1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | Expansion of M/s Maa Chhinnmastika Cement and Ispat Pvt. Ltd. for production of 67,500 TPA Rolled Product by installation of 2x12 Ton Induction Furnace with Billet Caster, Iron Ore Crushing & Benefici | (b)Name of the Company / Organisation | MAA CHHINNMASTIKA CEMENT AND ISPAT PRIVATE LIMITED | (c)Registered Address | At: Hehal, Post: Barkakana, District: Ramgarh, Jharkhand,,Ramgarh,Jharkhand-829103 | (d)Legal Status of the Company | Private | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | Alok Rungta | (b)Designation (Owner/ Partner/ CEO) | Director | (c)Address | Near: P.N. Bank, Main Road, Ramgarh Cantt., District: Ramgarh, Jharkhand,,Patratu,Ramgarh,Jharkhand-829122 | (d)Pin code | 829122 | (e)E-mail | alok_rungta@hotmail.com | (f)STD Code. | 6553(f)Telephone No. | 226846 | (g)Fax No. | 226845 | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 3(a) Metallurgical industries (ferrous & non ferrous)
| Minor Activity | | (b)Category | A | (c)Proposal Number | IA/JH/IND/84413/2004 | (d)Master Proposal Number(Single Window) | SW/84411/2018 | (e)EAC concerned (for category A Projects only) | Industrial Projects - 1 | (f)Project Type | Expansion |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | Plot No. 563, 386, 383, 384, 385, 387, 388 Khata N | (b)Pincode | 829103 | (c)Bounded Latitudes (North) | | From | | Degree | 23.6158 | Minutes | | Second | | From | | Degree | 23.6213 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 85.4250 | Minutes | | Second | | From | | Degree | 85.4313 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | 73E/6 & 73E/10 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 260 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 1.5 | (j)Seismic Zone | 2 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Jharkhand | |
|
|
Details of State of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
NIL | |
|
6. | Details of Terms of Reference (ToR)/EC: | (a)MoEF&CC / SEIAA File Number | N-502 | (c)Date of Issue of TOR | 25 Dec 2004 | (f)Previous TOR Letter | Copy of Previous TOR letter | (b)Date of Apply of EC | 10 Jan 2019 | (c)Date of Issue of EC | 07 Aug 2019 | (d)Previous EC Letter | Copy of Previous EC letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | No | (b)Whether details of Public Hearing available? | Yes | (c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above | Yes | |
|
7.1. Details of Public Hearing |
---|
|
S. No. | Details of Advertisement | Details of Public Hearing | Venue | Location Details | No. of People Attended | Issues Raised | Designation of Presiding Officer | Other Designation of Presiding Officer |
---|
(1.) | | Copy of Public Hearing : | Copy of Public Hearing | Date : | 30 Jan 2018 | Distance of Public Hearing Venue from the Proposed Project : | 2 |
| Rejkiykrit Utkremit Madhye Vidyalaya | State : | Jharkhand | District : | Ramgarh | Tehsil : | No Data | Village : | Hehal |
| 84 | During Public Hearing, Issues regarding the Air pollution control and employment generation were raised. | Others | ADM | |
8. | Details of Project Configuration/Product: | Details Not Applicable | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | (a)Details of certified report on compliance of earlier environmental clearance condition | (i)Certified Compliance By | SPCB | (ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on | | (iii)Letter No. | JSPCB/HO/RNC/CTO-1146757/2017/1096 | (iv)Status of Compliance | Compiled | (v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) | Copy of Certified Compliance Report | (vi)Date of site visit | Jul 20 2017 12:00AM | (b)Details of Capacity Expansion | |
|
S. No. | Product/Activity (Capacity/Area) | Quantity From | Quantity To | Total | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | Liquid Steel | 0 | 73500 | 73500 | Tons per Annum(TPA) | | Others | In House Consumption | (2.) | Power | 0 | 15 | 15 | Mega Watt(MW) | | Others | Captive Use | (3.) | Rolled Product (TMT Bars) | 0 | 67500 | 67500 | Tons per Annum(TPA) | | Road | | (4.) | Iron ore Crushing & Beneficiation Plant | 0 | 201000 | 201000 | Tons per Annum(TPA) | | Others | In House Consumption | (5.) | Billet | 0 | 72000 | 72000 | Tons per Annum(TPA) | | Road | | (6.) | Slag Crushing plant of SMS slag | 0 | 12000 | 12000 | Tons per Annum(TPA) | | Others | In House Consumption | (7.) | Sponge Iron | 90000 | 0 | 90000 | Tons per Annum(TPA) | | Others | In House Consumption | |
