Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Proposed POL Depot by Hindustan Petroleum Corporation Limited (HPCL)
(b)Name of the Company / Organisation HPCL HISAR
(c)Registered Address Hindustan Petroleum Corporation Limited,Petroleum House, 17 Jamshedji Tata Road, Mumbai,Hisar,Haryana-400020
(d)Legal Status of the Company Central PSU
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Sanjeev Kumar Ishwar
(b)Designation (Owner/ Partner/ CEO) manager
(c)Address Hindustan Petroleum Corporation Limited,Gresham House, 2nd Floor, Sir PM Road,Fort, Mumbai,Mumbai,Mumbai City,Maharashtra-400001
(d)Pin code 400001
(e)E-mail skishwar@hpcl.in
(f)STD Code. 22(f)Telephone No. 22759508
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity6(b)Isolated storage & handling of hazardous chemicals (As per threshold planning
Minor Activity
(b)Category B1
   Reason for Applying at Ministry SEIAA
(c)Proposal Number IA/HR/IND2/83334/2018
(d)Master Proposal Number(Single Window) SW/83283/2018
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. For approach road (Khasra Nos. for depot area are
(b)Pincode 125049
(c)Bounded Latitudes (North)
From
Degree 29.29473
Minutes
Second
From
Degree 29.2958
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 76.02208
Minutes
Second
From
Degree 76.02646
Minutes
Second
(e)Survey of India Topo Sheet No. H43P15, H43P16, H43Q4, H43Q3
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 220
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 0
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Haryana
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number SEIAA/HR/18/395
(b)Date of Apply of TOR 03 Mar 2018
(c)Date of Issue of TOR / Standard ToR 12 Apr 2018
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :19 Aug 2018
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :27 Sep 2018
Distance of Public Hearing Venue from the Proposed Project :0
Premises of Hindusthan Petroleum corporation limited, Village-Datta, Tehsil- Hansi, District- Hisar, state-Haryana (Project site).
State :Haryana
District :Hisar
Tehsil :Hansi
Village :Datta
55Details about the approach road to the project site and bypass road widening were asked. Inquiry about the safety measures taken for operation, and Fire safety awareness details to the local villagersOthersAdditional Deputy Commissioner, Hisar.
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Storage Facility79229 KLFor MS, HSD, Ethanol and Biodiesel
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)ETHANOL: UG TANK180OthersKilo Litre (KL)Road
(2.)MS: UG TANK70OthersKilo Litre (KL)Road
(3.)SLOP TANKS : A/G TANK100OthersKilo Litre (KL)Road
(4.)SLOP TANKS: UG TANK40OthersKilo Litre (KL)Road
(5.)MS: A/G TANK28629OthersKilo Litre (KL)Road
(6.)ETHANOL: A/G IFR Tanks2260OthersKilo Litre (KL)Road
(7.)BIO DIESEL: A/G CR Tanks3600OthersKilo Litre (KL)Road
(8.)HSD: UG TANK70OthersKilo Litre (KL)Road
(9.)BIO DIESEL: UG Tank180OthersKilo Litre (KL)Road
(10.)BIO DIESEL: A/G CR Tanks3600OthersKilo Litre (KL)Road
(11.)HSD: A/G CR TANK43200OthersKilo Litre (KL)Road
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 01 Jan 1990
(iv)Valid Upto 01 Jan 1990
(v)File No. Not applicable
(vi)Application No. No CTO obtained as this is new Project
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 255
(b) Funds Allocated for Environment Management (Capital) (in Crores) 0.425
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.85
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.13
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 0
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 0
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)STORAGE FACILITY0OthersNOT APPLICATIONNOT APPLICATIONOthersNIL0 OthersNOT APPLICATIONCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Feb 2018 To 31 May 2018
(b)Season Summer
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 08
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM2.5Micro Gram per Meter Cube34.623.534.37860
(2.)NOxMicro Gram per Meter Cube20.111.219.92280
(3.)PM10Micro Gram per Meter Cube69.34768.854100
(4.)SO2Micro Gram per Meter Cube13.26.213.0680
    14.2.     No. of Ground Water monitoring locations : 06
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA8.17.16.58.5
(2.)TDSmg/l5313645002000
(3.)TSSmg/l20.112
(4.)Heavy MetalsZincmg/l0.240.06515
(5.)Total Hardnessmg/l289266200600
(6.)Chloridesmg/l17296250100
(7.)Fluoridemg/l0.50.31.01.5
    14.3.     No. of Surface Water monitoring locations : 02
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA7.637.55C
(2.)DOmg/l6.86.6C
(3.)CODmg/l1816C
(4.)BODmg/l3.73.1C
    14.4.     No. of Ambient Noise monitoring locations : 08
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))57.941.370
(2.)Leq(Day)A-weighted decibels(dB(A))68.252.475
    14.5.     No. of Soil Sample Monitored locations : 08
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)N(Nitrogen)Kilogram per hectare230187
(2.)P(Phosphorus)Kilogram per hectare18.510.9
(3.)K(Potassium)Kilogram per hectare234202
(4.)Electric ConductivityMillisiemens per Centimetre373298
(5.)pHOthers1:5 Soil Suspension7.476.20
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 1.53 To 19.25
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 0.43 To 18.30
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater50Copy of Permission LetterPipelineOthersBore well21-4/1392/HR/IND/201825 Sep 20185
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic Sewage11Septic tank and soak pitOtherssoak pit and septic tank01
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 1
(b)Total Discharged Water (Kilolitre per Day) 1
(c)Total Reused Water (Kilolitre per Day) 0
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Municipal Solid wasteMunicipal Solid Waste3000Tons0RoadOthersLocal Municipal Body
(2.)Sludge from oil tanksHazardous Waste (as per Hazardous and Other Waste Management rules 2016)0.2Tons15RoadAuthorized Recyclers
