1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | Workover of the temporarily abandoned 2 (sweet gas) wells & 5 nos of additional exploratory /development well in an area of 9.63 sq.km of Achanta filed in West Godavari District in Andhra Pradesh for | (b)Name of the Company / Organisation | PFH OIL & GAS PRIVATE LIMITED | (c)Registered Address | PFH Oil & Gas PL, 703 Tower 1, PS Srijan Corporate Park, Plot G2, Block GP, Sector 5, Salt Lake City, Kolkata, WB, India,,Kolkata,West Bengal-700091 | (d)Legal Status of the Company | Private | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | Mark Sargon | (b)Designation (Owner/ Partner/ CEO) | Vice President – Operations | (c)Address | PFH Oil Gas PL, 703 Tower 1, PS Srijan Corporate Park, Plot G2, Block GP, Sector 5, Salt Lake City, Kolkata,,,Kolkata,West Bengal-700091 | (d)Pin code | 700091 | (e)E-mail | ss@pfhoil.com | (f)STD Code. | 33(f)Telephone No. | 40508300 | (g)Fax No. | 03340508326 | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 1(b) Offshore and onshore oil and gas exploration, development & production
| Minor Activity | 1(b) Offshore and onshore oil and gas exploration, development & production
| (b)Category | A | (c)Proposal Number | IA/AP/IND2/69756/2017 | (d)Master Proposal Number(Single Window) | SW/84435/2018 | (e)EAC concerned (for category A Projects only) | Industrial Projects - 2 | (f)Project Type | Fresh EC |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | none | (b)Pincode | 534123 | (c)Bounded Latitudes (North) | | From | | Degree | 16.590653 | Minutes | | Second | | From | | Degree | 16.617682 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 81.799495 | Minutes | | Second | | From | | Degree | 81.844063 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | E44W2,E44W3,E44V15,E44V16 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 15 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 1 | (j)Seismic Zone | 3 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Andhra Pradesh | |
|
|
Details of State(s) of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
(1.) | Andhra Pradesh | West Godavari | Achanta | | |
|
6. | Details of Terms of Reference (ToR): | (a)MoEF&CC / SEIAA File Number | IA-J-11011/482/2017-IA-II(I) | (b)Date of Apply of TOR | 25 Sep 2017 | (c)Date of Issue of TOR / Standard ToR | 06 Nov 2017 | (d)Previous TOR Letter | Copy of Previous TOR letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | No | (b)Whether details of Public Hearing available? | Yes | (c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above | Yes | |
|
7.1. Details of Public Hearing |
---|
|
S. No. | Details of Advertisement | Details of Public Hearing | Venue | Location Details | No. of People Attended | Issues Raised | Designation of Presiding Officer | Other Designation of Presiding Officer |
---|
(1.) | | Copy of Public Hearing : | Copy of Public Hearing | Date : | 28 Sep 2018 | Distance of Public Hearing Venue from the Proposed Project : | 0 |
| Project Site | State : | Andhra Pradesh | District : | West Godavari | Tehsil : | Achanta | Village : | Kodamanchilli |
| 100 | Blow out prevention measures, waste water management, CSR activities, Protection measures during heavy vehicle movement, Local employment. | Others | Joint Collector | |
8. | Details of Project Configuration/Product: | |
|
8.1. Project Configuration |
---|
S. No. | Plant/Equipment/Facility | Configuration | Remarks |
---|
(1.) | drill rig equipment | Not Applicable | | |
8.2. Product |
---|
S. No. | Product/Activity (Capacity/Area) | Quantity | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | 6 Ha (per well 1 Ha. 1 abandoned well and 5 new wells) | 6 | Hectares | | Others | Land | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | Details Not Applicable | |
|
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | N/A | (iv)Valid Upto | N/A | (v)File No. | NA | (vi)Application No. | NA | (vii)Copy of Consent to operate valid as on date | NA | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 10 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | .20 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 0.15 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 0.05 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | No | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 5.5 | (b)Existing quantity of raw material/fuel | N/A | (c)Total quantity of raw material/fuel | 5.5 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | FUEL | 5.5 | Kilo Litre per Day | | Local | Road | | 5 | Open Market | | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 01 Dec 2017 To 28 Feb 2018 | (b)Season | Winter | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 6 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | PM10 | | Micro Gram per Meter Cube | 54.4 | 37.1 | 54.3 | 100 | (2.) | SO2 | | Micro Gram per Meter Cube | 14.7 | 6.1 | 14.7 | 80 | (3.) | Others | Hydrocarbon | Micro Gram per Meter Cube | 389.3 | 217.3 | 389 | - | (4.) | NOx | | Micro Gram per Meter Cube | 16 | 14.7 | 16 | 80 | (5.) | PM2.5 | | Micro Gram per Meter Cube | 25.8 | 18.2 | 25.8 | 60 | |
