Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Hemani Industries Ltd. (Unit-VI)
(b)Name of the Company / Organisation Hemani Intermediates Pvt. Ltd.
(c)Registered Address Plot No. 3208, GIDC Estate Ankleshwar, Dist: Bharcuh, GUJARAT,Plot No. 3208, GIDC Estate Ankleshwar, Dist: Bharcuh, GUJARAT,Bharuch,Madhya Pradesh-393002
(d)Legal Status of the Company Others
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant D N Rai
(b)Designation (Owner/ Partner/ CEO) General Manager
(c)Address Plot No. 3208, GIDC Estate Ankleshwar, Dist: Bharcuh, GUJARAT,Plot No. 3208, GIDC Estate Ankleshwar, Dist: Bharcuh, GUJARAT,Vagra,Bharuch,Madhya Pradesh-393002
(d)Pin code 393002
(e)E-mail hr3.1@hemanigroup.com
(f)STD Code. 0(f)Telephone No. 626 195
(g)Fax No. 650 627
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(b) Pesticides industry and pesticide specific intermediates (excluding formulations)
5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
Minor Activity
(b)Category A
(c)Proposal Number IA/GJ/IND2/82838/2018
(d)Master Proposal Number(Single Window) SW/82834/2018
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Plot No. T-35,36,37,45,46,47
(b)Pincode 392130
(c)Bounded Latitudes (North)
From
Degree 21.775458
Minutes
Second
From
Degree 21.778956
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 72.833017
Minutes
Second
From
Degree 72.836867
Minutes
Second
(e)Survey of India Topo Sheet No. From Environmental Information Centre
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 9
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 12
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Gujarat
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number J-11011/231/2018-IA.II (I)
(b)Date of Apply of TOR 13 Jul 2018
(c)Date of Issue of TOR / Standard ToR 16 Aug 2018
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason Located inside of GIDC-Saykha
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Specialty Chemical Manufacturing PlantSpecialty Chemical5 (f)
(2.)Pesticide Manufacturing PlantPesticide5 (b)
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Specialty Chemicals16500OthersTons per MonthRoad
(2.)Pesticide Products31200OthersTons per MonthRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 120
(b) Funds Allocated for Environment Management (Capital) (in Crores) 25
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 1.8
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 30
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 100000
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 100000
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)HSD Fuel48Kilo Litre per DayLocal MarketRoad25 Open MarketCopy of Linkage
(2.)ammonia10000Tons per AnnumLocal MarketRoad20 Open MarketCopy of Linkage
(3.)Coal144000Tons per AnnumLocal MarketRoad25 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Oct 2017 To 31 Dec 2017
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 7
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)SO2Micro Gram per Meter Cube17.6412.571780
(2.)PM2.5Micro Gram per Meter Cube45.7842.764560
(3.)NOxMicro Gram per Meter Cube19.4813.631980
(4.)PM10Micro Gram per Meter Cube81.0672.481100
    14.2.     No. of Ground Water monitoring locations : 7
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA8.337.446.58.5
(2.)TSSmg/l14350100
(3.)TDSmg/l6382155002000
(4.)Total Hardnessmg/l149.6101.6300600
(5.)Fluoridemg/l0011.5
(6.)Chloridesmg/l78.5759.122501000
(7.)Heavy MetalsFemg/l0.5900.31
    14.3.     No. of Surface Water monitoring locations : 1
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA8.28.2C
(2.)BODmg/l11C
(3.)CODmg/l8.48.4C
(4.)DOmg/l4.84.8C
    14.4.     No. of Ambient Noise monitoring locations : 7
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))44.741.245
(2.)Leq(Day)A-weighted decibels(dB(A))53.147.255
    14.5.     No. of Soil Sample Monitored locations : 7
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pHOthersNA7.897.21
(2.)K(Potassium)Milligram per Kilogram862248
(3.)Electric ConductivityMillisiemens per Centimetre58.253.9
(4.)N(Nitrogen)Milligram per Kilogram291.4196.8
(5.)P(Phosphorus)Milligram per Kilogram92.5364.57
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 50 To 75
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 100 To 150
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersGIDC Water Supply813620Copy of Permission LetterPipelineIntake WellGIDC/DM(CG)/ANK/0701 Jan 20188136
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Industrial81208120ETP (Primary, Secondary, Tertiary), RO & MEEReuse within the Plant & Recycling,OthersLoss7695425
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 8120
(b)Total Discharged Water (Kilolitre per Day) 425
(c)Total Reused Water (Kilolitre per Day) 7695
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Organic WasteIndustrial Waste2160Tons30RoadCo-Processing
(2.)ETP SludgeIndustrial Waste4800Tons25RoadTreatment, Storage and Disposal Facility(TSDF)
(3.)Process Sludge from CaCl2Industrial Waste7200Tons40RoadOtherssell for agricultural use
