1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | Proposed expansion in manufacturing expansion of dyes and chemicals manufacturing unit of /s. Spectrum Dyes & Chemicals Pvt. Ltd. | (b)Name of the Company / Organisation | SPECTRUM DYES AND CHEMICALS PVT. LTD. | (c)Registered Address | Block no. 484,502, 503 A, 504 & 505. NH-8, Palsana, Dist: Surat, Gujarat.,,Surat,Gujarat-394315 | (d)Legal Status of the Company | Private | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | Avneep Bansal | (b)Designation (Owner/ Partner/ CEO) | Director | (c)Address | Block no. 484,502,503 A, 504, 505, NH 8, Palsana, Dist Surat, Gujarat.,,Palsana,Surat,Gujarat-394315 | (d)Pin code | 394315 | (e)E-mail | env@spectrumdyes.com | (f)STD Code. | 0(f)Telephone No. | 0 | (g)Fax No. | | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
| Minor Activity | | (b)Category | A | (c)Proposal Number | IA/GJ/IND2/79313/2017 | (d)Master Proposal Number(Single Window) | SW/79128/2018 | (e)EAC concerned (for category A Projects only) | Industrial Projects - 2 | (f)Project Type | Expansion |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | Block no-484, 502, 503-A , 504 & 505 | (b)Pincode | 394315 | (c)Bounded Latitudes (North) | | From | | Degree | 21.094666 | Minutes | | Second | | From | | Degree | 21.095960 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 72.975479 | Minutes | | Second | | From | | Degree | 72.975636 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | F43M16/F43N4,(46C/16,46G/4) | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 19.51 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 0 | (j)Seismic Zone | 3 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Gujarat | |
|
|
Details of State of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
NIL | |
|
6. | Details of Terms of Reference (ToR)/EC: | (a)MoEF&CC / SEIAA File Number | J-11011/36/2003-IA-II(II) | (c)Date of Issue of TOR | 09 Dec 2017 | (f)Previous TOR Letter | Copy of Previous TOR letter | (b)Date of Apply of EC | 01 Oct 2018 | (c)Date of Issue of EC | 09 May 2019 | (d)Previous EC Letter | Copy of Previous EC letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | No | (b)Whether details of Public Hearing available? | Yes | (c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above | Yes | |
|
7.1. Details of Public Hearing |
---|
|
S. No. | Details of Advertisement | Details of Public Hearing | Venue | Location Details | No. of People Attended | Issues Raised | Designation of Presiding Officer | Other Designation of Presiding Officer |
---|
(1.) | | Copy of Public Hearing : | Copy of Public Hearing | Date : | 25 May 2018 | Distance of Public Hearing Venue from the Proposed Project : | 1.6 |
| Late Shree Chhotubhai Dayalji Desai hall, Behind Post Office, Palsana Main Road | State : | Gujarat | District : | Surat | Tehsil : | Chorasi | Village : | Palsana |
| 116 | 26 Verbal Issues Raised During Public Hearing & 25 Written Issued before public hearing through GPCB. Reply for both type of queries given in PH Proceedings. Attached herewith as well as Annexure-XLII | Others | | |
8. | Details of Project Configuration/Product: | Details Not Applicable | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | (a)Details of certified report on compliance of earlier environmental clearance condition | (i)Certified Compliance By | Regional | (ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on | Bhopal | (iii)Letter No. | 5-77/2004(ENV)/448 | (iv)Status of Compliance | Compiled | (v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) | Copy of Certified Compliance Report | (vi)Date of site visit | Jul 20 2018 12:00AM | (b)Details of Capacity Expansion | |
|
S. No. | Product/Activity (Capacity/Area) | Quantity From | Quantity To | Total | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | Dispersing Agent | 1500 | 0 | 1500 | Others | MT/Month | Road | | (2.) | Dyes Intermediate | 400 | 350 | 750 | Others | MT/Month | Road | | (3.) | S.O dyes | 250 | 650 | 900 | Others | MT/Month | Road | | (4.) | Formulated SO dyes | 0 | 2400 | 2400 | Others | MT/Month | Road | | |
| (c)Details of Configuration | |
|
S. No. | Plant / Equipment / Facility | Existing Configuration | Proposed Configuration | Final configuration after expansion | Remarks |
---|