| (c)Details of Configuration | |
|
S. No. | Plant / Equipment / Facility | Existing Configuration | Proposed Configuration | Final configuration after expansion | Remarks |
---|
(1.) | Sponge Iron Plant | 3x100 TPD DRI Kiln | 0 | 3x100 TPD DRI Kiln | | (2.) | Iron ore Crushing and Beneficiation plant | - | 80-100 TPH Single stream | 80-100 TPH Single stream | | (3.) | SMS - Induction Furnace | 0 | 2x12 T | 2x12 T | | (4.) | SMS - Billet Caster | - | 2 strand (6x11 m) | 2 strand (6x11 m) | | (5.) | Captive Power Plant | - | WHRB – 3x2 MW, AFBC-1x9 MW | WHRB – 3x2 MW, AFBC-1x9 MW | | (6.) | Slag Crushing plant | - | 5 TPH Single Stream | 5 TPH Single Stream | | |
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | 06 Jun 2018 | (iv)Valid Upto | 31 Dec 2022 | (v)File No. | JSPCB/HO/RNC/CTO-2204067/2018/958 | (vi)Application No. | 958 | (vii)Copy of Consent to operate valid as on date | Copy of Consent to Operate | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 155.5 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 8.20 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 1.42 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 0.984 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | No | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 317300 | (b)Existing quantity of raw material/fuel | 260200 | (c)Total quantity of raw material/fuel | 577500 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | Dolomite | 2300 | Tons per Annum | | Daltonganj, Jharkhand. Katni, M.P. | Road | | 400 | Linkage | | Copy of Linkage | (2.) | Coal | 45000 | Tons per Annum | | CCL | Road | | 150 | Linkage | | Copy of Linkage | (3.) | Iron ore | 201000 | Tons per Annum | | West Singhbhum, Jharkhand & Barbil, Odisha | Road | | 300 | Linkage | | Copy of Linkage | (4.) | Non coking coal for COP | 144000 | Tons per Annum | | CCL | Road | | 150 | Linkage | | Copy of Linkage | (5.) | Sponge Iron | 73500 | Tons per Annum | | In house | Conveyor Belt | | 0 | Others | In House | Copy of Linkage | (6.) | Pig Iron, Purchased & Return Steel Scrap | 14200 | Tons per Annum | | Tata, Bokaro & other places of Jharkhand | Road | | 200 | Linkage | | Copy of Linkage | (7.) | Char | 22000 | Tons per Annum | | Inhouse | Conveyor Belt | | 0 | Others | In House | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 01 Oct 2016 To 31 Dec 2016 | (b)Season | Post-Monsoon | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | PM10 | | Micro Gram per Meter Cube | 96.40 | 45.2 | 94.70 | 100 | (2.) | PM2.5 | | Micro Gram per Meter Cube | 57.7 | 27.6 | 57.25 | 60 | (3.) | NOx | | Micro Gram per Meter Cube | 27.9 | 22.1 | 27.80 | 80 | (4.) | Others | CO | Mili Gram per Meter Cube | 2.13 | 0.37 | 2.11 | 4 | (5.) | SO2 | | Micro Gram per Meter Cube | 16.1 | 7.7 | 16.05 | 80 | |
14.2. No. of Ground Water monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | pH | | | NA | | 8.04 | 7.27 | 6.5 | 8.5 | (2.) | TSS | | | mg/l | | 0 | 0 | 0 | 0 | (3.) | Chlorides | | | mg/l | | 139.3 | 64.2 | 250 | 1000 | (4.) | TDS | | | mg/l | | 629 | 357 | 500 | 2000 | (5.) | Fluoride | | | mg/l | | 1.32 | 0.88 | 1 | 1.5 | (6.) | Heavy Metals | | Zinc | mg/l | | 2.15 | 0.90 | 5 | 15 | (7.) | Total Hardness | | | mg/l | | 328.7 | 187 | 200 | 600 | |
14.3. No. of Surface Water monitoring locations : 2 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | COD | | mg/l | | 50.10 | 48.73 | C | (2.) | BOD | | mg/l | | 13.09 | 11.60 | C | (3.) | pH | | NA | | 7.80 | 7.78 | C | (4.) | DO | | mg/l | | 5.9 | 5.5 | C | |
14.4. No. of Ambient Noise monitoring locations : 8 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Day) | A-weighted decibels(dB(A)) | 55.36 | 52.18 | 75 | (2.) | Leq(Night) | A-weighted decibels(dB(A)) | 44.84 | 40.16 | 70 | |
