Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Proposed Manufacturing of Specialty chemicals & Agro Chemical products
(b)Name of the Company / Organisation CRIMSUN ORGANICS PRIVATE LIMITED
(c)Registered Address Plot No. C-10 & C-11, SIPCOT Industrial complex, kudikadu village, Cuddalore Taluk , Cuddalore District Tamilnadu,,Cuddalore,Tamil Nadu-607005
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant S. Ramesh Prabhakaran
(b)Designation (Owner/ Partner/ CEO) Managing Director
(c)Address Plot No. C-10 and C-11, SIPCOT industrial complex, Kudikadu village, Cuddalore Taluk, Cuddalore District. Tamil nadu,,Cuddalore,Cuddalore,Tamil Nadu-607005
(d)Pin code 607005
(e)E-mail drgvraj@hotmail.com
(f)STD Code. 4142(f)Telephone No. 239933
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(b) Pesticides industry and pesticide specific intermediates (excluding formulations)
5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
Minor Activity
(b)Category A
(c)Proposal Number IA/TN/IND2/75539/2018
(d)Master Proposal Number(Single Window) SW/82976/2018
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Plot No. C-9, C-10 and C-11
(b)Pincode 607005
(c)Bounded Latitudes (North)
From
Degree 11.679589
Minutes
Second
From
Degree 11.681425
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 79.754911
Minutes
Second
From
Degree 79.756800
Minutes
Second
(e)Survey of India Topo Sheet No. 58 M/9, 58 M/10 & 58 M/13
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 6.096
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 0.38
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Tamil Nadu
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)HaryanaPanchkulaPanchkulaRattewali
(2.)Tamil NaduCuddaloreCuddalore
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number IA-J-11011/207/2018-IA-II(I)
(b)Date of Apply of TOR 23 Jun 2018
(c)Date of Issue of TOR / Standard ToR 27 Jul 2018
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason Project Falls under notified Industrial Area
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Reactor with SS condenser7 KL1 No
(2.)Reactor with Glass condenser8 KL1 No
(3.)Steam Boiler3 ton per hour2 Nos (Existing-1 and Proposed-1)
(4.)Moving bed bioreactor COD100 KLD1 No
(5.)3 stage scrubber600 kgs gas/hour2 Nos (Existing-1 and Proposed-1)
(6.)Wet scrubber10 kgs/hour1 No
(7.)Storage tank-1Old -15 KL and New-30 KL2 Nos (Existing-1 and Proposed-1)
(8.)Air compressor60 CFM2 Nos (Existing-1 and Proposed-1)
(9.)Storage tank15 KL3 Nos
(10.)Storage tank25 KL1 No
(11.)Storage tank30 KL3 Nos
(12.)Above ground storage tank20 KL (New)3 Nos
(13.)Reactor with reflux column10 KL7 Nos (Existing-1 and Proposed-6)
(14.)Storage tank-2Old- 15 KL and New-30 KL2 Nos (Existing-1 and Proposed-1)
(15.)Storage Tank-315 KL1 No
(16.)Spare tank20 KL1 No
(17.)Reactor with graphite condenser6.3 KL1 No
(18.)Bromine Tank15 KL1 No
(19.)Reactor with graphite condenser6.3 KL7 Nos (Existing-1 and Proposed-6)
(20.)Chilled brine plant30 TR2 Nos (Existing-1 and Proposed-1)
(21.)Aerator100 KLD1 No
(22.)Ro plant100 KLD2 Nos (Existing-1 and Proposed-1)
(23.)Reactor with glass reflux system8 KL1 No
(24.)Reactor with SS condenser4 KL1 No
(25.)Autoclave3 KL1 No
(26.)MEE2 MT per hour2 Nos (Existing-1 and Proposed-1)
(27.)Cooling tower400 TR4 Nos (Existing-1 and Proposed-3)
(28.)Reactor2 KL1 No
(29.)Reactor with glass reflux system2 KL3 Nos (Existing-1 and Proposed-2)
(30.)Reactor with graphite condenser4 KL1 No
(31.)Reactor with SS condenser14 KL7 Nos (Existing-1 and Proposed-6)
(32.)Above ground storage tank15 KL (New)3 Nos
(33.)Fire water circulation6 kgs/cm21 No
(34.)Storage tank furnace oil30 KL1 No
(35.)Intermediate tank20 KL1 No
(36.)Reactor attached with reflux column3 KL1 No
(37.)Chilled water plant120 TR3 Nos (Existing-1 and Proposed-2)
(38.)Ion Exchanger5 KL per hour1 No
(39.)Reactor with SS condenser5 KL1 No
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Hexaconazole30OthersTons per monthRoad,Rail,Otherssea
(2.)Difenoconazole15OthersTons per monthRoad,Rail,Otherssea