(1.) | Boiler | 6 TPH Running + 4 TPH stand by | 10 TPH Running + 6 TPH Stand By | 10 TPH Running + 6 TPH Stand By | 4 TPH will be resale | (2.) | Spray Dryer | Existing 6 Nos. | Proposed 1 Nos. | Total 7 Nos. | | (3.) | Effluent Treatment Plant | 1 MLD | 2.5 MLD | 2.5 MLD | Modification and up gradation in existing | (4.) | HAG | 1 Nos - 4000 U | 1 Nos - 3000 U | 1 Nos – 4000U 1 Nos - 3000 U | | (5.) | Thermopack | 1 Nos. 2,00,000 Kcal/hr, 1 Nos. 3,00,000 Kcal/hr | 0 | 1 Nos. 2,00,000 Kcal/hr, 1 Nos. 3,00,000 Kcal/hr | | |
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | 28 Aug 2015 | (iv)Valid Upto | 21 Oct 2019 | (v)File No. | AWH/ 80897 & GPCB/CCA-SRT-123(12)/ID_21392/371557 | (vi)Application No. | 100571 | (vii)Copy of Consent to operate valid as on date | Copy of Consent to Operate | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 47.58 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 31.56 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 0.92 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 11.65 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | No | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 40068 | (b)Existing quantity of raw material/fuel | 24207 | (c)Total quantity of raw material/fuel | 64275 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | Sulfuric Acid | 5256 | Tons per Annum | | Local Market | Road | | 50 | Others | RM Annexure | Copy of Linkage | (2.) | Naphthalene | 6420 | Tons per Annum | | Local Market | Road | | 50 | Others | RM Annexure | Copy of Linkage | (3.) | Acetic Acid | 2556 | Tons per Annum | | Local Market | Road | | 50 | Others | RM Annexure | Copy of Linkage | (4.) | Caustic Lye (100%) | 4512 | Tons per Annum | | Local Market | Road | | 50 | Others | RM Annexure | Copy of Linkage | (5.) | Dimethylformamide (DMF) | 1536 | Tons per Annum | | Local Market | Road | | 50 | Others | RM Annexure | Copy of Linkage | (6.) | Coal | 27375 | Tons per Annum | | Local Market | Road | | 50 | Others | RM Annexure | Copy of Linkage | (7.) | Methanol | 3120 | Tons per Annum | | Local Market | Road | | 300 | Others | RM Annexure | Copy of Linkage | (8.) | Oleum | 7380 | Tons per Annum | | Local Market | Road | | 50 | Others | RM Annexure | Copy of Linkage | (9.) | Phenol | 1140 | Tons per Annum | | Local Market | Road | | 300 | Others | RM Annexure | Copy of Linkage | (10.) | ammonia | 864 | Tons per Annum | | Local Market | Road | | 50 | Others | RM Annexure | Copy of Linkage | (11.) | HCl (30% Solution) | 8304 | Tons per Annum | | Local Market | Road | | 50 | Others | RM Annexure | Copy of Linkage | (12.) | Soda ash | 1224 | Tons per Annum | | Local Market | Road | | 100 | Others | RM Annexure | Copy of Linkage | (13.) | Sodium Acetate | 3840 | Tons per Annum | | Local Market | Road | | 100 | Others | RM Annexure | Copy of Linkage | (14.) | Ethylene Oxide | 744 | Tons per Annum | | Local Market | Road | | 50 | Others | RM Annexure | Copy of Linkage | (15.) | 1,4- DI HYDROXYANTHRAQUINONE | 84 | Tons per Annum | | Local Market | Road | | 50 | Others | RM Annexure | Copy of Linkage | (16.) | Formaldehyde | 4332 | Tons per Annum | | Local Market | Road | | 50 | Others | RM Annexure | Copy of Linkage | (17.) | NG | 460 | Others | SCM/hr | Local Market | Others | Pipeline | 100 | Others | RM Annexure | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 01 Oct 2017 To 31 Dec 2017 | (b)Season | Winter | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | PM2.5 | | Micro Gram per Meter Cube | 34.70 | 29.30 | 33.50 | 60 | (2.) | SO2 | | Micro Gram per Meter Cube | 19.60 | 14.30 | 17.18 | 80 | (3.) | Others | co | Micro Gram per Meter Cube | 540.0 | 230.0 | 345.73 | 2000 | (4.) | NOx | | Micro Gram per Meter Cube | 24.10 | 17.10 | 20.82 | 80 | (5.) | PM10 | | Micro Gram per Meter Cube | 65.20 | 56.20 | 62.93 | 100 | |
14.2. No. of Ground Water monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | pH | | | mg/l | | 7.27 | 6.72 | 6.5 | 8.5 | (2.) | TSS | | | mg/l | | 23 | 5 | 100 | 300 | (3.) | Fluoride | | | mg/l | | 0 | 0 | 0 | 0 | (4.) | Chlorides | | | mg/l | | 545 | 60 | 250 | 1000 | (5.) | Others | COD | | mg/l | | 16.0 | 8.0 | 100 | 1000 | (6.) | Total Hardness | | | mg/l | | 231 | 138 | 300 | 600 | (7.) | TDS | | | mg/l | | 1448 | 540 | 500 | 2000 | |
14.3. No. of Surface Water monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | Others | TDS | mg/l | | 1088 | 238 | A | (2.) | pH | | Others | pH Unit | 7.5 | 6.8 | A | (3.) | DO | | mg/l | | 6.90 | 6.0 | A | (4.) | COD | | mg/l | | 96 | 8 | A | (5.) | BOD | | mg/l | | 30 | 3 | A | |