14.5. No. of Soil Sample Monitored locations : 8 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | N(Nitrogen) | Kilogram per hectare | | 260.5 | 198.7 | (2.) | P(Phosphorus) | Kilogram per hectare | | 20.4 | 10.9 | (3.) | Electric Conductivity | Millisiemens per Centimetre | | 0.333 | 0.276 | (4.) | pH | Others | NA | 7.08 | 6.19 | (5.) | K(Potassium) | Kilogram per hectare | | 170.03 | 98.05 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 11.19 To 2.25 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 1.6 To 5.9 | (c)Whether Ground Water Intersection will be there ? | No | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | Surface | | 2335 | 2 | Copy of Permission Letter | Pipeline | | Others | Pipeline | 28 | 12 Apr 2017 | 2335 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | Zero liquid Discharge | 0 | 0 | NA | Others | Reused | 0 | 0 | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 0 | (b)Total Discharged Water (Kilolitre per Day) | 0 | (c)Total Reused Water (Kilolitre per Day) | 0 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Char | Others | Char | 22000 | Tons | 0 | Others | In House Consumption | Others | Reused | (2.) | Coal Fines | Others | Coal Fines | 4000 | Tons | 0 | Others | In House Consumption | Others | Reused | (3.) | Slag | Others | Slag | 13200 | Tons | 0 | Others | In House Consumption | Others | Reused | (4.) | Scale | Others | Mill Scale | 500 | Tons | 30 | Road | | Others | Sold to Sinter plants | (5.) | Dust | Others | Bag Filter dust | 2730 | Tons | 30 | Road | | Others | Sold to Sinter plants | (6.) | Bottom Ash | Bottom Ash | | 5100 | Tons | 30 | Road | | Others | Road Making | (7.) | Bottom Ash | Bottom Ash | | 5100 | Tons | 30 | Road | | Others | Road Making | (8.) | Fly Ash | Fly Ash | | 41400 | Tons | 40 | Road | | Others | Block/Brick Manufacturers | (9.) | Iron Ore Fines | Others | Dust | 5000 | Tons | 30 | Road | | Others | Sold To Sinter Plants | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | PM10 | | Microgram per Meter Cube | 90.70 | 0.5 | 6.78 | 97.48 | 100 | (2.) | PM2.5 | | Microgram per Meter Cube | 54.70 | 0.5 | 2.06 | 56.76 | 60 | (3.) | SO2 | | Microgram per Meter Cube | 14 | 0.5 | 22.96 | 32.46 | 80 | (4.) | NOx | | Microgram per Meter Cube | 27.40 | 0.5 | 2.99 | 56.19 | 80 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | Stock House | - | 30 | 0.6 | PM10 | | 0.119 | (2.) | Product House 1 | - | 30 | 0.75 | PM10 | | 0.170 | (3.) | AFBC Boiler | - | 70 | 1.25 | PM10 | | 0.630 | (4.) | Material Handling Area | - | 40 | 0.75 | PM10 | | 0.174 | (5.) | Crusher (Ore Crushing) | - | 30 | 0.5 | PM10 | | 0.083 | (6.) | Crusher (Slag Crushing) | - | 30 | 0.5 | PM10 | | 0.083 | (7.) | Material Handling area | - | 40 | 0.75 | PM10 | | 0.174 | (8.) | Material Handling area | - | 40 | 0.75 | PM10 | | 0.174 | (9.) | Cooler Discharge 2 | - | 30 | 0.6 | PM10 | | 0.162 | (10.) | Cooler Discharge 1 | - | 30 | 0.53 | PM10 | | 0.127 | (11.) | Material Handling Area | - | 40 | 0.75 | PM10 | | 0.174 | (12.) | Intermediate bin | - | 30 | 0.7 | PM10 | | 0.162 | (13.) | Product House 2 | - | 30 | 0.75 | PM10 | | 0.170 | (14.) | 2x12T Induction Furnace | - | 40 | 0.55 | PM10 | | 0.560 | (15.) | DRI Kiln #1 with WHRB | - | 65 | 1.6 | PM10 | | 1.579 | (16.) | DRI Kiln #2 & #3 with WHRB | - | 65 | 1.8 | PM10 | | 1.999 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 15000 | (b)Source | DVC/Captive Power Plant | (c)Uploaded Copy of Agreement | Not Applicable | (d)Standby Arrangement (Details of DG Sets) | 1×1010 KVA, 1×500 KVA & 1×320 KVA | (e)Stack Height (in m) | 30 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 0 | (b)Private Land (ha.) | 12.42 | (c)Government Land (ha.) | 0 | (d)Revenue Land (ha.) | 0 | (e)Other Land (ha.) | 0 | Total Land (ha.) | 12.42 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 12093 | (b)Waste/Barren Land (ha.) | 1881.9 | (c)Grazing/ Community Land (ha.) | 3133.1 | (d)Surface Water Bodies (ha.) | 284.8 | (e)Settlements (ha.) | 1809 | (f)Industrial (ha.) | 0 | (g)Forest (ha.) | 12422.5 | (h)Mangroves (ha.) | 0 | (i)Marine Area (ha.) | 0 | (j)Others (ha.) : River Bed | 0 | Total (ha.) | 31624.3 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Main Plant | | 6.34 | | (2.) | Tailing Pond | | 0.28 | | (3.) | Green belt | | 4.36 | | (4.) | Others | Vacant and Parking Area | 1.44 | | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | WLS | No WLS | 0 | No WLS within 10 km radius of Project site | (2.) | ESAs | No ESAs | 0 | No ESAs within 10 km radius of Project site | (3.) | Corridors | No Corridors | 0 | No Corridors within 10 km radius of Project site | (4.) | Wildlife