(3.)Trifloxystrobin20OthersTons per monthRoad,Rail,Otherssea
(4.)Cymoxanil20OthersTons per monthRoad,Rail,Otherssea
(5.)Pyroclostrobin20OthersTons per monthRoad,Rail,Otherssea
(6.)Metalaxil20OthersTons per monthRoad,Rail,Otherssea
(7.)Boscalid20OthersTons per monthRoad,Rail,Otherssea
(8.)Picoxystrobin20OthersTons per monthRoad,Rail,Otherssea
(9.)Mesotrione20OthersTons per monthRoad,Rail,Otherssea
(10.)Imazamox30OthersTons per monthRoad,Rail,Otherssea
(11.)Pinoxaden30OthersTons per monthRoad,Rail,Otherssea
(12.)Ametryn30OthersTons per monthRoad,Rail,Otherssea
(13.)Tembotrione20OthersTons per monthRoad,Rail,Otherssea
(14.)Halosulfuron20OthersTons per monthRoad,Rail,Otherssea
(15.)Chlorimuron-ethyl20OthersTons per monthRoad,Rail,Otherssea
(16.)Dichlorvos (DDVP)50OthersTons per monthRoad,Rail,Otherssea
(17.)Diafenthiuron30OthersTons per monthRoad,Rail,Otherssea
(18.)Alphacypermethrin20OthersTons per monthRoad,Rail,Otherssea
(19.)Fipronil20OthersTons per monthRoad,Rail,Otherssea
(20.)Acetamiprid30OthersTons per monthRoad,Rail,Otherssea
(21.)Flonicamid20OthersTons per monthRoad,Rail,Otherssea
(22.)Metaflumizone20OthersTons per monthRoad,Rail,Otherssea
(23.)Spirotetramate20OthersTons per monthRoad,Rail,Otherssea
(24.)Thiophanate Methyl50OthersTons per monthRoad,Rail,Otherssea
(25.)Topramezone20OthersTons per monthRoad,Rail,Otherssea
(26.)Propiconazole30OthersTons per monthRoad,Rail,Otherssea
(27.)Carbendazim50OthersTons per monthRoad,Rail,Otherssea
(28.)Pretilachlor50OthersTons per monthRoad,Rail,Otherssea
(29.)Buprofezin30OthersTons per monthRoad,Rail,Otherssea
(30.)Etoxazole20OthersTons per monthRoad,Rail,Otherssea
(31.)Spiromesifen20OthersTons per monthRoad,Rail,Otherssea
(32.)Parachlorobenzyl cyanide20OthersTons per monthRoad,Rail,Otherssea
(33.)Pyrazole20OthersTons per monthRoad,Rail,Otherssea
(34.)Tricyclazole50OthersTons per monthRoad,Rail,Otherssea
(35.)Cyproconazole30OthersTons per monthRoad,Rail,Otherssea
(36.)Tebuconazole20OthersTons per monthRoad,Rail,Otherssea
(37.)Thifluzamide20OthersTons per monthRoad,Rail,Otherssea
(38.)Glyphosate50OthersTons per monthRoad,Rail,Otherssea
(39.)Clodinafop-propargyl20OthersTons per monthRoad,Rail,Otherssea
(40.)Bis-pyribac Sodium20OthersTons per monthRoad,Rail,Otherssea
(41.)Quizalofop20OthersTons per monthRoad,Rail,Otherssea
(42.)Propaquizalofop20OthersTons per monthRoad,Rail,Otherssea
(43.)Fluroxypyr20OthersTons per monthRoad,Rail,Otherssea
(44.)Penoxsulam20OthersTons per monthRoad,Rail,Otherssea
(45.)Pendimethalin30OthersTons per monthRoad,Rail,Otherssea
(46.)Nicosulfuron20OthersTons per monthRoad,Rail,Otherssea
(47.)Metsulfuron20OthersTons per monthRoad,Rail,Otherssea
(48.)Acephate30OthersTons per monthRoad,Rail,Otherssea
(49.)Thiamethoxam30OthersTons per monthRoad,Rail,Otherssea
(50.)Cypermethrin30OthersTons per monthRoad,Rail,Otherssea
(51.)Propargite30OthersTons per monthRoad,Rail,Otherssea
(52.)Indoxacarb20OthersTons per monthRoad,Rail,Otherssea
(53.)Dinotefuran20OthersTons per monthRoad,Rail,Otherssea
(54.)Chlorantraniliprole20OthersTons per monthRoad,Rail,Otherssea
(55.)Sulfoxaflor20OthersTons per monthRoad,Rail,Otherssea
(56.)Meta-phenoxy benzaldehyde(MPB)30OthersTons per monthRoad,Rail,Otherssea
(57.)Flucetosulfuron20OthersTons per monthRoad,Rail,Otherssea
(58.)Imidacloprid30OthersTons per monthRoad,Rail,Otherssea
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 30.6
(b) Funds Allocated for Environment Management (Capital) (in Crores) 4
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 3.06
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.591
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? Yes
b)Critically polluted areas as notified by the Central Pollution Control Board(CPCB) from time to time Yes
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? Yes