14.2. No. of Ground Water monitoring locations : 4 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | pH | | | NA | | 8.1 | 7.42 | 6.5 | 8.5 | (2.) | TDS | | | mg/l | | 2234 | 878 | 500 | 2000 | (3.) | Total Hardness | | | mg/l | | 395 | 165 | 200 | 600 | (4.) | Heavy Metals | | Aluminum | mg/l | | 0.02 | 0.01 | 0.03 | 2 | (5.) | TSS | | | mg/l | | 75 | 32 | 0 | 0 | (6.) | Fluoride | | | mg/l | | 0.52 | 0.20 | 1 | 1.5 | (7.) | Chlorides | | | mg/l | | 521 | 200 | 250 | 1000 | |
14.3. No. of Surface Water monitoring locations : 1 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | pH | | mg/l | | 7.2 | 7.2 | A | (2.) | DO | | mg/l | | 5.6 | 5.6 | A | (3.) | COD | | mg/l | | 15 | 15 | A | (4.) | BOD | | mg/l | | 6 | 6 | E | |
14.4. No. of Ambient Noise monitoring locations : 4 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Day) | A-weighted decibels(dB(A)) | 40.5 | 28.3 | 50 | (2.) | Leq(Night) | A-weighted decibels(dB(A)) | 32 | 29 | 40 | |
14.5. No. of Soil Sample Monitored locations : 4 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | N(Nitrogen) | Kilogram per hectare | | 26.32 | 16.24 | (2.) | Electric Conductivity | Millisiemens per Centimetre | | 520 | 30 | (3.) | K(Potassium) | Kilogram per hectare | | 3062.5 | 412.5 | (4.) | pH | Others | - | 7.91 | 6.28 | (5.) | P(Phosphorus) | Kilogram per hectare | | 0 | 0 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 2 To 4 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 1 To 2 | (c)Whether Ground Water Intersection will be there ? | NA | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | Others | Tankers | 25 | 5 | Not Appliacble | modeOthers | Tankers | Others | Tankers | Not Applicable | 09 Oct 2018 | 25 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | Drilling Operations | 4 | 5 | Reuse within plant | Reuse within the Plant & Recycling | | 4 | | (2.) | Domestic | 5 | 6 | Modular STP | Others | Soak Pit | 4 | 1 | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 9 | (b)Total Discharged Water (Kilolitre per Day) | 1 | (c)Total Reused Water (Kilolitre per Day) | 8 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Drill Cuttings | Others | Solid Waste | 12 | Tons | 1 | Road | | Authorized Recyclers | | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | PM10 | | Microgram per Meter Cube | 54.3 | 0 | 0 | 54.3 | 100 | (2.) | PM2.5 | | Microgram per Meter Cube | 25.8 | 0 | 0 | 25.8 | 60 | (3.) | NOx | | Microgram per Meter Cube | 16 | 0.5 | 15.5 | 31.5 | 80 | (4.) | SO2 | | Microgram per Meter Cube | 14.7 | 0.5 | 0.01 | 14.71 | 80 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | DG Stack | HSD | 30 | 0.25 | SO2 | | 0.01 | (2.) | DG Stack | HSD | 30 | 0.25 | NOx | | 15.5 | (3.) | DG Stack | HSD | 30 | 0.25 | PM10 | | 0 | (4.) | DG Stack | HSD | 30 | 0.25 | NOx | | 15.5 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 2500 | (b)Source | DG Sets | (c)Uploaded Copy of Agreement | Not Applicable | (d)Standby Arrangement (Details of DG Sets) | 1000 kva | (e)Stack Height (in m) | 30 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 0 | (b)Private Land (ha.) | 1 | (c)Government Land (ha.) | 0 | (d)Revenue Land (ha.) | 0 | (e)Other Land (ha.) | 0 | Total Land (ha.) | 1 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 6 | (b)Waste/Barren Land (ha.) | 0 | (c)Grazing/ Community Land (ha.) | 0 | (d)Surface Water Bodies (ha.) | 0 | (e)Settlements (ha.) | 0 | (f)Industrial (ha.) | 0 | (g)Forest (ha.) | 0 | (h)Mangroves (ha.) | 0 | (i)Marine Area (ha.) | 0 | (j)Others (ha.) : 1 ha land required for each drill site,The land wi | 0 | Total (ha.) | 6 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Green belt | | 0.33 | | (2.) | Others | Drilling Rig and other Ancillary facilities | 0.67 | | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Critically Polluted Area | None | 0 | None Within 10 km Radius | (2.) | WLS | None | 0 | None Within 10 km Radius | (3.) | NPA | None | 0 | None Within 10 km Radius | (4.) | ESAs | None | 0 | None Within 10 km Radius | (5.) | ESZs | None | 0 | None Within 10 km Radius | (6.) | Corridors | None | 0 | None Within 10 km Radius | (7.) | Wildlife Corridors | None | 0 | None Within 10 km Radius | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Forest | | None | 0 | None Within 10 km Radius | (2.) | Defence Installations | | None | 0 | None Within 10 km Radius | (3.) | Archaeological Sites | | None | 0 | None Within 10 km Radius | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