Corridors | No Wildlife Corridor | 0 | No Wildlife corridors within 10 km radius of Project site | (5.) | ESZs | No ESZs | 0 | No ESZs within 10 km radius of Project site | (6.) | Critically Polluted Area | No CPA | 0 | No Critically Polluted area within 10 km radius of Project site | (7.) | NPA | No NPA | 0 | No NPA within 10 km radius of Project site | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Archaeological Sites | | No Archaeological sites | 0 | No Archaeological sites within 10 km radius of Project site | (2.) | Defence Installations | | No Defence Installation | 0 | No Defence Installation within 10 km radius of Project site | (3.) | Others | Religious Place | Maa Chinnamastika Temple | 29 | East direction from project site | (4.) | Forest | | Bundu PF | 4.5 | North Direction from the project site | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
25. | Tree Cutting: | (a)No. of Trees Cut for the Project (if Forest Land not Involved) | Not Applicable | (b)Details of Tree Cutting and Planting of Trees | Not Applicable | |
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 12.42 | (b)Land yet to be acquired(Ha) | 0 | (c)Status of Land acquisition if not acquired | Not Applicable | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 0 | (b)No. of Households | 0 | (c)No. of PDFs (Project Displaced Families) | 0 | (d)No. of PAFs (Project Affected Families) | 0 | (e)Funds Allocated for R&R(in INR) (in Lacs) | 0 | (f)Status of R&R | Completed | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | No | (b)Whether conservation plan for Schedule-I Species has been prepared ? | No | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | No | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | Yes | (i)Details of Water Bodies in Buffer Area | Damodar River | (ii)Direction of Water Bodies in Buffer Area | North East | (iii)Distance of Water Bodies in Buffer Area | 2 | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 80 | (b)Permanent Employment-During Operation | 396 | (c)Temporary Employment- During Construction | 20 | (d)Temporary Employment- During Operation | 0 | (e)No. of working days | 300 | (f)Total Manpower | 496 | |
|
|
S. No. | Description | Existing | Proposed | Total |
---|
(1.) | Total Area of Green Belt | 0 | 4.36 | 4.36 | (2.) | Percentage of Total Project Area | 0 | 33 | 33 | (3.) | No. of Plants | 0 | 6000 | 6000 | (4.) | Funds Allocated | 0 | 3000000 | 3000000 | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Social | The region shall also be benefited from the project as there will be direct and indirect employment of people in the steel plant. Preference will be given to the people of the state possessing requisite skill and qualification criteria. Also there will be lot of scope for indirect employment of the people of the state in and around the project site. | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details : NOT APPLICABLE |
35. Sector Specific Details For Industrial Projects - 1 |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | QCI/NABET/ENV/ACO/17/ 0279 | (ii)Name of the EIA Consultant | Vardan Environet | (iii)Address | D-142, Ground Floor, Sushant Lok-III, Golf Course Ext. Road, Sector-57, Gurugram, Haryana- 122002 | (iv)Mobile No. | 9953147268 | (v)Landline No. | 0124429103 | (vi)Email Id | vardanenviro165@gmail.com | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | Industrial Projects - 1 | (ix)Validity of Accreditation | 09 Nov 2019 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought: |
---|
Sno. | EDS Letter | Remarks | Date of EDS |
---|
1. | NA | You are requested to submit details of ToR in the Form-2 and certificate of compliance of earlier EC from the regional office of MOEFCC | 14 Nov 2018 | 2. | NA | The correction have been made as per the instruction received | 10 Jan 2019 | |
Additional Detail Sought: |
---|
Sno. | ADS Letter | Remarks | Date of ADS |
---|
1. | ADS Reply Letter | Reply of ADS generated on 27/02/2019. | 18 Apr 2019 | 2. | NA | ADS | 27 Feb 2019 | |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | Alok Rungta | Designation | Director | Name of Company (Applicant Name should not be given here) | MAA CHHINNMASTIKA CEMENT AND ISPAT PRIVATE LIMITED | Address | At: Hehal, Post: Barkakana, District: Ramgarh, Jharkhand |
|