14.4. No. of Ambient Noise monitoring locations : 8 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Night) | A-weighted decibels(dB(A)) | 61.60 | 54.20 | 70 | (2.) | Leq(Day) | A-weighted decibels(dB(A)) | 68.80 | 60.10 | 75 | |
14.5. No. of Soil Sample Monitored locations : 3 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | pH | Others | pH unit | 7.8 | 7.5 | (2.) | P(Phosphorus) | Milligram per Kilogram | | 0 | 0 | (3.) | Electric Conductivity | Others | NA | 0 | 0 | (4.) | N(Nitrogen) | Milligram per Kilogram | | 60 | 50 | (5.) | K(Potassium) | Milligram per Kilogram | | 0 | 0 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 10.85 To 2.84 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 3 To 5 | (c)Whether Ground Water Intersection will be there ? | No | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | GroundWater | | 2700 | 0 | Copy of Permission Letter | Pipeline | | Tube Well | | 21-4/3481/GJ/IND/2018 - Existing + Proposed | 27 Jan 2018 | 2700 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | Processing | 1875 | 1875 | ETP | Others | CETP | 0 | 1875 | (2.) | floor & drum washing | 25 | 25 | ETP | Others | CETP | 0 | 25 | (3.) | Domestic | 75 | 75 | ETP | Others | CETP | 0 | 75 | (4.) | Boiler & Cooling | 270 | 270 | ETP | Others | CETP | 0 | 270 | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 2245 | (b)Total Discharged Water (Kilolitre per Day) | 2245 | (c)Total Reused Water (Kilolitre per Day) | 0 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | ETP sludge | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 15000 | Tons | 300 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (2.) | Discarded container | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 60000 | Tons | 50 | Road | | Authorized Recyclers | | (3.) | used oil | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 1.8 | Tons | 50 | Road | | Authorized Recyclers | | (4.) | process waste | Industrial Waste | | 60 | Tons | 100 | Road | | Others | CHWIF | (5.) | distillation residue | Industrial Waste | | 2100 | Tons | 100 | Road | | Others | CHWIF | (6.) | gypsum | Industrial Waste | | 6000 | Tons | 300 | Road | | Co-Processing | | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | PM2.5 | | Microgram per Meter Cube | 63.62 | 1.5 | 0.13 | 63.75 | 60 | (2.) | NOx | | Microgram per Meter Cube | 19.05 | 1.5 | 0.025 | 19.075 | 80 | (3.) | SO2 | | Microgram per Meter Cube | 15.71 | 1.5 | 0.05 | 15.76 | 80 | (4.) | PM10 | | Microgram per Meter Cube | 63.62 | 1.5 | 0.13 | 63.75 | 100 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | 10 TPH boiler + HAG | coal / Lignight | 36 | 1 | PM10 | | 1.13 | (2.) | 10 TPH boiler + HAG | coal / Lignite | 36 | 1 | SO2 | | 0.87 | (3.) | DD plant scrubber | NA | 6 | 0.2 | Others | HCL | 0.0022 | (4.) | 10 TPH boiler + HAG | coal/Lignite | 36 | 1 | NOx | | 0.43 | (5.) | spray dryer 9 | steam(HAG) | 33 | 1.2 | PM10 | | 0.9 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 6000 | (b)Source | DGVCL | (c)Uploaded Copy of Agreement | Not Applicable | (d)Standby Arrangement (Details of DG Sets) | 6760 KVA | (e)Stack Height (in m) | 11 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 0 | (b)Private Land (ha.) | 4.98 | (c)Government Land (ha.) | 0 | (d)Revenue Land (ha.) | 0 | (e)Other Land (ha.) | 0 | Total Land (ha.) | 4.98 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 25307.34 | (b)Waste/Barren Land (ha.) | 1955.61 | (c)Grazing/ Community Land (ha.) | 0 | (d)Surface Water Bodies (ha.) | 173.79 | (e)Settlements (ha.) | 1725.87 | (f)Industrial (ha.) | 2255.75 | (g)Forest (ha.) | 0 | (h)Mangroves (ha.) | 0 | (i)Marine Area (ha.) | 0 | (j)Others (ha.) : N.A | 0 | Total (ha.) | 31418.36 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Green belt | | 1.02 | | (2.) | Main Plant | | 3.96 | | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Wildlife Corridors | N.A | 0 | N.A | (2.) | Corridors | N.A | 0 | N.A | (3.) | Critically Polluted Area | N.A | 0 | N.A | (4.) | WLS | NA | 0 | N.A | (5.) | NPA | N.A | 0 | N.A | (6.) | ESAs | N.A | 0 | N.A | (7.) | ESZs | N.A | 0 | N.A | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Forest | | N.A | 0 | N.A | (2.) | Archaeological Sites | | N.A | 0 | N.A | (3.) | Defence Installations | | N.A | 0 | N.A | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
