1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | M/s. Sun Particle Board Pvt. Ltd. | (b)Name of the Company / Organisation | SUN PARTICLE BOARD PVT LTD | (c)Registered Address | Survey no.441/P1&2, Haripar-Kerala Road, Village-Bela (Rangpar), Bela(Rangpar)-363642, Tal.Dist- Morbi,,Morbi,Gujarat-363642 | (d)Legal Status of the Company | State Government | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | Deep Patel | (b)Designation (Owner/ Partner/ CEO) | Director | (c)Address | Survey No.441/P1Haripar-Kerala Road,Village-Bela-Rangpar, BEla -rangpar, Dist.-Morbi -363642,,Morbi,Morbi,Gujarat-363642 | (d)Pin code | 363642 | (e)E-mail | sunpartical2014@gmail.com | (f)STD Code. | 0(f)Telephone No. | 00000000 | (g)Fax No. | 000000 | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
| Minor Activity | | (b)Category | B1 | Reason for Applying at Ministry | Specific | (c)Proposal Number | IA/GJ/IND2/80288/2017 | (d)Master Proposal Number(Single Window) | SW/80059/2018 | (e)EAC concerned (for category A Projects only) | Industrial Projects - 2 | (f)Project Type | Expansion |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | Survey. No. : 441/P 1 & 2, Haripar-Kerala Road | (b)Pincode | 363642 | (c)Bounded Latitudes (North) | | From | | Degree | 2536523.00 | Minutes | | Second | | From | | Degree | 2536982.00 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 688811.00 | Minutes | | Second | | From | | Degree | 688958.00 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | F42E16(41I/116)&F42K13(41J/13) | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 36 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 1.30 | (j)Seismic Zone | 4 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Gujarat | |
|
|
Details of State of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
NIL | |
|
6. | Details of Terms of Reference (ToR)/EC: | (a)MoEF&CC / SEIAA File Number | J-11011/284/2017-IA II (I) | (c)Date of Issue of TOR | 25 Sep 2017 | (f)Previous TOR Letter | Copy of Previous TOR letter | (b)Date of Apply of EC | 12 Jan 2019 | (c)Date of Issue of EC | 03 Sep 2019 | (d)Previous EC Letter | Copy of Previous EC letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | No | (b)Whether details of Public Hearing available? | Yes | (c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above | Yes | |
|
7.1. Details of Public Hearing |
---|
|
S. No. | Details of Advertisement | Details of Public Hearing | Venue | Location Details | No. of People Attended | Issues Raised | Designation of Presiding Officer | Other Designation of Presiding Officer |
---|
(1.) | | Copy of Public Hearing : | Copy of Public Hearing | Date : | 26 Jun 2018 | Distance of Public Hearing Venue from the Proposed Project : | 0 |
| M/s. Sun Particle Board Pvt. Ltd., Survey. No. : 441/P 1 & 2, Haripar-Kerala Road | State : | Gujarat | District : | Morbi | Tehsil : | Morbi | Village : | Bela (Rangpar) |
| 96 | Due to the use of hazardous chemicals there is a possibility of depletion of fertility of the nearby land and human and animal health will be affected. Also it may affect the environment and contamina | Others | Resident Additional Collector & Additional District Magistrate , Morbi | |
8. | Details of Project Configuration/Product: | Details Not Applicable | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | (a)Details of certified report on compliance of earlier environmental clearance condition | (i)Certified Compliance By | SPCB | (ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on | | (iii)Letter No. | AWH-79106 | (iv)Status of Compliance | Compiled | (v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) | Copy of Certified Compliance Report | (vi)Date of site visit | Sep 26 2018 12:00AM | (b)Details of Capacity Expansion | |
|