(3.)Spent lube oilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)0.15Kilolitre15RoadAuthorized Recyclers
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)NOxMicrogram per Meter Cube20.10.84.024.180
(2.)PM2.5Microgram per Meter Cube34.60.82.07436.67460
(3.)SO2Microgram per Meter Cube13.20.81.1014.380
(4.)PM10Microgram per Meter Cube69.30.82.07471.374100
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)DG SET 600KVA (2NOS)Diesel100.2OthersCO0.043 g/s
(2.)DG SET 400KVA (1NOS)Diesel90.15PM100.0073 g/s
(3.)DG SET 400KVA (1NOS)Diesel90.15OthersCO0.023 g/s
(4.)DG SET 600KVA (2NOS)Diesel100.2PM100.0139 g/s
(5.)DG SET 600KVA (2NOS)Diesel100.2NOx0.343 g/s
(6.)DG SET 400KVA (1NOS)Diesel90.15NOx0.18 mg/s
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 1000
(b)Source Haryana State Electricity Board (HSEB)
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 600 KVA - 2 nos, 400 KVA - 1 nos
(e)Stack Height (in m) 10
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 18.36
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 18.36
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 1.61
(b)Waste/Barren Land (ha.) 16.75
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 0
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : NIL 0
    Total (ha.) 18.36
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Main Plant16.602
(2.)OthersApproach road1.772
Total (ha.) 18.374
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)WLSNIL0Not within 10km radius
(2.)ESAsNIL0Not within 10km radius
(3.)Critically Polluted AreaNIL0Not within 10km radius
(4.)NPANIL0Not within 10km radius
(5.)ESZsNIL0Not within 10km radius
(6.)CorridorsNIL0Not within 10km radius
(7.)Wildlife CorridorsNIL0Not within 10km radius
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Archaeological SitesNONE0Not within 10km radius
(2.)Defence InstallationsNONE0Not within 10km radius
(3.)ForestNONE0Not within 10km radius
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) Not Applicable
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 1.772
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired Only for Approach road
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 5
(b)Permanent Employment-During Operation 45
(c)Temporary Employment- During Construction 390
(d)Temporary Employment- During Operation 5
(e)No. of working days 300
(f)Total Manpower 445
32.
Green Belt in Ha:
(a)Total Area of Green Belt 6.05
(b)Percentage of Total Project Area 32.95
(c)No. of Plants to be Planted 58
(d)Funds Allocated for Plantation 1200000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialThe proposed project is expected to bring significant socio-economic and environmental benefits both at local and national level like; Projects of this category will improve availability of the physical infrastructures like drainage, communication and transportation facilities, etc.Also the project will indirectly boost up the social infrastructure of the surrounding like local education, medical and communication of the surrounding area and the project will provide indirect employment to unskil
(2.)FinancialThe proposed project in Haryana will improve supply position of the petroleum products which is vital for economic growth as well as improving the quality of life. The improved petroleum supply will have strong logistic support for delivering the products to customers without interruption.
(3.)EnvironmentalIndirect benefits are also expected to occur in the region by way of reduction of delivery distance by tankers which in turn will reduce trucks on the road reducing the vehicular load on the public roads. This will result in reduced air pollution and reduced probability of accidents on the roads due to less movement of tank trucks HPCL will lay its focus on CSR activities specially on local communities in and around areas of Company's operations.
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1619/RA0048
(ii)Name of the EIA Consultant ABC TECHNO LABS INDIA PRIVATE LIMITED
(iii)Address 400, 13th street, SIDCO Industrial estate, North Phase, ambattur, chennai - 600098
(iv)Mobile No. 9444260000
(v)Landline No. 0442625779
(vi)Email Id eia@abctechnolab.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 25 May 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAPlease inform/clarify the following:- - Whether the proposed POL storage is permitted at the project site and/or in conformity with land use of the area. That needs to be confirmed along with supporting documents. - Whether any permission is required from the SPCB to allow such a g unit in non-industrial area. - Approval for project site and layout plan by PESO from safety considerations. 01 Nov 2018
2.NAThe correction have been made as per the instruction received 02 Nov 2018
3.NAAs per one of the specific conditions of the ToR granted by SEIAA Haryana vide letter dated 15/5/2018, permission was to be obtained for 58 kl of water. Please inform the compliance in this regard. 08 Nov 2018
4.NAAs per one of the specific conditions of the ToR granted by SEIAA Haryana vide letter dated 15/5/2018, permission was to be obtained for 58 kl of water. Please inform the compliance in this regard. 08 Nov 2018
5.NAThe correction have been made as per the instruction received 09 Nov 2018
6.NAIn view of your submissions, ToR dated 15/5/2018 should have been amended accordingly. The said condition is one of the specific conditions stipulated in the said ToR, and as such the proposal for EC is not compliant with that. 13 Nov 2018
7.NAThe correction have been made as per the instruction received 17 Nov 2018
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantSanjeev Kumar Ishwar
Designationmanager
Name of Company (Applicant Name should not be given here)HPCL HISAR
AddressHindustan Petroleum Corporation Limited
Print