Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Development Drilling of 4 wells in Borholla ML block, Jorhat District and development drilling of 8 wells in Nambar ML area, East Lakhibari ML area, Khoraghat ML and Khorghat extension ML area in Gola
(b)Name of the Company / Organisation ONGC
(c)Registered Address NIL
(d)Legal Status of the Company NIL
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant
(b)Designation (Owner/ Partner/ CEO) ChiefGeneralManager
(c)Address NIL
(d)Pin code 110070
(e)E-mail kumar_rajeeva@ongc.co.in
(f)STD Code. (f)Telephone No.
(g)Fax No. 26129067
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity1(b) Offshore and onshore oil and gas exploration, development & production
Minor Activity1(b) Offshore and onshore oil and gas exploration, development & production
(b)Category A
(c)Proposal Number IA/AS/IND2/83554/2014
(d)Master Proposal Number(Single Window) SW/83543/2018
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Jorhat and Golaghat districts
(b)Pincode 785685
(c)Bounded Latitudes (North)
From
Degree 2930625.5
Minutes
Second
From
Degree 621248.4
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 2880626.8
Minutes
Second
From
Degree 586856.6
Minutes
Second
(e)Survey of India Topo Sheet No. 00
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 100
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 00
(j)Seismic Zone 5
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Assam
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number J-11011/49/2014- IA II
(b)Date of Apply of TOR 03 Feb 2014
(c)Date of Issue of TOR / Standard ToR 18 Dec 2014
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :04 Apr 2017
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :06 May 2017
Distance of Public Hearing Venue from the Proposed Project :10
Bodosa Club cum Bodo library, Rangjali Nagar, near KHDC, Uriamghat, Dist- Golaghat Assam
State :Assam
District :Golaghat
Tehsil :Golaghat
Village :Uriamghat
63Effects of drilling on paddy fields, compensation issues, pollution control measures.Others
(2.)
Date of Advertisement :04 Apr 2017
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :09 May 2017
Distance of Public Hearing Venue from the Proposed Project :5
Sonowal Kachari kala Kristi Bikash kendra
State :Assam
District :Jorhat
Tehsil :Titabar
Village :Borholla
45Drill site affects agricultural area, more CSR activities, compensation paymentOthers
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Development DrillingTotal 12 wells
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Oil220Kilo Litre per DayOtherspipeline and tankers
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 240
(b) Funds Allocated for Environment Management (Capital) (in Crores) 0.17
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 3.6
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.28
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 06
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 6
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)diesel6Kilo Litre per DayNAOthersNA0 OthersNACopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Oct 2015 To 31 Dec 2015
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 08
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube64.443.500NAAQS guidelines
(2.)PM2.5Micro Gram per Meter Cube00000000
(3.)NOxMicro Gram per Meter Cube16.539.2400NAAQS guidelines
(4.)SO2Micro Gram per Meter Cube8.265.2300NAAQS guidelines
    14.2.     No. of Ground Water monitoring locations : 07
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA8.26.818.57.0
(2.)TDSmg/l3882405002000
(3.)Chloridesmg/l5.963.972501000
(4.)Fluoridemg/l0.520.231.01.5
(5.)TSSmg/l34190000
(6.)Total Hardnessmg/l11488200600
(7.)Heavy MetalsZnmg/l0.210.06515
    14.3.     No. of Surface Water monitoring locations : 07
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA8.57.2D
(2.)CODmg/l23.013.0D
(3.)DOmg/l7.65.2D
(4.)BODmg/l5.02.5D
    14.4.     No. of Ambient Noise monitoring locations : 08
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))67.841.5CPCB Guidelines
(2.)Leq(Night)A-weighted decibels(dB(A))59.830.0CPCB Guidelines
    14.5.     No. of Soil Sample Monitored locations : 05
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pHOthersNA7.26.1
(2.)N(Nitrogen)OthersPercentage by mass3.141.23
(3.)K(Potassium)Milliequivalents per 100 Gram0.070.02
(4.)P(Phosphorus)Milliequivalents per 100 Gram1.91.3
(5.)Electric ConductivityOthersmicro siemens per centimeter97.467.8
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 3.8 To 7.96
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 3.31 To 6.89
(c)Whether Ground Water Intersection will be there ? NA
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersTankers250 Not Appliacble modeOthersTankersOthersNANA18 Dec 201425
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Sewage Water1012septic tanks followed by soak pitsOthersseptic tanks followed by soak pits100
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 10
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 10