S. No. | Product/Activity (Capacity/Area) | Quantity From | Quantity To | Total | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | Urea Formaldehyde Resin | 0.00 | 6000 | 6000 | Tons per Annum(TPA) | | Road | | (2.) | Melamine Formaldehyde Resin | 0.0 | 3600 | 3600 | Tons per Annum(TPA) | | Road | | (3.) | Paraffin Wax Emulsion | 0.00 | 600 | 600 | Tons per Annum(TPA) | | Road | | (4.) | Plain and Pre-Laminated Particle Boards | 18000 | 10800 | 28800 | Tons per Annum(TPA) | | Road | | |
| (c)Details of Configuration | |
|
S. No. | Plant / Equipment / Facility | Existing Configuration | Proposed Configuration | Final configuration after expansion | Remarks |
---|
(1.) | DUST COLLECTOR | 1 | 0 | 1 | | (2.) | CHIP CRUSHER | 1 | 0 | 1 | | (3.) | FORMER | 1 | 0 | 1 | | (4.) | CUTTER | 1 | 0 | 1 | | (5.) | SANDING M/C (POLISHING AND GRINDING) | 1 | 0 | 1 | | (6.) | DRYER | 1 | 0 | 1 | | (7.) | D G SET | 1 | 1 | 2 | | (8.) | COMPRESSOR | 1 | 0 | 1 | | (9.) | U.F.Reaction Vessel | 0 | 1 | 1 | | (10.) | RING MILL CRUSHER | 1 | 0 | 1 | | (11.) | Thermopack | 1 | 0 | 1 | | (12.) | M.F.Reaction Vessel | 0 | 1 | 1 | | (13.) | PRESS | 1 | 0 | 1 | | |
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | 22 May 2016 | (iv)Valid Upto | 31 Dec 2020 | (v)File No. | AWH-79106 | (vi)Application No. | 105974 | (vii)Copy of Consent to operate valid as on date | Copy of Consent to Operate | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 13.1 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 1.3 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 0.075 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 0.097 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | No | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | Yes | 8.(a) | If any Industrial Estate/Complex / Export processing Zones /Special Economic Zones/Biotech Parks / Leather Complex with homogeneous type of industries such as Items 4(d), 4(f), 5(e), 5(f), or those Industrial estates with pre –defined set of activities (not necessarily homogeneous, obtains prior environmental clearance, individual industries including proposed industrial housing within such estates /complexes will not be required to take prior environmental clearance, so long as the Terms and Conditions for the industrial estate/complex are complied with (Such estates/complexes must have a clearly identified management with the legal responsibility of ensuring adherence to the Terms and Conditions of prior environmental clearance, who may be held responsible for violation of the same throughout the life of the complex/estate | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 29191.68 | (b)Existing quantity of raw material/fuel | 34506 | (c)Total quantity of raw material/fuel | 63697.68 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | Bonding Glue | 5846.4 | Tons per Annum | | Captive | Others | Internal transfer | 0 | Captive | | Copy of Linkage | (2.) | Formaldehyde | 4998 | Tons per Annum | | Indigenous | Road | | 250 | Open Market | | Copy of Linkage | (3.) | Urea | 1626 | Tons per Annum | | Indigenous | Road | | 250 | Open Market | | Copy of Linkage | (4.) | Caustic Soda | 1.44 | Tons per Annum | | Indigenous | Road | | 250 | Open Market | | Copy of Linkage | (5.) | Formic Acid | 1.44 | Tons per Annum | | Indigenous | Road | | 250 | Open Market | | Copy of Linkage | (6.) | Melamine | 1368 | Tons per Annum | | Indigenous | Road | | 250 | Open Market | | Copy of Linkage | (7.) | Mono Ethylene Glycol (MEG)/DEG | 172.8 | Tons per Annum | | Indigenous | Road | | 250 | Open Market | | Copy of Linkage | (8.) | Paraformaldehyde | 25.2 | Tons per Annum | | Indigenous | Road | | 250 | Open Market | | Copy of Linkage | (9.) | Paraffin Wax | 163.2 | Tons per Annum | | Indigenous | Road | | 250 | Open Market | | Copy of Linkage | (10.) | Aqueous Ammonia | 5.4 | Tons per Annum | | Indigenous | Road | | 250 | Open Market | | Copy of Linkage | (11.) | Stearic Acid | 21.6 | Tons per Annum | | Indigenous | Road | | 250 | Open Market | | Copy of Linkage | (12.) | Decorative Paper | 403.2 | Tons per Annum | | Indigenous | Road | | 250 | Open Market | | Copy of Linkage | (13.) | Borax Powder | 5.4 | Tons per Annum | | Indigenous | Road | | 250 | Open Market | | Copy of Linkage | (14.) | wood saw Dust | 5760 | Tons per Annum | | Indigenous | Road | | 120 | Open Market | | Copy of Linkage | (15.) | Strips of Pine woods | 43200 | Tons per Annum | | Indigenous | Road | | 120 | Open Market | | Copy of Linkage | (16.) | Sodium pentachlorophenate | 6 | Tons per Annum | | Indigenous | Road | | 250 | Open Market | | Copy of Linkage | (17.) | n-Butyl Alcohol | 93.6 | Tons per Annum | | Indigenous | Road | | 250 | Open Market | | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 01 Oct 2017 To 31 Dec 2017 | (b)Season | Winter | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | PM10 | | Micro Gram per Meter Cube | 98.00 | 60.00 | 94.00 | 100 per 24 Hr | (2.) | PM2.5 | | Micro Gram per Meter Cube | 47.00 | 15.00 | 43.32 | 60 per 24 Hr | (3.) | SO2 | | Micro Gram per Meter Cube | 24.00 | 12.00 | 22.00 | 80 per 24 Hr | (4.) | NOx | | Micro Gram per Meter Cube | 30.00 | 18.00 | 29.00 | 80 per 24 Hr | |
14.2. No. of Ground Water monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | TDS | | | mg/l | | 5166.00 | 1094.00 | 500 | 2000 | (2.) | pH | | | NA | | 8.31 | 7.08 | 6.5 | 8.5 | (3.) | Chlorides | | | mg/l | | 2910.80 | 398.00 | 250 | 1000 | (4.) | Fluoride | | | mg/l | | 20.10 | 1.40 | 1.0 | 1.5 | (5.) | TSS | | | Others | NTU | 0.1 | 0.1 | 1 | 5 | (6.) | Heavy Metals | | Lead | mg/l | | 0 | 0 | 0 | 0.1 | (7.) | Total Hardness | | | mg/l | | 2400.90 | 400.70 | 200 | 600 | |
14.3. No. of Surface Water monitoring locations : 4 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | pH | | NA | | 8.48 | 8.13 | A | (2.) | DO | | mg/l | | 6.80 | 3.80 | E | (3.) | BOD | | mg/l | | 108.00 | 8.00 | E | (4.) | COD | | mg/l | | 306.0 | 22.4 | E | |
14.4. No. of Ambient Noise monitoring locations : 8 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Night) | A-weighted decibels(dB(A)) | 42.90 | 33.10 | 70 | (2.) | Leq(Day) | A-weighted decibels(dB(A)) | 61.60 | 48.50 | 75 | |
14.5. No. of Soil Sample Monitored locations : 8 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | pH | Others | - | 8.31 | 7.08 | (2.) | Electric Conductivity | Millisiemens per Centimetre | | 7.71 | 1.63 | (3.) | P(Phosphorus) | Milligram per Kilogram | | 0.06 | 0.02 | (4.) | K(Potassium) | Milligram per Kilogram | | 3.60 | 3.00 | (5.) | N(Nitrogen) | Milligram per Kilogram | | 19.00 | 3.10 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 3 To 5 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 6 To 8 | (c)Whether Ground Water Intersection will be there ? | No | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | GroundWater | | 14.5 | 0 | Copy of Permission Letter | Pipeline | | Open Well | | 21-4/3522/GJ/IND/2018 | 16 Feb 2018 | 14.5 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | Industrial | 0.50 | 0 | Recycling | Reuse within the Plant & Recycling | | 0.5 | | (2.) | Domestic | 1.50 | 0 | N/A | Others | Septic Tank | 0 | 1.50 | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 2 | (b)Total Discharged Water (Kilolitre per Day) | 1.5 | (c)Total Reused Water (Kilolitre per Day) | 0.5 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Resin Residue | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 2.4 | Tons | 0 | Others | In House Transfer | Others | To be reused in next batch preparation. | (2.) | Discarded Empty Bags, Drums, Carboys & Paper | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 312 | Tons | 20 | Road | | Authorized Recyclers | | (3.) | Used Oil | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 0.05 | Kilolitre | 20 | Road | | Authorized Recyclers | | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | PM10 | | Microgram per