Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Workover of the temporarily abandoned 2 (sweet gas) wells & 5 nos of additional exploratory /development well in an area of 9.63 sq.km of Achanta filed in West Godavari District in Andhra Pradesh for
(b)Name of the Company / Organisation PFH OIL & GAS PRIVATE LIMITED
(c)Registered Address PFH Oil & Gas PL, 703 Tower 1, PS Srijan Corporate Park, Plot G2, Block GP, Sector 5, Salt Lake City, Kolkata, WB, India,,Kolkata,West Bengal-700091
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Mark Sargon
(b)Designation (Owner/ Partner/ CEO) Vice President – Operations
(c)Address PFH Oil Gas PL, 703 Tower 1, PS Srijan Corporate Park, Plot G2, Block GP, Sector 5, Salt Lake City, Kolkata,,,Kolkata,West Bengal-700091
(d)Pin code 700091
(e)E-mail ss@pfhoil.com
(f)STD Code. 33(f)Telephone No. 40508300
(g)Fax No. 03340508326
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity1(b) Offshore and onshore oil and gas exploration, development & production
Minor Activity1(b) Offshore and onshore oil and gas exploration, development & production
(b)Category A
(c)Proposal Number IA/AP/IND2/69756/2017
(d)Master Proposal Number(Single Window) SW/84435/2018
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. none
(b)Pincode 534123
(c)Bounded Latitudes (North)
From
Degree 16.590653
Minutes
Second
From
Degree 16.617682
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 81.799495
Minutes
Second
From
Degree 81.844063
Minutes
Second
(e)Survey of India Topo Sheet No. E44W2,E44W3,E44V15,E44V16
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 15
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 1
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Andhra Pradesh
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)Andhra PradeshWest GodavariAchanta
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number IA-J-11011/482/2017-IA-II(I)
(b)Date of Apply of TOR 25 Sep 2017
(c)Date of Issue of TOR / Standard ToR 06 Nov 2017
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :29 Aug 2018
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :28 Sep 2018
Distance of Public Hearing Venue from the Proposed Project :0
Project Site
State :Andhra Pradesh
District :West Godavari
Tehsil :Achanta
Village :Kodamanchilli
100Blow out prevention measures, waste water management, CSR activities, Protection measures during heavy vehicle movement, Local employment.OthersJoint Collector
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)drill rig equipmentNot Applicable
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)6 Ha (per well 1 Ha. 1 abandoned well and 5 new wells)6HectaresOthersLand
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 10
(b) Funds Allocated for Environment Management (Capital) (in Crores) .20
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.15
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.05
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 5.5
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 5.5
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)FUEL5.5Kilo Litre per DayLocalRoad5 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Dec 2017 To 28 Feb 2018
(b)Season Winter
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 6
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube54.437.154.3100
(2.)SO2Micro Gram per Meter Cube14.76.114.780
(3.)OthersHydrocarbonMicro Gram per Meter Cube389.3217.3389-
(4.)NOxMicro Gram per Meter Cube1614.71680
(5.)PM2.5Micro Gram per Meter Cube25.818.225.860
    14.2.     No. of Ground Water monitoring locations : 4
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA8.17.426.58.5
(2.)TDSmg/l22348785002000
(3.)Total Hardnessmg/l395165200600
(4.)Heavy MetalsAluminummg/l0.020.010.032
(5.)TSSmg/l753200
(6.)Fluoridemg/l0.520.2011.5
(7.)Chloridesmg/l5212002501000
    14.3.     No. of Surface Water monitoring locations : 1
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHmg/l7.27.2A
(2.)DOmg/l5.65.6A
(3.)CODmg/l1515A
(4.)BODmg/l66E
    14.4.     No. of Ambient Noise monitoring locations : 4
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))40.528.350
(2.)Leq(Night)A-weighted decibels(dB(A))322940
    14.5.     No. of Soil Sample Monitored locations : 4
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)N(Nitrogen)Kilogram per hectare26.3216.24
(2.)Electric ConductivityMillisiemens per Centimetre52030
(3.)K(Potassium)Kilogram per hectare3062.5412.5
(4.)pHOthers-7.916.28
(5.)P(Phosphorus)Kilogram per hectare00
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 2 To 4
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 1 To 2
(c)Whether Ground Water Intersection will be there ? NA
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersTankers255 Not Appliacble modeOthersTankersOthersTankersNot Applicable09 Oct 201825
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Drilling Operations45Reuse within plantReuse within the Plant & Recycling4
