Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) “M/s Indian Potash Limited (Distillery Unit) has proposed the establishment of new Molasses based Distillery of 45 KLD along with co-generation power: 1.4 MW at P.O. Rohana Mill, Block Charthawal, Teh
(b)Name of the Company / Organisation INDIA POTASH LIMITED DISTILLERY UNIT
(c)Registered Address Rohana, Block Charthawal, Muzaffarnagar, Uttar Pradesh,,Muzaffarnagar,Uttar Pradesh-251202
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Vishal Sonak
(b)Designation (Owner/ Partner/ CEO) GM
(c)Address Rohana, Block Charthawal, Muzaffarnagar, Uttar Pradesh,,Muzaffarnagar,Muzaffarnagar,Uttar Pradesh-251001
(d)Pin code 251001
(e)E-mail indianpotash123@gmail.com
(f)STD Code. 2459(f)Telephone No. 164852
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(g) Distilleries
Minor Activity
(b)Category A
(c)Proposal Number IA/UP/IND2/82774/2017
(d)Master Proposal Number(Single Window) SW/82767/2018
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. 634,635/1 TO 635/10,640/1,639,641,642
(b)Pincode 251202
(c)Bounded Latitudes (North)
From
Degree 29.34.03
Minutes
Second
From
Degree 29.34.08
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 77.41.14
Minutes
Second
From
Degree 77.41.22
Minutes
Second
(e)Survey of India Topo Sheet No. 53G10
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 250
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 25
(j)Seismic Zone 4
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Uttar Pradesh
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number J-11011/310/2016 IA II I
(b)Date of Apply of TOR 10 Apr 2017
(c)Date of Issue of TOR / Standard ToR 15 Jun 2017
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :15 Aug 2018
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :25 Sep 2018
Distance of Public Hearing Venue from the Proposed Project :0.1
Inside proposed project site
State :Uttar Pradesh
District :Muzaffarnagar
Tehsil :Muzaffarnagar
Village :Rohana
182Concerns were raised with regards to: a. Employment opportunities for local population b. Odour problems c. Disposal of residual spent wash after use as fuel. d. How will water be abstracted fromOthersADDITIONAL DISTRICT MAGISTRATE
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)New molasses based distillery (AA/ENA/RS)45 kld
(2.)Power1.4 MW
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)ETHANOL45Kilo Litre per DayRoad
(2.)POWER1.4Mega Watt(MW)OthersVIA TRANSMISSION LINES
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 15 Oct 2018
(iv)Valid Upto 31 Dec 2020
(v)File No. UNIT WILL TAKE NOC AFTER GRANT OF EC
(vi)Application No. -
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 82
(b) Funds Allocated for Environment Management (Capital) (in Crores) 25
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 5
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.8
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 202
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 202
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Bagasse as fuel for co generation power plant30600Tons per Annumfrom own sugar unitRoad0.3 OthersUNIT WILL SOURCE BAGASSE FROM OWN SUGAR MILLCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Dec 2016 To 28 Feb 2017
(b)Season Winter
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube82.845.282100
(2.)SO2Micro Gram per Meter Cube12.86.812.480
(3.)NOxMicro Gram per Meter Cube20.69.220.280
(4.)PM2.5Micro Gram per Meter Cube46.82646.160
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHOthersph7.67.18.58.5
(2.)Total Hardnessmg/l316248200600
(3.)Chloridesmg/l64.0338.022501000
(4.)Fluoridemg/l0.520.2811.5
(5.)TSSmg/l....
(6.)TDSmg/l537.8434.75002000
(7.)Heavy Metalsironmg/l0.190.130.3.
    14.3.     No. of Surface Water monitoring locations : 4
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)BODmg/l22.412.8C
(2.)DOmg/l5.14.8C
(3.)pHOthersPH7.87.3C
(4.)CODmg/l8862.4C
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))60.551.265
(2.)Leq(Night)A-weighted decibels(dB(A))5045.955
    14.5.     No. of Soil Sample Monitored locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pHOthersPH7.467.16
(2.)P(Phosphorus)Kilogram per hectare6739
(3.)K(Potassium)Kilogram per hectare28294
(4.)Electric ConductivityMillisiemens per Centimetre..
