Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Proposed Expansion of Isolated Storage Terminal with additional One Storage Tanks for MS (9000 KL)
(b)Name of the Company / Organisation INDIAN OIL CORPORATION LIMITED MARKETING DIVISION
(c)Registered Address Indian Oil Bhavan, G-9, Ali Yavar Jung Marg Bandra (East), Mumbai-400051,,New Delhi,Delhi-400051
(d)Legal Status of the Company Central PSU
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Binod Jha
(b)Designation (Owner/ Partner/ CEO) CTM
(c)Address IOCL, Tikri Kalan Terminal, NH No.-10, Tikri Kalan Ghevra Mode, New Delhi-110041,,Punjabi Bagh,West,Delhi-110041
(d)Pin code 110041
(e)E-mail bkjha@indianoil.in
(f)STD Code. 11(f)Telephone No. 28353520
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity6(b)Isolated storage & handling of hazardous chemicals (As per threshold planning
Minor Activity6(b)Isolated storage & handling of hazardous chemicals (As per threshold planning
(b)Category B1
   Reason for Applying at Ministry SEIAA
(c)Proposal Number IA/DL/IND2/83328/2007
(d)Master Proposal Number(Single Window) SW/83302/2018
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. IOCL Tikri Kalan Terminal, N.H – 10, Tikri Kalan-
(b)Pincode 110041
(c)Bounded Latitudes (North)
From
Degree 3174862.81
Minutes
Second
From
Degree 3175253.57
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 693874.03
Minutes
Second
From
Degree 694172.10
Minutes
Second
(e)Survey of India Topo Sheet No. H43 W13, H43 X1, H43 W14, H43 X2
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 212
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 0
(j)Seismic Zone 4
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Delhi
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number J-11011/287/2017-IA-II (I)
(c)Date of Issue of TOR 05 Jul 2007
(f)Previous TOR Letter Copy of Previous TOR letter
(b)Date of Apply of EC 02 Dec 2008
(c)Date of Issue of EC 30 Jan 2009
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :19 Jul 2018
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :27 Aug 2018
Distance of Public Hearing Venue from the Proposed Project :0
IOCL Tikri Kalan Terminal, N.H – 10, Tikri Kalan- Ghevra Mode, New Delhi – 110041
State :Delhi
District :West
Tehsil :Rajouri Garden
Village :Tikri Kalan
47During Public Hearing following issues are raised: 1. Why there is requirement of additional tank? 2. What are the safety features provided along with new additional tank? 3. What is the safety aspOthersSh. Suresh Kumar Meena (ADM, West District, GNCTD) Sh. B.L Chawla (Sr. Environmental Engineer, DPCC) Sh. Surinder Singh (Environmental Engineer, DPCC) Sh. S.K Goyel (Environmental Engineer, DPCC)
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Lucknow
(iii)Letter No. IOC/TKR/EC/Compliance
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Jan 2 2019 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)MS14830900023830Kilo Litre per Day(KLD)OthersPipeline
(2.)SKO135101351Kilo Litre per Day(KLD)OthersPipeline
(3.)Ethanol6000600Kilo Litre per Day(KLD)OthersPipeline
(4.)HSD22879022879Kilo Litre per Day(KLD)OthersPipeline
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)MS STORAGE TANKS4 TANKS1 TANK5 TANKSISOLATED STORAGE FACILITY
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 17 Dec 2014
(iv)Valid Upto 27 Jul 2019
(v)File No. DPCC/CMC/2014/35253
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 19.3
(b) Funds Allocated for Environment Management (Capital) (in Crores) 6.70
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.193
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.261
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 9000
(b)Existing quantity of raw material/fuel 14830
(c)Total quantity of raw material/fuel 23830
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)MS23830OthersKLMathura Jalandhar pipelineOthersPipeline147 LinkageCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Mar 2017 To 31 May 2017
(b)Season Summer
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM2.5Micro Gram per Meter Cube111.680.1106.360
(2.)NOxMicro Gram per Meter Cube33.821.128.780
(3.)SO2Micro Gram per Meter Cube17.49.114.980
(4.)PM10Micro Gram per Meter Cube216.1156.9199.15100
(5.)OthersHCMicro Gram per Meter Cube15096135.875-
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA7.627.126.58.5
(2.)Chloridesmg/l28549122501000
(3.)Total Hardnessmg/l1358856200600
(4.)Fluoridemg/l1.20.611.5
(5.)OthersTurbidityOthersNTU3.81.6515
(6.)TDSmg/l560821825002000
(7.)TSSmg/l0000
    14.3.     No. of Surface Water monitoring locations : 0
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)DOmg/l00C
(2.)CODmg/l00C
(3.)pHNA00C
(4.)BODmg/l00C
(5.)OthersTDSmg/l00C
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))82.250.575
(2.)Leq(Night)A-weighted decibels(dB(A))77.640.270
    14.5.     No. of Soil Sample Monitored locations : 4
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)K(Potassium)Milliequivalents per 100 Gram1.10.6
(2.)N(Nitrogen)Othersmg/100gm1158.4579.2
(3.)P(Phosphorus)Othersmg/100gm367.4206.1
(4.)pHOthers-7.827.21
(5.)Electric ConductivityOthersS/m00
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 8 To 8.1
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 0 To 0
