
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 0.6077
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 0.6077
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 22541
(b)Waste/Barren Land (ha.) 3138
(c)Grazing/ Community Land (ha.) 2321
(d)Surface Water Bodies (ha.) 714
(e)Settlements (ha.) 2181
(f)Industrial (ha.) 269
(g)Forest (ha.) 251
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : other land 0
    Total (ha.) 31415
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Built Up Area0.1902
(2.)Green belt0.2085
(3.)Othersopen area0.2090
Total (ha.) 0.6077
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted Areanone within 10 km radius area0N.A.
(2.)ESZsnone within 10 km radius area0N.A.
(3.)Wildlife Corridorsnone within 10 km radius area0N.A.
(4.)WLSnone within 10 km radius area0N.A.
(5.)NPAnone within 10 km radius area0N.A.
(6.)Corridorsnone within 10 km radius area0N.A.
(7.)ESAsnone within 10 km radius area0N.A.
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Defence InstallationsNone within 10 km radius area0not applicable
(2.)Archaeological SitesNone within 10 km radius area0not applicable
(3.)ForestBerna Reserve Forest11.94Berna reserve forest is outside 10 km radius area from project site
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0.6077
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired not applicable
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Yet To Start
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species Indian Peafawl
(b)Whether conservation plan for Schedule-I Species has been prepared ? Yes
(i)Uploaded copy of conservation plan Copy of conservation plan
(ii)Fund Provision made included in conservation plan
(iii)Period of Implementation 1 to 5 years
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Hathmati river
(ii)Direction of Water Bodies in Buffer Area South East
(iii)Distance of Water Bodies in Buffer Area 4.6
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 12
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 0
(e)No. of working days 25
(f)Total Manpower 12
32.
Green Belt in Ha:
(a)Total Area of Green Belt 0.2085
(b)Percentage of Total Project Area 34.31
(c)No. of Plants to be Planted 300
(d)Funds Allocated for Plantation 100000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)Socialsocial & financial benefits
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1619/RA 0033
(ii)Name of the EIA Consultant T. R. Associates
(iii)Address A-401, S.G. Business Hub, B/w. Sola Bhagwat & Gota over bridge, near umiya campus, S. G. Highway, Ahmedabad - 380060
(iv)Mobile No. 9825371099
(v)Landline No. 0792745069
(vi)Email Id adm.trassocaites@gmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 17 Mar 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAPlease inform/clarify the following:- - Whether the proposed industrial operations are permitted at the identified site and/or in conformity with land use of the area. That needs to be confirmed along with supporting documents. - Permission required from SPCB to allow such polluting units in non industrial area. - Clearance for ground water withdrawal. 11 Nov 2018
2.NAThe correction have been made as per the instruction received 30 Jul 2019
3.NAPlease reply to our observations dated 11/11/2018 to take the proposal forward. 27 Aug 2019
4.NAThe correction have been made as per the instruction received 27 Aug 2019
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantNAVNEET PATEL PATEL
DesignationPARTNER
Name of Company (Applicant Name should not be given here)HEXANE PHARMACHEM INDUSTRIES
AddressPLOT NO. 4, BLOCK NO. 253, VILL: NANANPUR, TALUKA : PRANTIJ, DISTRICT : SABARKANTHA