8.(a) If any Industrial Estate/Complex / Export processing Zones /Special Economic Zones/Biotech Parks / Leather Complex with homogeneous type of industries such as Items 4(d), 4(f), 5(e), 5(f), or those Industrial estates with pre –defined set of activities (not necessarily homogeneous, obtains prior environmental clearance, individual industries including proposed industrial housing within such estates /complexes will not be required to take prior environmental clearance, so long as the Terms and Conditions for the industrial estate/complex are complied with (Such estates/complexes must have a clearly identified management with the legal responsibility of ensuring adherence to the Terms and Conditions of prior environmental clearance, who may be held responsible for violation of the same throughout the life of the complex/estate
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 188
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 188
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Raw materials 18842768.62OthersTons per AnnumIndia and other countriesRoad,Rail,Otherssea and air167 OthersOpen marketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Mar 2018 To 31 May 2018
(b)Season Summer
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)SO2Micro Gram per Meter Cube15.86.615.580
(2.)PM2.5Micro Gram per Meter Cube36.920.336.760
(3.)PM10Micro Gram per Meter Cube70.237.270.2100
(4.)NOxMicro Gram per Meter Cube34.018.534.080
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA7.876.536.58.5
(2.)TSSmg/l11100100
(3.)Fluoridemg/l0.580.2711.5
(4.)Heavy MetalsCadiummg/l0.920.01515
(5.)TDSmg/l14332835002000
(6.)Chloridesmg/l410.749.42501000
(7.)Total Hardnessmg/l721125200600
    14.3.     No. of Surface Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA7.926.62A
(2.)CODmg/l328E
(3.)BODmg/l161E
(4.)DOmg/l6.25.1B
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))54.142.565
(2.)Leq(Day)A-weighted decibels(dB(A))59.450.575
    14.5.     No. of Soil Sample Monitored locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)K(Potassium)Milligram per Kilogram7850
(2.)N(Nitrogen)Milligram per Kilogram12082
(3.)P(Phosphorus)Milligram per Kilogram4935
(4.)pHOthersNA8.257.4
(5.)Electric ConductivityOthersµS/cm23099.5
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 2 To 5
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 2 To 5
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersSIPCOT151.010.02Copy of Permission LetterPipelineOthersSIPCOT pipelineDI/SIC-Cud/ Crimsun/201806 Aug 2018490
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Sewage1818ZLDGreen Belt Renewal Plant,Othersothers180
(2.)Effluent8888ZLDReuse within the Plant & Recycling,Othersothers7216
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 106
(b)Total Discharged Water (Kilolitre per Day) 16
(c)Total Reused Water (Kilolitre per Day) 90
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Organic wasteMunicipal Solid Waste26.1Tons0.05RoadOthersOrganic waste convertor
(2.)Process residueHazardous Waste (as per Hazardous and Other Waste Management rules 2016)192Tons1.5RoadTreatment, Storage and Disposal Facility(TSDF)
(3.)Used oilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)0.5Kilolitre0.05RoadOthersBurnt in Furnace oil boiler
(4.)ETP sludgeHazardous Waste (as per Hazardous and Other Waste Management rules 2016)135Tons1.5RoadTreatment, Storage and Disposal Facility(TSDF)
(5.)Inorganic wasteMunicipal Solid Waste11.4Tons0.35RoadAuthorized Recyclers
(6.)MS drumsHazardous Waste (as per Hazardous and Other Waste Management rules 2016)30000Kilolitre1RoadAuthorized Recyclers
(7.)MEE saltsHazardous Waste (as per Hazardous and Other Waste Management rules 2016)2693Tons260RoadOthersDisposed through TNWML (TSDF)
(8.)Organic residue and CatalystHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1172Tons0.35RoadAuthorized Recyclers
(9.)HDPE used linersHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1Tons0.5RoadAuthorized Recyclers
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM2.5Microgram per Meter Cube36.902.46539.3660
(2.)NOxMicrogram per Meter Cube3403.3137737.3180
(3.)PM10Microgram per Meter Cube70.202.4652572.66100
(4.)SO2Microgram per Meter Cube15.802.4655318.2680
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)DG 500 kVAHSD90.25PM100.0000827