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersLocal Source2015Copy of Permission LettermodeOthersTankerOthersTankerDJB/Z.E-IV/West-III/2018-19/11117 May 201836900
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic50NAOthersSoak Pit05
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 5
(b)Total Discharged Water (Kilolitre per Day) 5
(c)Total Reused Water (Kilolitre per Day) 0
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Tank Cleaning SludgeHazardous Waste (as per Hazardous and Other Waste Management rules 2016)6Tons10RoadOthersAuthorize Vendor
(2.)Used OilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)0.52Tons10RoadOthersAuthorize Vendor
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM2.5Microgram per Meter Cube00000
(2.)SO2Microgram per Meter Cube00000
(3.)NOxMicrogram per Meter Cube00000
(4.)Others(Specify)HCMicrogram per Meter Cube00000
(5.)PM10Microgram per Meter Cube00000
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)Fire Water Engine PumpHSD3.50.15OthersPM, SO2 and NOx--
(2.)DG SetHSD40.15OthersPM, SO2 and NOx--
(3.)Fire Water Engine PumpHSD3.50.15OthersPM, SO2 and NOx--
(4.)Fire Water Engine PumpHSD3.50.15OthersPM, SO2 and NOx--
(5.)DG SetHSD40.15OthersPM, SO2 and NOx--
(6.)DG SetHSD40.15OthersPM, SO2 and NOx--
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 1000
(b)Source Grid supply (Existing source)
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 3 DG Sets
(e)Stack Height (in m) 4
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 16.1874
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 16.1874
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 0.011682
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0.001929
(d)Surface Water Bodies (ha.) 0.000405
(e)Settlements (ha.) 0.009828
(f)Industrial (ha.) 0
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Fellow land, Open scrub & Dry river channel 0.009207
    Total (ha.) 0.033051
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Main Plant7.0936
(2.)Built Up Area0.2023Adm. Building & Other blocks
(3.)Green belt8.8915Inc. Misc. & Open space
Total (ha.) 16.1874
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)WLSNA0NA
(2.)NPANA0NA
(3.)ESAsNA0NA
(4.)CorridorsNA0NA
(5.)Wildlife CorridorsNA0NA
(6.)Critically Polluted AreaNA0NA
(7.)ESZsNA0NA
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestNA0NA
(2.)Archaeological SitesNA0NA
(3.)Defence InstallationsNA0NA
(4.)OthersOthersNA0NA
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) Not Applicable
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 16.1874
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Yet To Start
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 10
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 0
(e)No. of working days 360
(f)Total Manpower 10
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt30775030775
(2.)Percentage of Total Project Area19.01019.01
(3.)No. of Plants600006000
(4.)Funds Allocated000
    33.       Project Benefits
S. No. Type of Project BenefitsDetails of Project Benefits
NIL
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1720/ RA 051
(ii)Name of the EIA Consultant Eco Chem Sales and Services
(iii)Address Office floor, Ashoka Pavilion ’A’ New Civil Road, Surat, 395001
(iv)Mobile No. 0
(v)Landline No. 0261223163
(vi)Email Id eco@ecoshripad.com
(vii)Category of Accreditation B
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 29 Feb 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAPlease inform/clarify the following:- - No compliance report from the Ministry's Regional Office for the EC dated 30/1/2009. - Permission for water withdrawal of 20 cum/day. - Base line air quality already exceeding in terms of PM10 & PM2.5. What would be incremental values due to the proposed expansion. - No details provided against item 6 of Form-2. Even, the entries against item 9, need to be confirmed. 02 Nov 2018
2.NAThe correction have been made as per the instruction received 22 Nov 2018
3.NAAs observed earlier also, please submit compliance report from the Ministry's Regional Office for the EC dated 30/1/2009 for consideration of the proposal. 04 Dec 2018
4.NAThe correction have been made as per the instruction received 23 Jan 2019
5.NAPlease submit copy of the EC dated 30/1/2009, and revise entries in column 6 of Form-2 accordingly as requested earlier also. Also submit CTO from the SPCB/DPCC showing present storage capacity of 39660 kl. 01 Feb 2019
6.NAThe correction have been made as per the instruction received 04 Feb 2019
7.NAThis refers to our earlier observations. Please inform about the EC for existing LPG bottling plant (reflected in the EC dated 30/1/2009) within the premises, and the compliance status thereof. 09 Feb 2019
8.NAThe correction have been made as per the instruction received 25 Feb 2019
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1.NA

Deferred

17 May 2019
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantBinod Jha
DesignationCTM
Name of Company (Applicant Name should not be given here)INDIAN OIL CORPORATION LIMITED MARKETING DIVISION
AddressIndian Oil Bhavan, G-9, Ali Yavar Jung Marg Bandra (East), Mumbai-400051
Print