Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Exploration and Development of drilling wells in the existing PML area (PML 4 sq.km) of Baola Field at Village Salajada, Tehsil Bavla, District Ahmedabad, Gujarat by M/s Sun Petrochemicals Pvt. Ltd
(b)Name of the Company / Organisation SUN PETROCHEMICALS PRIVATE LIMITED
(c)Registered Address 17/B, Mahal Industrial Estate, Mahakali Caves Road,Andheri East,Mumbai (Suburban),Maharashtra-400093
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Sidharth Saini
(b)Designation (Owner/ Partner/ CEO) Deputy General Manager
(c)Address 17/B, Mahal Industrial Estate, Mahakali Caves Road,Andheri East,,Mumbai (Suburban),Maharashtra-400093
(d)Pin code 400093
(e)E-mail sidharth.saini@sunpetro.com
(f)STD Code. 22(f)Telephone No. 66455925
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity1(b) Offshore and onshore oil and gas exploration, development & production
Minor Activity1(b) Offshore and onshore oil and gas exploration, development & production
(b)Category A
(c)Proposal Number IA/GJ/IND2/81450/2010
(d)Master Proposal Number(Single Window) SW/81444/2018
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. PML Granted For the following Coordinates 22 °48’
(b)Pincode 382220
(c)Bounded Latitudes (North)
From
Degree 224845
Minutes
Second
From
Degree 234845
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 722240
Minutes
Second
From
Degree 722336
Minutes
Second
(e)Survey of India Topo Sheet No. 46B5
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 25
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 42
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Gujarat
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number J-11011/729/2009-IA II(I)
(c)Date of Issue of TOR 17 Jun 2010
(f)Previous TOR Letter Copy of Previous TOR letter
(b)Date of Apply of EC 30 Nov 2018
(c)Date of Issue of EC 20 May 2019
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :10 Jun 2018
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :11 Jul 2018
Distance of Public Hearing Venue from the Proposed Project :3
Grain Merchant Association Hall, Near APMC Gate, Tal: Bavla, Dist: Ahmadabad, State: Gujarat
State :Gujarat
District :Ahmedabad
Tehsil :Bavla
Village :Bavla
43Shri Zhakirhussain Akbar Bhai Vhora surphant, Gram Panchayat Village Rupal raised the point that it is requested to company that children of there village are come forward with education so give thisOthersAdditional District Magistrate, Ahmadabad
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Bhopal
(iii)Letter No. 5-46/2010 (ENV)/474 dated: 12.09.2018
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Aug 12 2018 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Crude Oil (200 bbls/day)30200230OthersBarrels (bbls)Road
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)FacilityWell Head InstallationEarly production systemEarly production systemNone
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 01 Feb 2018
(iv)Valid Upto 03 Dec 2022
(v)File No. AWH-90913
(vi)Application No. 130093
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 19.50
(b) Funds Allocated for Environment Management (Capital) (in Crores) 0.195
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.19
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) .007
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 170
(b)Existing quantity of raw material/fuel 5
(c)Total quantity of raw material/fuel 175
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)diesel170Othersliter per hour per wellNot ApplicableRoad18 Othersopen marketCopy of Linkage
(2.)Water2250Othersliters per wellNot ApplicableRoad20 OthersIn to the scope of Rig ContractorCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Oct 2017 To 31 Dec 2017
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube965295.54100
(2.)SO2Micro Gram per Meter Cube14513.5480
(3.)PM2.5Micro Gram per Meter Cube572456.5460
(4.)NOxMicro Gram per Meter Cube261325.0880
    14.2.     No. of Ground Water monitoring locations : 10
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA7.857.426.58.5
(2.)TDSmg/l4983235002000
(3.)Chloridesmg/l86502501000
(4.)Fluoridemg/l1.04.6911.5
(5.)Heavy MetalsPbmg/l00.01.01
(6.)Total Hardnessmg/l304143200600
(7.)OthersColourOthersHazen43515
(8.)TSSmg/l10800
    14.3.     No. of Surface Water monitoring locations : 5
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)CODmg/l3220E
(2.)OthersTotal ColiformOthersMPN/100ml486366E
(3.)DOmg/l6.65.8E
(4.)pHNA7.847.23E
(5.)BODmg/l127E
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))62.444.675
(2.)Leq(Night)A-weighted decibels(dB(A))48.638.270
    14.5.     No. of Soil Sample Monitored locations : 5
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)Electric ConductivityOthersmicro mhos/cm598180
(2.)N(Nitrogen)OthersMg/100gm22.818.2
(3.)P(Phosphorus)Othersmg/100gm.96.76
(4.)pHOthersNA8.126.88
(5.)K(Potassium)Othersmg/100gm2.3.9
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 2.28 To 22.58
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 1.06 To 16.52
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Surface2516 Not Appliacble modeOthersRoadOthersAuthorized VendorsAfter grant of EC05 Oct 201825
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Produced water2020Evaporation pitDischarge into Surface Water BodyEvaporation pit20
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 20
(b)Total Discharged Water (Kilolitre per Day) 20
(c)Total Reused Water (Kilolitre per Day) 0
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Drill Cuttings wasteHazardous Waste (as per Hazardous and Other Waste Management rules 2016)120Tons112RoadTreatment, Storage and Disposal Facility(TSDF)
(2.)Drilling Mud and other Drilling wasteHazardous Waste (as per Hazardous and Other Waste Management rules 2016)Waste Water150Tons0OthersThrough temporary PipelineOthersEvaporation Pit with HDPE liner