25. | Tree Cutting: | (a)No. of Trees Cut for the Project (if Forest Land not Involved) | 0 | (b)Details of Tree Cutting and Planting of Trees | Not Applicable | |
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 4.98 | (b)Land yet to be acquired(Ha) | 0 | (c)Status of Land acquisition if not acquired | 100% land acquired | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 0 | (b)No. of Households | 0 | (c)No. of PDFs (Project Displaced Families) | 0 | (d)No. of PAFs (Project Affected Families) | 0 | (e)Funds Allocated for R&R(in INR) (in Lacs) | 0 | (f)Status of R&R | Completed | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | No | (b)Whether conservation plan for Schedule-I Species has been prepared ? | No | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | Yes | (i)Details of Water Bodies in Core Area | Mindhola river, 2.6 KM | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | No | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 0 | (b)Permanent Employment-During Operation | 122 | (c)Temporary Employment- During Construction | 0 | (d)Temporary Employment- During Operation | 0 | (e)No. of working days | 365 | (f)Total Manpower | 122 | |
|
|
S. No. | Description | Existing | Proposed | Total |
---|
(1.) | Total Area of Green Belt | 9017.90 | 1167.10 | 10184 | (2.) | Funds Allocated | 10 | 5 | 15 | (3.) | No. of Plants | 1250 | 350 | 1600 | (4.) | Percentage of Total Project Area | 20 | 31 | 51 | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Social | • Promoting Education, including Special Education and Employment Enhancing Vocation Skills Especially among Children, Women, Elderly, and the Differently-Able and Livelihood Enhancement Projects.
• Improve the Poverty and Malnutrition, Promoting Preventive Health Care and Sanitation and making available Safe Drinking Water. | (2.) | Financial | The company shall earmarks fund up to 91.53 lacs for Proposed CSR activity for 5 year
The proposed green belt will enhance the aesthetic beauty of the surrounding environment and Rs. 15.0Lacs fund is allocated for 5 years greenbelt development plan | (3.) | Environmental | • Ensuring Environmental Sustainability, Ecological Balance, Protection of Flora and Fauna, Animal Welfare, Agro-forestry, Conservation of Natural Resources and Maintaining Quality of Soil, Air and Water. | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details : NOT APPLICABLE |
35. Sector Specific Details For Industrial Projects - 2 |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | NABET/EIA/1720/RA 0099 | (ii)Name of the EIA Consultant | EN-VISION ENVIRONMENTAL SERVICES | (iii)Address | 201,301, UTC BUILDING, NR.APPLE HOSPITAL, UDHNA DARWAJA, 395002-SURAT | (iv)Mobile No. | 9428001891 | (v)Landline No. | 0261234477 | (vi)Email Id | eia@en-vision.co.in | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | Industrial Projects - 2 | (ix)Validity of Accreditation | 01 Dec 2020 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought: |
---|
Sno. | EDS Letter | Remarks | Date of EDS |
---|
1. | NA | - Please submit legible copy of the CCR for the EC dated 1/4/2004.
- Entry at item 6 of the Form-2 shows details as Nil, which needs to be rectified.
- Status of clearance required for ground water withdrawal to meet the requirement for the present industrial operations. | 23 Sep 2018 | 2. | NA | The correction have been made as per the instruction received | 24 Sep 2018 | 3. | NA | Our queries dated 23/9/2018 are yet to be addressed. Further, please clarify about the CTO obtained for the production capacity higher than the EC capacity of 250 TPM. | 29 Sep 2018 | 4. | NA | The correction have been made as per the instruction received | 01 Oct 2018 | |
Additional Detail Sought: |
---|
Sno. | ADS Letter | Remarks | Date of ADS |
---|
1. | ADS Reply Letter | With Reference to MOM of 1st EAC (Industry-2) Meeting dated 19-20 Dec 2018 , we hereby submit the Compliance of Online ADS Generated dated 02nd Jan 2019 as per attached. | 09 Jan 2019 | 2. | NA | Deferred | 02 Jan 2019 | |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | Avneep Bansal | Designation | Director | Name of Company (Applicant Name should not be given here) | SPECTRUM DYES AND CHEMICALS PVT. LTD. | Address | Block no. 484,502, 503 A, 504 & 505. NH-8, Palsana, Dist: Surat, Gujarat. |
|