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Waste lube/System oilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)0.15Kilolitre00RoadAuthorized Recyclers
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM2.5Microgram per Meter Cube0000000000
(2.)SO2Microgram per Meter Cube8.26005.013.26NAAQS
(3.)Others(Specify)HCMicrogram per Meter Cube2.67004.06.67NAAQS
(4.)NOxMicrogram per Meter Cube16.53002.018.53NAAQS
(5.)PM10Microgram per Meter Cube64.40016.2880.68NAAQS
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)DG SetsDiesel7.70.5SO20.0025
(2.)DG SetsDiesel7.70.5NOx0.001
(3.)DG SetsDiesel7.70.5PM100.008
(4.)DG SetsDiesel7.70.5OthersHC0.036
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 1430
(b)Source DG Set
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 1430
(e)Stack Height (in m) 7.7
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 13.27
(b)Private Land (ha.) 0
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 8.0
(e)Other Land (ha.) 0
    Total Land (ha.) 21.27
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 1067
(b)Waste/Barren Land (ha.) 190
(c)Grazing/ Community Land (ha.) 00
(d)Surface Water Bodies (ha.) 557
(e)Settlements (ha.) 366
(f)Industrial (ha.) 00
(g)Forest (ha.) 390
(h)Mangroves (ha.) 00
(i)Marine Area (ha.) 00
(j)Others (ha.) : Follow land 582
    Total (ha.) 3152
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)OthersNA0000
Total (ha.) 0
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)ESAsNA00NA
(2.)Critically Polluted AreaNA00NA
(3.)WLSNA00NA
(4.)CorridorsNA00NA
(5.)Wildlife CorridorsNA00NA
(6.)ESZsNA00NA
(7.)NPANA00NA
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Archaeological SitesNA00NA
(2.)Defence InstallationsNA00NA
(3.)ForestNambar Forest008 wells are falling in the Nambar Forest area.
23.3.
(a)Whether Noc / Permission from the competent authority is required? Yes
(i)Uploaded Noc / Permission from the competent authority Copy of Noc / Permission from the competent authority
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? Yes
(a)Forests Clearance Status Application for Forest Clearance yet to be submitted
(b)Legal Status of Forest Land Reserved
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 13.27
(b)Land yet to be acquired(Ha) 8
(c)Status of Land acquisition if not acquired Forest land acquired.Nonforest land to be acquired
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Yet To Start
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area 1 pond in East Likhibari ML area and 2 Ponds in Nambar ML area
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area 1 River (Dhans-iri) which passes through Nambar ML area, Khoraghat ML area and Khoraghat extension ML area)
(ii)Direction of Water Bodies in Buffer Area North
(iii)Distance of Water Bodies in Buffer Area 0
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 5
(b)Permanent Employment-During Operation 50
(c)Temporary Employment- During Construction 20
(d)Temporary Employment- During Operation 30
(e)No. of working days 120
(f)Total Manpower 105
32.
Green Belt in Ha:
(a)Total Area of Green Belt 00
(b)Percentage of Total Project Area 0.00
(c)No. of Plants to be Planted 00
(d)Funds Allocated for Plantation 00
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.       Project Benefits
S. No. Type of Project BenefitsDetails of Project Benefits
NIL
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1417/ SA 030
(ii)Name of the EIA Consultant Asian Consulting Engineers Pvt Ltd.
(iii)Address 66, 2nd FLOOR Hemkunt Colony, Nehru Place, Delhi- 110048
(iv)Mobile No. 9312693905
(v)Landline No. 41635644
(vi)Email Id info@asianconsulting.org
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 17 Nov 2017
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAPlease inform/clarify the following:- - Copy of the ToR dated 18/12/2014 not attached. Any extension thereof. - Certificate of Accreditation for the EIA consultant not attached. - Status of the proposal for forest clearance as indicated at item 24 of Form-2. - Status of acquisition of land of 13.27 ha of land. 11 Nov 2018
2.NAThe correction have been made as per the instruction received 19 Nov 2018
3.NA- Details provided in response to our earlier observations dated 11/11/2018, are not consistent/matching with those mentioned in column 24 (for forest clearance) & column 26 (land acquisition status) of Form-2, and need to be corrected for factual information. - Please inform present status of accreditation of the EIA Consultant M/s Asian Consulting Engineers Pvt Ltd. 03 Dec 2018
4.NAThe correction have been made as per the instruction received 10 Dec 2018
5.NAIn view of the discrepancies still persisting (Column 24 shows application for forest clearance yet to be submitted, Column 26 shows forest land acquired), we reiterate our observations dated 3/12/2018 for the needful. 16 Dec 2018
6.NAThe correction have been made as per the instruction received 31 Dec 2018
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of Applicant
DesignationChiefGeneralManager
Name of Company (Applicant Name should not be given here)ONGC
AddressCorporate HSE, 8th Floor Core IV, SCOPE Minar, Delhi 10092