Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Proposed Establishment of Pesticides and it’s intermediates & Synthetic organic chemicals manufacturing unit
(b)Name of the Company / Organisation PRASOL CHEMICALS LIMITED
(c)Registered Address Prasol House, Plot No. A-17/2/3, TTC Industrial Area, Khairane MIDC, Navi Mumbai,,Mumbai City,Maharashtra-400710
(d)Legal Status of the Company Others
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Gaurang N Parikh
(b)Designation (Owner/ Partner/ CEO) ManagingDirector
(c)Address Prasol House, Plot No. A-17/2/3, TTC Industrial area, Khairane MIDC, Navi Mumbai,,Mumbai,Mumbai City,Maharashtra-400710
(d)Pin code 400710
(e)E-mail dnshah@prasolchem.com
(f)STD Code. 22(f)Telephone No. 27782555
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(b) Pesticides industry and pesticide specific intermediates (excluding formulations)
Minor Activity5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
(b)Category A
(c)Proposal Number IA/MH/IND2/62822/2017
(d)Master Proposal Number(Single Window) SW/82266/2018
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Plot no FS30 Add MIDC Mahad Raigad Maharashtra
(b)Pincode 402309
(c)Bounded Latitudes (North)
From
Degree 18.7
Minutes
Second
From
Degree 18.7
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 73.2
Minutes
Second
From
Degree 73.2
Minutes
Second
(e)Survey of India Topo Sheet No. E43H8 E43H12
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 46
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 0.14
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Maharashtra
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)MaharashtraRaigadMahad
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number IA-J-11011/70/2017-IA-II(I)
(b)Date of Apply of TOR 28 Feb 2017
(c)Date of Issue of TOR / Standard ToR 10 Jul 2017
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason Project is within notified MIDC.
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Reactor Columns Storage Tanks BoilersWill be installedNo
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Zinc Dialkyl Dithiophosphate or Alkyl Sodium Dithiophosphate or Sodium Dithiophosphate6000Tons per AnnumRoad
(2.)2-Methyl Adrohol Acetate or Trimethyl Cyclohexyl Acetate or Styrallyl Acetate or Phenethyl Acetate5000Tons per AnnumRoad
(3.)Sodium Sulphite650Tons per AnnumRoad
(4.)Diethyl Thiophosphoric Acid or Diethyl Thiophosphoryl Chloride or Dimethyl Thiophosphoryl Chloride12000Tons per AnnumRoad
(5.)O-Methyl Cyclohexanol or O-Methyl Cyclohexanone or Styrallyl Alcohol or 3,3,5 Trimethyl Cyclohexanol or 3,3,5 Trimethyl Cyclohexanone5000Tons per AnnumRoad
(6.)Sodium Hydrogen Sulphide8500Tons per AnnumRoad
(7.)Hydrochloric Acid19500Tons per AnnumRoad
(8.)Dimethyl Phosphoramidothioate1000Tons per AnnumRoad
(9.)Wettable Sulphur3000Tons per AnnumRoad
(10.)Ammonium Hydroxide150Tons per AnnumRoad
(11.)Dil. Acetic Acid3000Tons per AnnumRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 13 Nov 2018
(iv)Valid Upto 13 Nov 2018
(v)File No. Not applicable. CTO not obtained for proposed proj
(vi)Application No. Not applicable. CTO not obtained for proposed proj
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 50
(b) Funds Allocated for Environment Management (Capital) (in Crores) 3
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 1
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 1.75
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 0
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 0
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Raw material0Tons per AnnumlocalRoad0 LinkageCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 09 Mar 2017 To 26 May 2017
(b)Season Summer
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)SO2Micro Gram per Meter Cube13.810.813.880
(2.)PM2.5Micro Gram per Meter Cube21.213.920.860
(3.)PM10Micro Gram per Meter Cube71.360.470.7100
(4.)OthersCOMili Gram per Meter Cube0.30.10.34
(5.)NOxMicro Gram per Meter Cube16.513.316.380
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA7.97.98.58.5
(2.)TSSmg/l0000
(3.)TDSmg/l50505002000
(4.)Total Hardnessmg/l108108200600
(5.)Heavy MetalsLeadmg/l000.010
(6.)OthersSulphatemg/l14.114.1200400
(7.)Chloridesmg/l33.733.72501000
(8.)Fluoridemg/l0011.5
    14.3.     No. of Surface Water monitoring locations : 10
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA7.757.75C
(2.)BODmg/l2020C
(3.)CODmg/l00C
(4.)OthersTDSmg/l6060C
(5.)DOmg/l4.54.5C
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))57.657.670
(2.)Leq(Day)A-weighted decibels(dB(A))62.662.675
    14.5.     No. of Soil Sample Monitored locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)N(Nitrogen)Kilogram per hectare23.9223.92
(2.)P(Phosphorus)Kilogram per hectare23.923.9
(3.)Electric ConductivityOthersmicromhos per cm236.3236.3
(4.)K(Potassium)Kilogram per hectare127.3127.3
(5.)pHOthersNA6.756.75
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 5 To 7
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 2 To 4
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Othersfrom MIDC5060 Not Appliacble PipelineOthersfresh water from MIDC011 Oct 2018355
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic & Industrial171200ETP RO MEEReuse within the Plant & Recycling171
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 171
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 171