Meter Cube | 88.38 | 0 | 1.68 | 90.06 | 100 /24hr | (2.) | SO2 | | Microgram per Meter Cube | 20.04 | 0 | 0.99 | 21.03 | 80 /24hr | (3.) | NOx | | Microgram per Meter Cube | 27.25 | 0 | 7.51 | 34.76 | 80 /24hr | (4.) | PM2.5 | | Microgram per Meter Cube | 39.33 | 0 | 0.42 | 39.75 | 60 /24hr | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | DG Set I | Diesel | 9 | 0.2 | SO2 | | 0.139 | (2.) | DG set I | Diesel | 9 | 0.2 | PM10 | | 0.149 | (3.) | Trimming Machine | - | 15 | 0.2 | PM10 | | 0.039 | (4.) | DG Set I | Diesel | 9 | 0.2 | NOx | | 1.048 | (5.) | Foaming | - | 15 | 0.2 | PM10 | | 0.024 | (6.) | TFH | Agro Waste | 30 | 0.4 | NOx | | 0.310 | (7.) | Sanding Machine | - | 15 | 0.2 | PM10 | | 0.039 | (8.) | DG Set II | Diesel | 9 | 0.2 | PM10 | | 0.037 | (9.) | DG Set II | Diesel | 9 | 0.2 | SO2 | | 0.035 | (10.) | DG Set II | Siesel | 9 | 0.2 | NOx | | 0.261 | (11.) | TFH | Agro Waste | 30 | 0.4 | SO2 | | 0.035 | (12.) | TFH | Agro Waste | 30 | 0.4 | PM10 | | 0.104 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 1200 | (b)Source | PGVCL | (c)Uploaded Copy of Agreement | Copy of Agreement | (d)Standby Arrangement (Details of DG Sets) | 2 Nos. D.G. Set: Existing : 500 KVA, Proposed: 12 | (e)Stack Height (in m) | 9 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 0 | (b)Private Land (ha.) | 2.5 | (c)Government Land (ha.) | 0 | (d)Revenue Land (ha.) | 0 | (e)Other Land (ha.) | 0 | Total Land (ha.) | 2.5 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 25052.00 | (b)Waste/Barren Land (ha.) | 523.00 | (c)Grazing/ Community Land (ha.) | 0 | (d)Surface Water Bodies (ha.) | 1360.00 | (e)Settlements (ha.) | 1440.00 | (f)Industrial (ha.) | 805.00 | (g)Forest (ha.) | 0 | (h)Mangroves (ha.) | 0 | (i)Marine Area (ha.) | 0 | (j)Others (ha.) : Land with scrub | 2235.00 | Total (ha.) | 31415 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Built Up Area | | 1.0 | | (2.) | Others | Open Land Internal Road Area | 0.68 | | (3.) | Green belt | | 0.83 | | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | WLS | Not within the study area | . | . | (2.) | NPA | Not within the study area | . | . | (3.) | ESAs | Not within the study area | . | . | (4.) | Critically Polluted Area | Not within the study area | . | . | (5.) | ESZs | Not within the study area | . | . | (6.) | Wildlife Corridors | Not within the study area | . | . | (7.) | Corridors | Not within the study area | . | . | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Forest | | Not within the study area | . | . | (2.) | Archaeological Sites | | Not within the study area | . | . | (3.) | Defence Installations | | Not within the study area | . | . | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
25. | Tree Cutting: | (a)No. of Trees Cut for the Project (if Forest Land not Involved) | Not Applicable | (b)Details of Tree Cutting and Planting of Trees | Not Applicable | |
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 2.5 | (b)Land yet to be acquired(Ha) | 0 | (c)Status of Land acquisition if not acquired | - | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 0 | (b)No. of Households | 0 | (c)No. of PDFs (Project Displaced Families) | 0 | (d)No. of PAFs (Project Affected Families) | 0 | (e)Funds Allocated for R&R(in INR) (in Lacs) | 0 | (f)Status of R&R | Yet To Start | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | Yes | (i)Details of Schedule-I Species | Indian Peafowl (Pavo cristatus), Lissemys punctata - Indian Flapshell Turtle | (b)Whether conservation plan for Schedule-I Species has been prepared ? | Yes | (i)Uploaded copy of conservation plan | Copy of conservation plan | (ii)Fund Provision made | 2 Lakhs | (iii)Period of Implementation | Continuous | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | No | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | Yes | (i)Details of Water Bodies in Buffer Area | Khetarkhadi(Tributary Godadhar Nadi) | (ii)Direction of Water Bodies in Buffer Area | North East | (iii)Distance of Water Bodies in Buffer Area | 1.87 | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 0 | (b)Permanent Employment-During Operation | 85 | (c)Temporary Employment- During Construction | 5 | (d)Temporary Employment- During Operation | 11 | (e)No. of working days | 300 | (f)Total Manpower | 101 | |
