Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Sunvik Steel Private Limited
(b)Name of the Company / Organisation Sunvik Steels Pvt Ltd
(c)Registered Address No.23, 3rd Floor, MES Road, Bahubali Nagar, Jalahalli Village, Bangalore 560013,No.23, 3rd Floor, MES Road, Bahubali Nagar, Jalahalli Village, Bangalore 560013,Bangalore Urban,Karnataka-560013
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Vivek Kejriwal
(b)Designation (Owner/ Partner/ CEO) Managing Director
(c)Address No.23, 3rd Floor, MES Road, Bahubali Nagar, Jalahalli Village, Bangalore 560013,No.23, 3rd Floor, MES Road, Bahubali Nagar, Jalahalli Village, Bangalore 560013,,Bangalore Urban,Karnataka-560013
(d)Pin code 560013
(e)E-mail harish@sunvik.in
(f)STD Code. 80(f)Telephone No. 23084713
(g)Fax No. 23084799
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity3(a) Metallurgical industries (ferrous & non ferrous)
Minor Activity
(b)Category A
(c)Proposal Number IA/KA/IND/79611/2008
(d)Master Proposal Number(Single Window) SW/79609/2018
(e)EAC concerned (for category A Projects only) Industrial Projects - 1
(f)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. 24, 33, 33P - P4, 56, 57, 59 to 72
(b)Pincode 560013
(c)Bounded Latitudes (North)
From
Degree 13.553417
Minutes
Second
From
Degree 13.558122
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 77.008008
Minutes
Second
From
Degree 77.015778
Minutes
Second
(e)Survey of India Topo Sheet No. 57 C/14 and 57 G/2
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 792
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 5.0
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Karnataka
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number J-11011/959/2008-IA II (I)
(c)Date of Issue of TOR 09 Feb 2009
(f)Previous TOR Letter Copy of Previous TOR letter
(b)Date of Apply of EC 20 Sep 2018
(c)Date of Issue of EC 06 May 2021
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :11 Aug 2017
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :12 Sep 2017
Distance of Public Hearing Venue from the Proposed Project :2.5
Near premises of Sri Rama Devara Temple Community Hall
State :Karnataka
District :Tumkur
Tehsil :Sira
Village :Haldodderi
70Dust pollution, Crop damage, Road damage, etc.Deputy Commissioner
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Bangalore
(iii)Letter No. EP/12.1/629/Karnataka
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit May 19 2018 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Sponge Iron9000060000150000Tons per Annum(TPA)Road
(2.)MS Ingots or Billets36000150000186000Tons per Annum(TPA)Road
(3.)Rolled Products30000150000180000Tons per Annum(TPA)Road
(4.)Cold Briquetted Iron060006000Tons per Annum(TPA)Road
(5.)Iron ore concentrate or Pellets0600000600000Tons per Annum(TPA)Road
(6.)Fly ash bricks20001800020000OthersBricks per dayRoad
(7.)WHRB Power Plant6511Mega Watt(MW)Othersthrough electrical cables
(8.)AFBC Power Plant41014Mega Watt(MW)Othersthrough electrical cables
(9.)Pig Iron09000090000Tons per Annum(TPA)Roadthrough electrical cables
(10.)Slag crusher and beneficiation4500900013500Tons per Annum(TPA)Road
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)AFBC Power Plant4 MW10 MW14 MW
(2.)Fly ash brick unit2000 Bricks/day18000 Bricks/day20000 Bricks/day
(3.)Rolling Mill1 x 100 TPD1 x 500 TPD1 x 100 TPD & 1 x 500 TPD
(4.)Tunnel Kilns02 x 100 TPD2 x 100 TPD
(5.)Iron ore beneficaiton & Pelletisation01 x 2000 TPD1 x 2000 TPD
(6.)Slag Crusher & Beneficiation Plant1 x 15 TPD1 x 30 TPD1 x 15 TPD & 1 x 30 TPD
(7.)WHRB Power Plant6 MW5 MW11 MW
(8.)DRI Kiln3 x 100 TPD1 x 200 TPD3 x 100 TPD & 1 x 200 TPD
(9.)Induction Furnace1 x 12 T2 x 25 T1 x 12 T & 2 x 25 T
(10.)Blast Furnace01 x 125 m31 x 125 m3
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 15 Sep 2016
(iv)Valid Upto 30 Jun 2021
(v)File No. AW-300966
(vi)Application No. 11783
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 550
(b) Funds Allocated for Environment Management (Capital) (in Crores) 47
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 4.25
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 3.45
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 96000
(b)Existing quantity of raw material/fuel 144000
(c)Total quantity of raw material/fuel 240000
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Imported Coal150000Tons per AnnumIndonesia or AustraliaRoad,Rail350 MoUCopy of Linkage
(2.)Iron Ore fines900000Tons per AnnumKarnatakaRoad,Rail200 e-auctionCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Oct 2015 To 31 Dec 2015