(2.)DG 500 kVAHSD90.25SO20.00000064
(3.)Coal fired 1 x10 TPHCoal320.85NOx0.8333
(4.)Furnace oil Boiler 3 TPHFurnace Oil250.60PM100.2567
(5.)DG 500 kVAHSD90.25NOx0.00125
(6.)DG 500 kVAHSD90.25PM100.0000827
(7.)DG 500 kVAHSD90.25SO20.00000064
(8.)Furnace oil Boiler 3 TPHFurnace Oil250.60NOx0.2567
(9.)Coal fired 1 x 10 TPHCoal320.85PM100.0041
(10.)Coal fired 1 x10 TPHCoal320.85SO21.8056
(11.)Furnace oil Boiler 3 TPHFurnace oil250.60SO20.2519
(12.)DG 500 kVAHSD90.25NOx0.00125
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 2000
(b)Source TANGEDCO
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 2 x 500 kVA
(e)Stack Height (in m) 9
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 0
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 1.8051
    Total Land (ha.) 1.8051
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 13482
(b)Waste/Barren Land (ha.) 933
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 1163
(e)Settlements (ha.) 2357
(f)Industrial (ha.) 287
(g)Forest (ha.) 77
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 12247
(j)Others (ha.) : Inland and coastal wetland 1441
    Total (ha.) 31987
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Green belt0.606333.59% of total area
(2.)Main Plant1.1988Including over all
Total (ha.) 1.8051
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaCuddalore Town6.94CEPI score 70.12
(2.)ESZsNil0Nil
(3.)CorridorsNil0Nil
(4.)Wildlife CorridorsNil0Nil
(5.)NPANil0Nil
(6.)WLSNil0Nil
(7.)ESAsNil0Nil
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestNil0Nil
(2.)Archaeological SitesNil0Nil
(3.)Defence InstallationsNil0Nil
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired Not applicable
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Yet To Start
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Uppanar river
(ii)Direction of Water Bodies in Buffer Area East
(iii)Distance of Water Bodies in Buffer Area 0.45
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 250
(c)Temporary Employment- During Construction 100
(d)Temporary Employment- During Operation 0
(e)No. of working days 300
(f)Total Manpower 350
32.
Green Belt in Ha:
(a)Total Area of Green Belt 0.606274
(b)Percentage of Total Project Area 33.59
(c)No. of Plants to be Planted 990
(d)Funds Allocated for Plantation 500000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialEmployment to local
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1619/RA 0083
(ii)Name of the EIA Consultant HUBERT ENVIRO CARE SYSTEM PVT LTD
(iii)Address Hubert Enviro Care Systems (P) Ltd. A-21, (Behind Lions Club School) III Phase, Thiru Vi Ka Industrial Estate. Guindy, Chennai - 600 032.
(iv)Mobile No. 9884390811
(v)Landline No. 0444363555
(vi)Email Id moses@hecs.in
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 13 Oct 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAWhether any proposal submitted online for amendment in the ToR dated 27/7/2018, and its present status. For the present, the EC proposal is not compliant with the said ToR. 28 Oct 2018
2.NAThe correction have been made as per the instruction received 01 Nov 2018
3.NAEIA consultant engaged by you is not accredited for preparing EIA/EMP reports, either for the projects covered category B of item 5(f) or category A/B of item 5(b). The proposal is, therefore, not admissible. 07 Nov 2018
4.NAThe correction have been made as per the instruction received 14 Nov 2018
5.NAWe reiterate our earlier observations vide query dated 7/11/2018 in respect of accreditation of consultant. Also, please confirm whether all the products covered under Herbicides, Insecticides are technical grade pesticides. 25 Nov 2018
6.NAThe correction have been made as per the instruction received 27 Nov 2018
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantS. Ramesh Prabhakaran
DesignationManaging Director
Name of Company (Applicant Name should not be given here)CRIMSUN ORGANICS PRIVATE LIMITED
AddressPlot No. C-10 & C-11, SIPCOT Industrial complex, kudikadu village, Cuddalore Taluk , Cuddalore District Tamilnadu
Print