Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) M/s. S. M. Industries
(b)Name of the Company / Organisation S. M. INDUSTRIES
(c)Registered Address Survey No. 192/4, Village Sokhada, Taluka Khambhat, Dist. Anand, Gujarat,,Anand,Gujarat-388620
(d)Legal Status of the Company Others
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Rakesh Shah
(b)Designation (Owner/ Partner/ CEO) Partner
(c)Address Survey No. 192/4, Village Sokhada, Taluka Khambhat, Dist. Anand, Gujarat,,Khambhat,Anand,Gujarat-388620
(d)Pin code 388620
(e)E-mail smindustries98@yahoo.co.in
(f)STD Code. 2698(f)Telephone No. 224521
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
Minor Activity5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
(b)Category A
(c)Proposal Number IA/GJ/IND2/82964/2017
(d)Master Proposal Number(Single Window) SW/82960/2018
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. SURVEY NO. 192/4, VILLAGE : SOKHADA, TALUKA : KHAM
(b)Pincode 388620
(c)Bounded Latitudes (North)
From
Degree 22.348703
Minutes
Second
From
Degree 22.348839
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 72.595258
Minutes
Second
From
Degree 72.595833
Minutes
Second
(e)Survey of India Topo Sheet No. --
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 10
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 3
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Gujarat
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number J-11011/371/2017-IA-II (I)
(c)Date of Issue of TOR 24 Aug 2017
(f)Previous TOR Letter Copy of Previous TOR letter
(b)Date of Apply of EC 26 Mar 2019
(c)Date of Issue of EC 17 Oct 2019
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :30 Jun 2018
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :07 Aug 2018
Distance of Public Hearing Venue from the Proposed Project :10
Shri Dahyabhai Hargovinddas Rao Sanskrutik Bhavan, Khambhat
State :Gujarat
District :Anand
Tehsil :Khambhat
Village :Sokhada
136Provision of employment to local people. Also the total green belt area that would be provided by company.OthersAdditional District Magistrate & Resident Additional Collector
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Bhopal
(iii)Letter No. Not Applicable
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Aug 24 2017 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)1001585100OthersMT/MonthRoad,Rail
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Spray Dryer1011200 lit/hr
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 21 Mar 2016
(iv)Valid Upto 04 Feb 2021
(v)File No. GPCB/CCA-AND-94(2)/ID:17608/
(vi)Application No. 99181
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 4.0
(b) Funds Allocated for Environment Management (Capital) (in Crores) 1
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.15
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 5
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 175
(b)Existing quantity of raw material/fuel 25
(c)Total quantity of raw material/fuel 200
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)diesel30OthersLiter/hrLocal SupplierRoad15 Open MarketCopy of Linkage
(2.)HCl100Tons per AnnumLocal SupplierRoad15 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 31 Oct 2017 To 31 Dec 2017
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 10
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM2.5Micro Gram per Meter Cube47.2841.6646.4960
(2.)SO2Micro Gram per Meter Cube17.0911.9416.5080
(3.)NOxMicro Gram per Meter Cube12.928.5712.1280
(4.)PM10Micro Gram per Meter Cube78.8369.3577.32100
(5.)OthersO3Micro Gram per Meter Cube14.3310.3714.21100
    14.2.     No. of Ground Water monitoring locations : 10
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)Total HardnessOthersAs CaCO3976.9858.06300600
(2.)pHNA9.078.106.58.5
(3.)TDSmg/l19204225002000
(4.)Chloridesmg/l603.50159.32501000
(5.)Heavy MetalsZincmg/l0.150.022515
(6.)TSSmg/l52250100
(7.)Fluoridemg/l0.050.0511.5
    14.3.     No. of Surface Water monitoring locations : 4
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA8.517.89C
(2.)DOmg/l6.330.41C
(3.)BODmg/l11C
(4.)OthersTurbidityOthersNTU1.60.41C
(5.)CODmg/l13.8911.24C
    14.4.     No. of Ambient Noise monitoring locations : 10
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))754775
(2.)Leq(Night)A-weighted decibels(dB(A))693970
    14.5.     No. of Soil Sample Monitored locations : 10
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)N(Nitrogen)Milligram per Kilogram26.80.2
(2.)P(Phosphorus)Milligram per Kilogram4.481.26
(3.)K(Potassium)Milligram per Kilogram25.29.01
(4.)Electric ConductivityMillisiemens per Centimetre4741
(5.)pHOthersNA9.257.78
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 65 To 90
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 65 To 90
(c)Whether Ground Water Intersection will be there ? Yes
(d)Upload Copy of Central Ground Water Authority Letter Copy of Central Ground Water Authority Letter
(e)Letter No. 21-4/2782/GJ/IND/2017
(f)Date of Issue 21 Apr 2017
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater311.5 Not Appliacble PipelineIntake Well21-4/2782/GJ/IND/201716 Jul 201730
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Industrial13.313.3ETP/ Spray Dryer/ MEEReuse within the Plant & Recycling13.3
(2.)Domestic33Septic Tank/ Soak PitOthersDisposed through septic tank and soak pit30