|
|
S. No. | Description | Existing | Proposed | Total |
---|
(1.) | Total Area of Green Belt | 0.83 | 0.0 | 0 | (2.) | Percentage of Total Project Area | 33.2 | 0 | 33 | (3.) | No. of Plants | 1245 | 0 | 1245 | (4.) | Funds Allocated | 1.5 | 0.25 | 1 | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Social | Company has planned to spend Rs.0.30 Lakhs/Annum for CSR activities. Which will result in development or improvement of many public amenities/facilities of the area. This CSR activities will also be helpful to improve quality of life as well as improvement of Health, Education and skill of local people.
Employment to 46 people in addition to 50 person in existing unit. In addition to this, indirect employment will also have similar benefits. These together will be considerably helpful in increas | (2.) | Financial | Company has planned to increase its capacity by 2 times which will result in 2 times higher payment of taxes & other levies, which will be considerably beneficial to the Government Exchequer. | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details : NOT APPLICABLE |
35. Sector Specific Details For Industrial Projects - 2 |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | 153 | (ii)Name of the EIA Consultant | Unistar Environment & Research Labs Pvt. Ltd. | (iii)Address | 215, Royal Arcade, Near GIDC Office, Vapi –396195 | (iv)Mobile No. | 9909946373 | (v)Landline No. | 0260243561 | (vi)Email Id | unistar@uerl.in | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | Industrial Projects - 2 | (ix)Validity of Accreditation | 30 Jan 2020 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought: |
---|
Sno. | EDS Letter | Remarks | Date of EDS |
---|
1. | NA | Please inform/clarify the following:-
- Consent of SPCB to allow the proposed resin mfg unit of capacity 12200 TPA at the given site,
- Present status of clearance for ground water withdrawal,
- Daily fuel consumption along with the undertaking in this regard,
- Expansion of particle board mfg from the present of 18000 TPA to 10800 TPA is not justified. | 01 Oct 2018 | 2. | NA | The correction have been made as per the instruction received | 02 Oct 2018 | 3. | NA | Please provide the details as desired vide query dated 1/10/2018 for further consideration of the proposal. | 02 Oct 2018 | 4. | NA | The correction have been made as per the instruction received | 18 Dec 2018 | 5. | NA | - No certificate of Accreditation has been attached against column 38 of Form-2.
- Given the water and fuel consumption, the project would be covered under small units and thus requires appraisal/approval applicable for category B i.e. at the state level. | 28 Dec 2018 | 6. | NA | The correction have been made as per the instruction received | 01 Jan 2019 | 7. | NA | In view of your last submissions, please inform whether any permission would be required under the MSIHC Rules, 1989 and/or the approval from PESO for the proposed site plan or storage of hazardous chemicals.Present status of the application for ground water withdrawal may also be informed. | 11 Jan 2019 | 8. | NA | The correction have been made as per the instruction received | 12 Jan 2019 | |
Additional Detail Sought : NIL |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | Deep Patel | Designation | Director | Name of Company (Applicant Name should not be given here) | SUN PARTICLE BOARD PVT LTD | Address | Survey no.441/P1&2, Haripar-Kerala Road, Village-Bela (Rangpar), Bela(Rangpar)-363642, Tal.Dist- Morbi |
|