(5.)N(Nitrogen)Kilogram per hectare289156
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 9.1 To 9.33
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 8.5 To 8.7
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Surface4501.8 Not Appliacble PipelineOthersPIPELINE126 Jun 2018450
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)CONDENSATES532800CPUOthersWITHIN PROCESS5320
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 532
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 532
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)FERMENTOR SLUDGEOthersFROM PROCESS600Tons0.2RoadOthersUSED AS MANURE
(2.)ASHOthersASH FROM BOILER4500Tons0.2RoadOthersUSED AS MANURE
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)SO2Microgram per Meter Cube15.60.5403.1418.7480
(2.)PM10Microgram per Meter Cube82.80.6780.1983.71100
(3.)PM2.5Microgram per Meter Cube.....
(4.)NOxMicrogram per Meter Cube20.6.5100.7521.2580
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)18 TPH SLOP FIRED BOILERBAGASSE AND SLOP552.5PM10150
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 1000
(b)Source UNIT WILL PRODUCE POWER
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) .
(e)Stack Height (in m) .
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 3.28
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 3.28
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 289.12
(b)Waste/Barren Land (ha.) 1.80
(c)Grazing/ Community Land (ha.) .
(d)Surface Water Bodies (ha.) 2.554
(e)Settlements (ha.) 4.73
(f)Industrial (ha.) .
(g)Forest (ha.) .
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) .
(j)Others (ha.) : URBAN 4.73
    Total (ha.) NaN
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Green belt1.1845
Total (ha.) 1.1845
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNO ANY CPA WITHIN 15 KMS RADIUS OF PROPOSED SITE0NO CPA OBSERVED IN STUDY AREA
(2.)NPANO ANY0NO NPA OBSERVED IN STUDY AREA
(3.)ESZsNO ANY0NO ESZ OBSERVED IN STUDY AREA
(4.)Wildlife CorridorsNO ANY0NO Corridor OBSERVED IN STUDY AREA
(5.)CorridorsNO ANY0NO Corridor OBSERVED IN STUDY AREA
(6.)WLSNO ANY0NO WLS OBSERVED IN STUDY AREA
(7.)ESAsNO ANY0NO ESA OBSERVED IN STUDY AREA
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Defence InstallationsNO ANY0NIL
(2.)ForestNO ANY FOREST OBSERVED IN STUDY AREA0NO FOREST FOUND
(3.)Archaeological SitesNO ANY0NO ANY ARCHAEOLOGICAL SITES AREA FOUND IN STUDY AREA
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 3.28
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired UNIT HAS ALREADY ACQUIRED LAND
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area RIVER KALI 2.5 KMS, ROHANA MINOR CANAL 2.0 KMS
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 20
(b)Permanent Employment-During Operation 30
(c)Temporary Employment- During Construction 20
(d)Temporary Employment- During Operation 10
(e)No. of working days 300
(f)Total Manpower 80
32.
Green Belt in Ha:
(a)Total Area of Green Belt 1.1845
(b)Percentage of Total Project Area 36.11
(c)No. of Plants to be Planted 2000
(d)Funds Allocated for Plantation 15
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)Environmentalunit will work on 4 R Principle:reduction, reuse, recycling and recovery.
(2.)SocialThe proposed project will create opportunities for employment which will help in improving the socio economic status of the region. Social welfare activities will be taken up on large scale.
(3.)Financialproject will • reduce dependence on Imports of foreign oil • improve market opportunity for agriculture crops • contribute to rural economic development
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1619/SA056
(ii)Name of the EIA Consultant Ascenso Enviro Private Limited
(iii)Address Ascenso Enviro Private Limited D-79, Second Floor Sector-6, Noida Uttar Pradesh-201301 (India)
(iv)Mobile No. 9454721732
(v)Landline No. 0112043332
(vi)Email Id anshumaan110@gmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 03 Oct 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAPlease inform/provide/clarify the following:- - Whether the proposed industrial operations are permitted at the project site and/or in conformity with land use of the area. That needs to be confirmed along with supporting documents. - Status of approval/clearance required to meet the fresh water requirement of 450 cum/day from the identified surface water source. - Approval from PESO for project site and the layout plan from safety considerations. 06 Nov 2018
2.NAThe correction have been made as per the instruction received 14 Nov 2018
3.NAPlease inform about the EC details for the attached sugar plant, and the compliance status thereof. 23 Nov 2018
4.NAThe correction have been made as per the instruction received 24 Nov 2018
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantVishal Sonak
DesignationGM
Name of Company (Applicant Name should not be given here)INDIA POTASH LIMITED DISTILLERY UNIT
AddressRohana, Block Charthawal, Muzaffarnagar, Uttar Pradesh