(4.)Empty Drums/ContainerHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1200Tons25RoadAuthorized Recyclers
(5.)Empty BagsIndustrial Waste600Tons25RoadAuthorized Recyclers
(6.)Distillation ResidueHazardous Waste (as per Hazardous and Other Waste Management rules 2016)3000Tons30RoadCo-Processing
(7.)MEE SaltIndustrial Waste145800Tons30RoadTreatment, Storage and Disposal Facility(TSDF)
(8.)Spent SolventIndustrial Waste60000Tons25RoadOtherssell to end users
(9.)Spent AcidIndustrial Waste240000Tons25RoadOtherssell to end users
(10.)Spent CarbonIndustrial Waste600Tons30RoadOthersIncineration Site
(11.)Iron SludgeIndustrial Waste38400Tons30RoadTreatment, Storage and Disposal Facility(TSDF)
(12.)Used OilIndustrial Waste3.6Kilolitre25RoadAuthorized Recyclers
(13.)Fly AshFly Ash12000Tons30RoadOtherssell to brick manufactures
(14.)Spent CatalystIndustrial Waste600Tons30RoadOthersRegenerator
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM2.5Microgram per Meter Cube43.552.130.0051743.5551760
(2.)SO2Microgram per Meter Cube14.252.130.0045114.2545180
(3.)Others(Specify)HClMicrogram per Meter Cube02.130.00170.0017200
(4.)NOxMicrogram per Meter Cube14.252.130.0017314.2517380
(5.)PM10Microgram per Meter Cube76.052.130.0051776.05517100
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)TFH (I,II,III,IV,V)Coal501PM10100
(2.)DG SetHSD110.2PM10100
(3.)Boiler I, II, IIICoal501PM10100
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 15000
(b)Source DGVCL
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 5000 KVA (2 NOS.)
(e)Stack Height (in m) 11
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 12.1
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 12.1
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 9706.81
(b)Waste/Barren Land (ha.) 1171.69
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 102.13
(e)Settlements (ha.) 375.56
(f)Industrial (ha.) 9.31
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Fallow, Open, River & Canal, Orchards, River bad, 20031.81
    Total (ha.) 31397.309999999998
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Green belt40000
(2.)Main Plant50000
(3.)OthersETP , Utility & Storage Area31000hazardous waste, Product & Raw Material
Total (ha.) 121000
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)ESAs--0--
(2.)ESZs--0--
(3.)Corridors--0--
(4.)Critically Polluted Area--0--
(5.)NPA--0--
(6.)Wildlife Corridors--0--
(7.)WLS--0--
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Forest--0--
(2.)Archaeological Sites--0--
(3.)Defence Installations--0--
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 12.1
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired Company has already acquired land for the proposed
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 75
(b)Permanent Employment-During Operation 150
(c)Temporary Employment- During Construction 75
(d)Temporary Employment- During Operation 200
(e)No. of working days 345
(f)Total Manpower 500
32.
Green Belt in Ha:
(a)Total Area of Green Belt 4
(b)Percentage of Total Project Area 33.06
(c)No. of Plants to be Planted 800
(d)Funds Allocated for Plantation 1200000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialLocal Employment, CSR & CER Activity
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. Stay Oder against NABET/QCI
(ii)Name of the EIA Consultant Aqua Air Environmental Engineers Pvt. Ltd.
(iii)Address 403, Center Point, Nr. Kadiwala School, Ring Road, Surat– 395002, Gujarat, India.
(iv)Mobile No. 7405328365
(v)Landline No. 0261277380
(vi)Email Id aqua_eia@yahoo.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 07 Apr 2016
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NA- Please provide details of project configuration and the products (Pesticides and Specialty Chemicals) against items 8.1 & 8.2 of the Form-2. - Why the plant should not conform to ZLD like other pesticides manufacturing units. 28 Oct 2018
2.NAThe correction have been made as per the instruction received 23 Nov 2018
3.NA- No reply has been submitted to our observations dated 28/10/2018. - Different products (27 categories) need to be categorized into items 5(b) & 5(f) of the schedule to the EIA Notification, 2006. - Products not covered under items 5(b) & 5(f) and thus not requiring EC, to be mentioned separately and taken out the proposal. 05 Dec 2018
4.NAThe correction have been made as per the instruction received 25 Dec 2018
5.NAAs informed earlier also, the products not covered under item 5(b) & 5(f) of the schedule to the EIA Notification, 2006, should be taken out of the proposal. Entries in column 8.2 of Form-2 need to be corrected accordingly. 31 Dec 2018
6.NAThe correction have been made as per the instruction received 01 Jan 2019
7.NAPlease see our observations dated 31/12/2018 for the needful to take the proposal forward. 11 Jan 2019
8.NAThe correction have been made as per the instruction received 15 Feb 2019
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantD N Rai
DesignationGeneral Manager
Name of Company (Applicant Name should not be given here)Hemani Intermediates Pvt. Ltd.
AddressPlot No. 3208, GIDC Estate Ankleshwar, Dist: Bharcuh, GUJARAT