25. | Tree Cutting: | (a)No. of Trees Cut for the Project (if Forest Land not Involved) | 0 | (b)Details of Tree Cutting and Planting of Trees | Not Applicable | |
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 0 | (b)Land yet to be acquired(Ha) | 5 | (c)Status of Land acquisition if not acquired | Drilling location will be decided based on the Det | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 0 | (b)No. of Households | 0 | (c)No. of PDFs (Project Displaced Families) | 0 | (d)No. of PAFs (Project Affected Families) | 0 | (e)Funds Allocated for R&R(in INR) (in Lacs) | 0 | (f)Status of R&R | Completed | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | Yes | (i)Details of Schedule-I Species | Pavo Cristatus, Gracula Spp | (b)Whether conservation plan for Schedule-I Species has been prepared ? | No | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | Yes | (i)Details of Water Bodies in Core Area | Ponds | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | Yes | (i)Details of Water Bodies in Buffer Area | Godavari River | (ii)Direction of Water Bodies in Buffer Area | East | (iii)Distance of Water Bodies in Buffer Area | 1.4 | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 10 | (b)Permanent Employment-During Operation | 20 | (c)Temporary Employment- During Construction | 10 | (d)Temporary Employment- During Operation | 10 | (e)No. of working days | 60 | (f)Total Manpower | 50 | |
|
32. | Green Belt in Ha: | (a)Total Area of Green Belt | 0.33 | (b)Percentage of Total Project Area | 33.00 | (c)No. of Plants to be Planted | 50 | (d)Funds Allocated for Plantation | 50000 | (e)Uploaded Green Belt plan | Copy of Green Belt Plan | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Social | · Generation of employment: The project will create opportunities for direct and indirect employment;
· Increase in purchasing power and improved standard of living of the area;
· Establishment of small and medium scale industries may be developed as consequence;
· Increased revenue to the state by way of royalty, taxes and duties;
· Regular Fund flow to local market;
· Overall Growth of the neighboring Area viz.:
o Agriculture and Animal husbandry;
o Health and family welfare;
o Watershed deve | (2.) | Environmental | Decreasing the carbon foot prints due to import of Oil& Gas by generating it locally. | (3.) | Financial | Compound Annual Growth Rate (CAGR) will increase if the reserves are found. | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details : NOT APPLICABLE |
35. Sector Specific Details For Industrial Projects - 2 |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | NABET/EIA/1619/RA0049 | (ii)Name of the EIA Consultant | Bhagavathi Ana Labs Pvt Ltd | (iii)Address | Plot no. 7-2-C14, Industrial Estate, Sanath Nagar, Hyderabad | (iv)Mobile No. | 9391116139 | (v)Landline No. | 0402380380 | (vi)Email Id | shyam.sundar@in.bureauveritas.com | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | Industrial Projects - 2 | (ix)Validity of Accreditation | 01 Jun 2019 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought: |
---|
Sno. | EDS Letter | Remarks | Date of EDS |
---|
1. | NA | Please inform about the details of EC for the abandoned wells (2 nos) and the compliance status thereof. Entry at item 8.2 of Form-2 (1 ha) needs to be clarified. | 11 Nov 2018 | 2. | NA | The correction have been made as per the instruction received | 13 Nov 2018 | 3. | NA | Please refer our earlier observations vide query dated 11/11/2018 and your response thereto. It is to inform that entry against column 8.2 of Form-2 is yet to corrected for the desired details.
Also, please submit documentary evidence, if any, for no requirement of EC to the drilling operations of two wells already carried out by M/s ONGC Ltd. | 23 Nov 2018 | 4. | NA | The correction have been made as per the instruction received | 10 Dec 2018 | |
Additional Detail Sought : NIL |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | Mark Sargon | Designation | Vice President – Operations | Name of Company (Applicant Name should not be given here) | PFH OIL & GAS PRIVATE LIMITED | Address | PFH Oil & Gas PL, 703 Tower 1, PS Srijan Corporate Park, Plot G2, Block GP, Sector 5, Salt Lake City, Kolkata, WB, India |
|