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube9691.2296.122100
(2.)PM2.5Microgram per Meter Cube545.9.554.560
(3.)SO2Microgram per Meter Cube148.01614.01680
(4.)NOxMicrogram per Meter Cube267.61.7627.7680
(5.)Others(Specify)COMicrogram per Meter Cube10006.95510554000
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)DG SetsDiesel30.3048NOxPm50.1
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 1440
(b)Source DG
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) during the drilling operations, Rig Contractor wil
(e)Stack Height (in m) 6
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 0
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 4
    Total Land (ha.) 4
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 400
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 0
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : None 0
    Total (ha.) 400
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)OthersEarly Production system4None
Total (ha.) 4
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNone0None
(2.)NPANone0None
(3.)ESAsNone0None
(4.)ESZsNone0None
(5.)CorridorsNone0None
(6.)Wildlife CorridorsNone0None
(7.)WLSNone0None
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestNone0None
(2.)Archaeological SitesNone0None
(3.)Defence InstallationsNone0None
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Yet To Start
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area Pond in Salajada Village
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 10
(b)Permanent Employment-During Operation 15
(c)Temporary Employment- During Construction 20
(d)Temporary Employment- During Operation 25
(e)No. of working days 300
(f)Total Manpower 70
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)No. of Plants100030004000
(2.)Total Area of Green Belt.501.321.82
(3.)Percentage of Total Project Area92433
(4.)Funds Allocated100003000040000
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)FinancialThe project is fulfillment of the Production Sharing Contract between the Company (Sun Petro) and Directorate General of Hydrocarbon, Govt. of India. It is one of the prospective areas for natural gases by Ministry of Petroleum and Natural Gas, Govt. of India. The viability Of the drilling wells will add onto the natural resources in national level with overall growth in Indian economy.
(2.)EnvironmentalProject Proponent will develop Green Belt to improve the Air Quality
(3.)SocialOne of the greatest impacts of the proposed project is creation of employment opportunities. It is Expected that a good number of people may get direct employment opportunities including skilled, semi-skilled and unskilled workers along with some indirect employment opportunities. This may change occupational, income & expenditure pattern of the people. The benefits of employment to successful job seekers are expected to include, at a household and individual level, in increase in socio-econom
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? Yes
(b)Details of Direction Issued Under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act CC&A issued by the GPCB. AWH-90913
(c)Uploaded Copy of Direction Issued Under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act Copy of Direction Issued
(d)Compliance status of the directions Complied
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1619/RA0063
(ii)Name of the EIA Consultant Mantec Consultants Pvt Ltd Noida
(iii)Address D 36, Sector 6
(iv)Mobile No. 9871095806
(v)Landline No. 0120421500
(vi)Email Id envmantec@gmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 29 Sep 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAPlease inform/clarify the following:- - As per the CCR dated 12/9/2018, no drilling activity was taken up during last 7 years. That reveals about the project for which EC was issued on 19/8/2010, was actually not implemented. In such a case, how the project would qualify under expansion category (Proposed oil production from 30 to 230 bbls). - EC was granted for drilling of two appraisal wells. In case the project not implemented, and no EC obtained for development and production of oil and gas, how CTO has been obtained for crude oil and gas production. In view of the above facts, the proposal involves violation of the EIA Notification, 2006. 12 Oct 2018
2.NAThe correction have been made as per the instruction received 16 Oct 2018
3.NAPlease refer our earlier observations. In response, your reply is silent on present oil production of 30 bbls. Also, no clarification has been provided regarding CTO already obtained for crude oil and gas production without obtaining the EC. - The earlier EC no more valid as of now and the project as per the approved scope of work, not implemented within the validity period, the present proposal would not qualify for expansion. In fact, works still going not against the earlier EC dated 19/8/2010 amounts to violation of the EIA Notification, 2006. 23 Oct 2018
4.NAThe correction have been made as per the instruction received 27 Oct 2018
5.NAAs observed earlier also vide queries dated 12/10/2018 & 23/10/2018, there is no convincing reply on present oil/gas production and the CTO from SPCB without obtaining EC for development/production for the same. Also please clarify how the EC dated 24/12/2010 for Modhera Field is relevant in the instant case, and/or the proposal should be treated under expansion category. The matter may be discussed with the concerned JS in the Ministry for further consideration. 06 Nov 2018
6.NAThe correction have been made as per the instruction received 30 Nov 2018
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantSidharth Saini
DesignationDeputy General Manager
Name of Company (Applicant Name should not be given here)SUN PETROCHEMICALS PRIVATE LIMITED
Address17/B, Mahal Industrial Estate, Mahakali Caves Road
Print