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Iron, Glass, Plastic scrap, glass woolMunicipal Solid Waste6Tons0RoadOthersSale to authorized party
(2.)Used Cotton Hand glovesIndustrial Waste5000Tons0RoadTreatment, Storage and Disposal Facility(TSDF)
(3.)MiscellaneousMunicipal Solid Waste0.75Tons0RoadTreatment, Storage and Disposal Facility(TSDF)
(4.)Distillation ResidueHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1000Tons0RoadOthersCHWTSDF or sale Authorized party
(5.)Residue from ZDDP manufactureHazardous Waste (as per Hazardous and Other Waste Management rules 2016)85Tons0RoadOthersCHWTSDF or sale Authorized party
(6.)Chemical sludge from ETPHazardous Waste (as per Hazardous and Other Waste Management rules 2016)230Tons0RoadTreatment, Storage and Disposal Facility(TSDF)
(7.)Used OilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)17Kilolitre0RoadAuthorized Recyclers
(8.)Spent CatalystHazardous Waste (as per Hazardous and Other Waste Management rules 2016)10Tons0RoadAuthorized Recyclers
(9.)Used Empty Barrels or LinersHazardous Waste (as per Hazardous and Other Waste Management rules 2016)11000Tons0RoadAuthorized Recyclers
(10.)Halogen containing compoundsHazardous Waste (as per Hazardous and Other Waste Management rules 2016)50Tons0RoadTreatment, Storage and Disposal Facility(TSDF)
(11.)SulphidesHazardous Waste (as per Hazardous and Other Waste Management rules 2016)36Tons0RoadTreatment, Storage and Disposal Facility(TSDF)
(12.)Ion exchange resinIndustrial Waste1.5Tons0RoadTreatment, Storage and Disposal Facility(TSDF)
(13.)Sand from Water FiltrationIndustrial Waste10Tons0RoadTreatment, Storage and Disposal Facility(TSDF)
(14.)Coal ashBottom Ash4380Tons0RoadOthersto brick manufacturer or CHWTSDF
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube65.72.50.165.8100
(2.)PM2.5Microgram per Meter Cube00000
(3.)NOxMicrogram per Meter Cube14.82.50.114.980
(4.)Others(Specify)NANA00000
(5.)SO2Microgram per Meter Cube12.12.52.614.780
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)BoilerFurnace Oil or Coal460.7SO22.6
(2.)DG setHSD3.60SO20
(3.)BoilerFurnace oil or coal460.7SO22.6
(4.)DG setHSD3.60SO20
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 2400
(b)Source MSEDCL
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 2 DG set of 400 KVA
(e)Stack Height (in m) 3.6
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 4.5
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 4.5
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 0
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 4.5
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : NA 0
    Total (ha.) 4.5
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Built Up Area1.8815
(2.)Green belt1.49
(3.)OthersParking area0.1450
Total (ha.) 3.5165
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)ESAsSolamkond village1Western ghat notification is in draft stage
(2.)Critically Polluted AreaNot applicable00
(3.)WLSNot applicable00
(4.)NPANot applicable00
(5.)ESZsNot applicable00
(6.)Wildlife CorridorsNot applicable00
(7.)CorridorsNot applicable00
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestPadvi1Nearest forest
(2.)Archaeological Sites--00
(3.)Defence Installations--00
(4.)Others----0--
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Kal river
(ii)Direction of Water Bodies in Buffer Area North
(iii)Distance of Water Bodies in Buffer Area 0.14
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 60
(c)Temporary Employment- During Construction 10
(d)Temporary Employment- During Operation 30
(e)No. of working days 6
(f)Total Manpower 100
32.
Green Belt in Ha:
(a)Total Area of Green Belt 1.49
(b)Percentage of Total Project Area 33.11
(c)No. of Plants to be Planted 150
(d)Funds Allocated for Plantation 25
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialSocial upliftment, Local employment
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. Sr No 5 of NABET accredited consultant
(ii)Name of the EIA Consultant Aditya Environmental Services Pvt Ltd
(iii)Address 107 Hiren Light Industrial Estate Mahim Mumbai
(iv)Mobile No. 9821513367
(v)Landline No. 0224212750
(vi)Email Id rajiv@aespl.co.in
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 11 Oct 2018
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NA- Product details mentioned in para 8.2 of Form-2 is not consistent with those in the ToR dated 10/7/2017. As per the said ToR, total production capacity is 29000 TPA for 7 group of products. - Please categorize the products separately under items 5(b) & 5(f) of the schedule to the EIA Notification, 2006. - Please attach the document in support of the CTO details provided at item 9.1. 16 Oct 2018
2.NAThe correction have been made as per the instruction received 15 Nov 2018
3.NA- As per the details now provided, different products are covered under category 5(b) & 5(f) of the schedule to the EIA Notification, 2006. But the entry at S.No.3(a) of Form-2 still shows 5(b). - Product details at S.No.8.2 of Form-2 should mention only those products covered under the domain of the EIA Notification, 2006. - EIA Consultant is not accredited for preparation of EIA/EMP report for the products under category B of item 5(f). 24 Nov 2018
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantGaurang N Parikh
DesignationManagingDirector
Name of Company (Applicant Name should not be given here)PRASOL CHEMICALS LIMITED
AddressPrasol House, Plot No. A-17/2/3, TTC Industrial Area, Khairane MIDC, Navi Mumbai
Print