(b)Season Winter
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM2.5Micro Gram per Meter Cube31.417.131.460
(2.)PM10Micro Gram per Meter Cube52.329.652.3100
(3.)OthersCOMicro Gram per Meter Cube6903556902000
(4.)SO2Micro Gram per Meter Cube15.99.515.980
(5.)NOxMicro Gram per Meter Cube17.99.917.980
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA7.67.16.58.5
(2.)TSSmg/l1.4100
(3.)TDSmg/l3752435002000
(4.)Total Hardnessmg/l302177300600
(5.)Chloridesmg/l1801052501000
(6.)Fluoridemg/l0.360.181.01.5
(7.)Heavy MetalsFemg/l0.0390.0200.31.0
    14.3.     No. of Surface Water monitoring locations : 4
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA8.17.8A
(2.)DOmg/l6.63.3A
(3.)BODmg/l4.83.2A
(4.)CODmg/l138.5A
(5.)OthersTDSmg/l379166A
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))613870
(2.)Leq(Day)A-weighted decibels(dB(A))654475
    14.5.     No. of Soil Sample Monitored locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pHOthersNA7.67.1
(2.)N(Nitrogen)Kilogram per hectare292205
(3.)P(Phosphorus)Kilogram per hectare8252
(4.)Electric ConductivityKilogram per hectare188123
(5.)K(Potassium)Kilogram per hectare3623
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 1.2 To 12
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 0.3 To 11
(c)Whether Ground Water Intersection will be there ? Yes
(d)Upload Copy of Central Ground Water Authority Letter Copy of Central Ground Water Authority Letter
(e)Letter No. KGA/CU Application-1/2017-18
(f)Date of Issue 04 Nov 2017
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater10000Copy of Permission LetterPipelineTube WellKGA/CU Application-1/2017-1804 Nov 20171642
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)GCP effluent8080Settling TankReuse within the Plant & Recycling80
(2.)DM Plant Regeneration2020sent to Central Monitoring BasinGreen Belt Renewal Plant20
(3.)sanitary wastewater1616septic tank following by saok pitOthersseptic tank followed by soak pit016
(4.)Boiler Blowdown2424sent to Central Monitoring BasinGreen Belt Renewal Plant240
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 140
(b)Total Discharged Water (Kilolitre per Day) 16
(c)Total Reused Water (Kilolitre per Day) 124
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Ash from Pellet PlantIndustrial Waste16200Tons0RoadOthersutilized in existing Brick manufacturing unit
(2.)Wet Scrapper sludgeIndustrial Waste27000Tons100RoadOtherswill be given to Brick manufacturer
(3.)Cinder from GasifierIndustrial Waste20Tons0RoadOthersutilised in existing Brick manufacturing unit
(4.)Dust from APCSOthersDust300Tons0RoadOthersutilised in existing brick manufacturing unit
(5.)TailingsIndustrial Waste270000Tons270RoadOthersgiven to Processing Plant
(6.)DolocharIndustrial Waste18000Tons0Conveyor BeltOtherswill be utilised in FBC Power plant
(7.)slag from SMSIndustrial Waste3000Tons25RoadOthersafter recovery of Fe, used for road construction
(8.)Mill ScalesIndustrial Waste3000Tons30RoadOthersgiven to ferro alloys unit
(9.)End cuttingIndustrial Waste4500Tons0Conveyor BeltOthersresued in induction furnace
(10.)Ash from Power PlantFly Ash15120Tons0RoadOthersused in existing brick manufacturing unit
(11.)Tar from GasifierHazardous Waste (as per Hazardous and Other Waste Management rules 2016)4Kilolitre100RoadOthersgiven to Tar recyclers
(12.)Kiln accretion slagIndustrial Waste6000Tons25RoadOtherswill be used in road construction
(13.)Granulated slagIndustrial Waste27000Tons100RoadOthersgiven to concrete block manufacturing units
(14.)Ash from DRIIndustrial Waste10800Tons0RoadOthersutilised in existing brick manufacturing unit
(15.)waste oilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1.0Kilolitre100RoadAuthorized Recyclers
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube52.310507.6259.92100
(2.)SO2Microgram per Meter Cube15.9105021.737.680
(3.)NOxMicrogram per Meter Cube17.8105012.930.780
(4.)Others(Specify)COMicrogram per Meter Cube69010502.06922000
(5.)PM2.5Microgram per Meter Cube31.410504.135.560
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)Rolling MillProducer Gas451.0NOx4.0
(2.)Pellet PlantProducer Gas522.2NOx7.6
(3.)DRI KilnCoal701.9PM101.5
(4.)DRI KilnCoal701.9SO221.4
(5.)Induction FurnaceElectricity301.0PM100.5
(6.)Induction FurnaceElectricity301.0NOx1.9
(7.)Rolling MillProducer Gas451.0PM100.4
(8.)Blast Furnace StoveBF Coke501.7NOx3.0
(9.)AFBC Power PlantCoal561.5SO21.8
(10.)Tunnel KilnProducer Gas611.0SO210.9
(11.)Pellet PlantProducer Gas522.2PM101.9
(12.)Blast Furnace StoveBF Coke501.7PM1017.4