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 16.3
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 16.3
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Used OilIndustrial Waste0.24Kilolitre10RoadAuthorized Recyclers
(2.)Discarded Drums/ ContainersIndustrial Waste72Tons15RoadAuthorized Recyclers
(3.)MEE saltHazardous Waste (as per Hazardous and Other Waste Management rules 2016)120Tons10RoadTreatment, Storage and Disposal Facility(TSDF)
(4.)Spray Dryer SludgeHazardous Waste (as per Hazardous and Other Waste Management rules 2016)240Tons15RoadOthersSold to Tinting dyes to end user
(5.)Fly Ash from BoilerFly Ash120Tons15RoadOthersCo-processing/ TSDF/ Landfilling
(6.)Spent SolventIndustrial Waste12Tons15RoadPipelineOthersSell to end user
(7.)ETP SludgeHazardous Waste (as per Hazardous and Other Waste Management rules 2016)14.4Tons10RoadTreatment, Storage and Disposal Facility(TSDF)
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)NOxMicrogram per Meter Cube9.661.50.1229.7880
(2.)SO2Microgram per Meter Cube17.0900017.0980
(3.)PM10Microgram per Meter Cube76.941.50.14377.083100
(4.)PM2.5Microgram per Meter Cube44.251.50.33944.58960
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)BoilerAgro Waste120.6SO2262
(2.)Spray DryerPNG150.5SO2262
(3.)Spray DryerPNG150.5NOx94
(4.)BoilerAgro Waste120.6NOx94
(5.)Spray DryerPNG150.5PM10150
(6.)BoilerAgro Waste120.6PM10150
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 80
(b)Source MGVCL
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 1
(e)Stack Height (in m) 10
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 4.452
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 4.452
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 93.68
(b)Waste/Barren Land (ha.) 7.75
(c)Grazing/ Community Land (ha.) 10.38
(d)Surface Water Bodies (ha.) 1.58
(e)Settlements (ha.) 10
(f)Industrial (ha.) 0.75
(g)Forest (ha.) 99
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 14.53
(j)Others (ha.) : Creek, Mud Float and other area 76.4
    Total (ha.) 314.07
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Main Plant1775
(2.)Green belt2177
(3.)Tailing Pond500ETP Area
Total (ha.) 4452
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)NPA--0--
(2.)ESAs--0--
(3.)Wildlife Corridors--0--
(4.)ESZs--0--
(5.)Critically Polluted Area--0--
(6.)WLS--0--
(7.)Corridors--0--
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Defence Installations--0--
(2.)Forest--0--
(3.)Archaeological Sites--0--
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 4.452
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired Land already acquired
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 10
(b)Permanent Employment-During Operation 5
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 5
(e)No. of working days 330
(f)Total Manpower 20
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt260002600
(2.)Percentage of Total Project Area58.4058.4
(3.)No. of Plants1900190
(4.)Funds Allocated5.905.9
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialProvision of employment to local people
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. Stay Order Against QCI NABET
(ii)Name of the EIA Consultant M/s. Aqua Air Environmental Engineers Pvt. Ltd.
(iii)Address 403, Centre Point, Nr. Kadiwala School, Ring Road, Surat
(iv)Mobile No. 9904433995
(v)Landline No. 0261246085
(vi)Email Id aqua_eia@yahoo.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 11 Apr 2016
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAPlease inform/clarify the following:- - Manufacturing of Azo Dyes through different processes namely, crude, blending and grinding, is covered under item 5(f) 'Synthetic Organic chemicals' and thus requires prior EC. - Status of EC for the present production of 15 TPM. - Clearance for ground water withdrawal for the proposed expansion from 15 to 100 TPM. 28 Oct 2018
2.NAThe correction have been made as per the instruction received 14 Nov 2018
3.NA- Please confirm requirement of EC for different category of products (other than Azo dyes) namely, Pigments, Solvent Dyes, Acid Dyes, Direct Dyes and Reaction Dyes. - Product details/list needs to be revised to mention only those products covered under the domain of the EIA Notification, 2006. 24 Nov 2018
4.NAThe correction have been made as per the instruction received 08 Mar 2019
5.NAAs observed earlier also, no requirement of EC for the dyes production @10 TPM by blending & grinding process, needs to be confirmed with detailed justification and the supporting documents. Also inform about permission from the concerned regulatory authority for ground water withdrawal of 31 cum/day. 24 Mar 2019
6.NAThe correction have been made as per the instruction received 26 Mar 2019
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterADDITIONAL INFORMATION FOR ENVIRONMENT CLEARANCE FOR PROPOSED EXPANSION OF DYES & NEW PIGMENTS IN EXISTING DYES UNIT AT PLOT NO. 192/4, VILLAGE: SOKHADA, TALUKA: KHAMBHAT, DIST: ANAND – 388 620 GUJARAT, INDIA, GUJARAT OF M/s. S. M. INDUSTRIES 08 Jun 2019
2.NA

Deferred

17 May 2019
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantRakesh Shah
DesignationPartner
Name of Company (Applicant Name should not be given here)S. M. INDUSTRIES
AddressSurvey No. 192/4, Village Sokhada, Taluka Khambhat, Dist. Anand, Gujarat
Print