(2.)Domestic56Modular STPOthersSoak Pit41
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 9
(b)Total Discharged Water (Kilolitre per Day) 1
(c)Total Reused Water (Kilolitre per Day) 8
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Drill CuttingsOthersSolid Waste12Tons1RoadAuthorized Recyclers
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube54.30054.3100
(2.)PM2.5Microgram per Meter Cube25.80025.860
(3.)NOxMicrogram per Meter Cube160.515.531.580
(4.)SO2Microgram per Meter Cube14.70.50.0114.7180
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)DG StackHSD300.25SO20.01
(2.)DG StackHSD300.25NOx15.5
(3.)DG StackHSD300.25PM100
(4.)DG StackHSD300.25NOx15.5
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 2500
(b)Source DG Sets
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 1000 kva
(e)Stack Height (in m) 30
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 1
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 1
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 6
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 0
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : 1 ha land required for each drill site,The land wi 0
    Total (ha.) 6
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Green belt0.33
(2.)OthersDrilling Rig and other Ancillary facilities0.67
Total (ha.) 1
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNone0None Within 10 km Radius
(2.)WLSNone0None Within 10 km Radius
(3.)NPANone0None Within 10 km Radius
(4.)ESAsNone0None Within 10 km Radius
(5.)ESZsNone0None Within 10 km Radius
(6.)CorridorsNone0None Within 10 km Radius
(7.)Wildlife CorridorsNone0None Within 10 km Radius
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestNone0None Within 10 km Radius
(2.)Defence InstallationsNone0None Within 10 km Radius
(3.)Archaeological SitesNone0None Within 10 km Radius
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0
(b)Land yet to be acquired(Ha) 5
(c)Status of Land acquisition if not acquired Drilling location will be decided based on the Det
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species Pavo Cristatus, Gracula Spp
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area Ponds
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Godavari River
(ii)Direction of Water Bodies in Buffer Area East
(iii)Distance of Water Bodies in Buffer Area 1.4
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 10
(b)Permanent Employment-During Operation 20
(c)Temporary Employment- During Construction 10
(d)Temporary Employment- During Operation 10
(e)No. of working days 60
(f)Total Manpower 50
32.
Green Belt in Ha:
(a)Total Area of Green Belt 0.33
(b)Percentage of Total Project Area 33.00
(c)No. of Plants to be Planted 50
(d)Funds Allocated for Plantation 50000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)Social· Generation of employment: The project will create opportunities for direct and indirect employment; · Increase in purchasing power and improved standard of living of the area; · Establishment of small and medium scale industries may be developed as consequence; · Increased revenue to the state by way of royalty, taxes and duties; · Regular Fund flow to local market; · Overall Growth of the neighboring Area viz.: o Agriculture and Animal husbandry; o Health and family welfare; o Watershed deve
(2.)EnvironmentalDecreasing the carbon foot prints due to import of Oil& Gas by generating it locally.
(3.)FinancialCompound Annual Growth Rate (CAGR) will increase if the reserves are found.
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1619/RA0049
(ii)Name of the EIA Consultant Bhagavathi Ana Labs Pvt Ltd
(iii)Address Plot no. 7-2-C14, Industrial Estate, Sanath Nagar, Hyderabad
(iv)Mobile No. 9391116139
(v)Landline No. 0402380380
(vi)Email Id shyam.sundar@in.bureauveritas.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 01 Jun 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAPlease inform about the details of EC for the abandoned wells (2 nos) and the compliance status thereof. Entry at item 8.2 of Form-2 (1 ha) needs to be clarified. 11 Nov 2018
2.NAThe correction have been made as per the instruction received 13 Nov 2018
3.NAPlease refer our earlier observations vide query dated 11/11/2018 and your response thereto. It is to inform that entry against column 8.2 of Form-2 is yet to corrected for the desired details. Also, please submit documentary evidence, if any, for no requirement of EC to the drilling operations of two wells already carried out by M/s ONGC Ltd. 23 Nov 2018
4.NAThe correction have been made as per the instruction received 10 Dec 2018
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantMark Sargon
DesignationVice President – Operations
Name of Company (Applicant Name should not be given here)PFH OIL & GAS PRIVATE LIMITED
AddressPFH Oil & Gas PL, 703 Tower 1, PS Srijan Corporate Park, Plot G2, Block GP, Sector 5, Salt Lake City, Kolkata, WB, India
Print