(13.)DRI KilnCoal701.9NOx5.8
(14.)Blast Furnace StoveBF Coke501.7SO217.4
(15.)AFBC Power PlantCoal561.5NOx1.8
(16.)Tunnel KilnProducer Gas611.0NOx1.6
(17.)Rolling MillProducer Gas451.0SO213.4
(18.)AFBC Power PlantCoal561.5PM100.5
(19.)Tunnel KilnProducer Gas611.0PM100.4
(20.)Pellet PlantProducer Gas522.2SO221.3
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 45800
(b)Source 25 MW Captive & 20.8 MW from State Grid
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 600 KVA, 380 KVA, 160 KVA
(e)Stack Height (in m) 7
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 20.03
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 19.43
    Total Land (ha.) 39.46
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 0
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 20.03
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : 0 19.43
    Total (ha.) 39
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Main Plant12.14Plant area (existing and proposed)
(2.)Area for Solid Waste Management2.83Tailing and Solid waste storage
(3.)Green belt13.36Greenbelt (existing and proposed)
(4.)Water Reservoir1.21Water Reservoir
(5.)OthersRaw material & product Storage area9.92
Total (ha.) 39.46
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)WLSNA0NA
(2.)NPANA0NA
(3.)ESAsNA0NA
(4.)ESZsNA0NA
(5.)CorridorsNA0NA
(6.)Wildlife CorridorsNA0NA
(7.)Critically Polluted AreaNA0NA
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestAnkasandra6.2Nil
(2.)Archaeological SitesNone0Nil
(3.)Defence InstallationsNone0Nil
(4.)Otherswater bodyDoddahalla Stream5.0nil
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 25.3
(b)Land yet to be acquired(Ha) 14.16
(c)Status of Land acquisition if not acquired To be allotted under Section 109 of Karnataka Land
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Doddahalla Stream
(ii)Direction of Water Bodies in Buffer Area West
(iii)Distance of Water Bodies in Buffer Area 5.0
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 150
(c)Temporary Employment- During Construction 300
(d)Temporary Employment- During Operation 0
(e)No. of working days 365
(f)Total Manpower 450
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt6.96.4612
(2.)Percentage of Total Project Area34.533.367
(3.)No. of Plants117501000021750
(4.)Funds Allocated7000006000001300000
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)EnvironmentalWith the implementation of the proposed plant, the socio-economic status of the local people will improve substantially. This will help in upliftment of the social status of the people in the area. Educational institutions will also come-up and will lead to improvement of educational status of the people in the area. Primary health and medical facilities will certainly improve due to the proposed plant.
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 1
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1619/RA 026
(ii)Name of the EIA Consultant Pioneer Enviro Laboratory and Consultants Pvt Ltd
(iii)Address 6-3-652, Flat # 7-3, Dhruvatara Apartments, Amrutha Estates, Erramanjil, Somajiguda, Hyderabad- 500082
(iv)Mobile No. 9440677333
(v)Landline No. 0402331427
(vi)Email Id pelcpl@yahoo.co.in
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 1
(ix)Validity of Accreditation 22 Jun 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File NA
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterDear sir,please find the attachment for Reply to ADS 19 Mar 2021
2.NA26.0 After detailed deliberations, the Committee observed that non-compliance for two of the earlier environmental conditions granted in 2009 i.e. prior permission for abstraction of ground water and prior approval from the State Forest Department regarding likely impact of the emissions of the plant on the reserved forest and the project proponent shall also be required to prepare and implement conservation plant for wildlife in consultation with State Forest Department.vThe Committee also noted several terms of reference prescribed were not addressed properly. Recommendations of the Committee: 27.0 Therefore, the Committee advised to submit the following information/reports for further consideration of the proposal. i) Closure of non-compliances of the earlier environmental clearance 12 Oct 2018
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantVivek Kejriwal
DesignationManaging Director
Name of Company (Applicant Name should not be given here)Sunvik Steels Pvt Ltd
AddressNo.23, 3rd Floor, MES Road, Bahubali Nagar, Jalahalli Village, Bangalore 560013