Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Proposed expansion in manufacturing expansion of dyes and chemicals manufacturing unit of /s. Spectrum Dyes & Chemicals Pvt. Ltd.
(b)Name of the Company / Organisation SPECTRUM DYES AND CHEMICALS PVT. LTD.
(c)Registered Address Block no. 484,502, 503 A, 504 & 505. NH-8, Palsana, Dist: Surat, Gujarat.,,Surat,Gujarat-394315
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Avneep Bansal
(b)Designation (Owner/ Partner/ CEO) Director
(c)Address Block no. 484,502,503 A, 504, 505, NH 8, Palsana, Dist Surat, Gujarat.,,Palsana,Surat,Gujarat-394315
(d)Pin code 394315
(e)E-mail env@spectrumdyes.com
(f)STD Code. 0(f)Telephone No. 0
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
Minor Activity
(b)Category A
(c)Proposal Number IA/GJ/IND2/79313/2017
(d)Master Proposal Number(Single Window) SW/79128/2018
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Block no-484, 502, 503-A , 504 & 505
(b)Pincode 394315
(c)Bounded Latitudes (North)
From
Degree 21.094666
Minutes
Second
From
Degree 21.095960
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 72.975479
Minutes
Second
From
Degree 72.975636
Minutes
Second
(e)Survey of India Topo Sheet No. F43M16/F43N4,(46C/16,46G/4)
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 19.51
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 0
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Gujarat
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number J-11011/36/2003-IA-II(II)
(c)Date of Issue of TOR 09 Dec 2017
(f)Previous TOR Letter Copy of Previous TOR letter
(b)Date of Apply of EC 01 Oct 2018
(c)Date of Issue of EC 09 May 2019
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :18 Apr 2018
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :25 May 2018
Distance of Public Hearing Venue from the Proposed Project :1.6
Late Shree Chhotubhai Dayalji Desai hall, Behind Post Office, Palsana Main Road
State :Gujarat
District :Surat
Tehsil :Chorasi
Village :Palsana
11626 Verbal Issues Raised During Public Hearing & 25 Written Issued before public hearing through GPCB. Reply for both type of queries given in PH Proceedings. Attached herewith as well as Annexure-XLIIOthers
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Bhopal
(iii)Letter No. 5-77/2004(ENV)/448
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Jul 20 2018 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Dispersing Agent150001500OthersMT/MonthRoad
(2.)Dyes Intermediate400350750OthersMT/MonthRoad
(3.)S.O dyes250650900OthersMT/MonthRoad
(4.)Formulated SO dyes024002400OthersMT/MonthRoad
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Boiler6 TPH Running + 4 TPH stand by10 TPH Running + 6 TPH Stand By10 TPH Running + 6 TPH Stand By4 TPH will be resale
(2.)Spray DryerExisting 6 Nos.Proposed 1 Nos.Total 7 Nos.
(3.)Effluent Treatment Plant1 MLD2.5 MLD2.5 MLDModification and up gradation in existing
(4.)HAG1 Nos - 4000 U1 Nos - 3000 U1 Nos – 4000U 1 Nos - 3000 U
(5.)Thermopack1 Nos. 2,00,000 Kcal/hr, 1 Nos. 3,00,000 Kcal/hr01 Nos. 2,00,000 Kcal/hr, 1 Nos. 3,00,000 Kcal/hr
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 28 Aug 2015
(iv)Valid Upto 21 Oct 2019
(v)File No. AWH/ 80897 & GPCB/CCA-SRT-123(12)/ID_21392/371557
(vi)Application No. 100571
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 47.58
(b) Funds Allocated for Environment Management (Capital) (in Crores) 31.56
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.92
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 11.65
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 40068
(b)Existing quantity of raw material/fuel 24207
(c)Total quantity of raw material/fuel 64275
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Sulfuric Acid5256Tons per AnnumLocal MarketRoad50 OthersRM AnnexureCopy of Linkage
(2.)Naphthalene6420Tons per AnnumLocal MarketRoad50 OthersRM AnnexureCopy of Linkage
(3.)Acetic Acid2556Tons per AnnumLocal MarketRoad50 OthersRM AnnexureCopy of Linkage
(4.)Caustic Lye (100%)4512Tons per AnnumLocal MarketRoad50 OthersRM AnnexureCopy of Linkage
(5.)Dimethylformamide (DMF)1536Tons per AnnumLocal MarketRoad50 OthersRM AnnexureCopy of Linkage
(6.)Coal27375Tons per AnnumLocal MarketRoad50 OthersRM AnnexureCopy of Linkage
(7.)Methanol3120Tons per AnnumLocal MarketRoad300 OthersRM AnnexureCopy of Linkage
(8.)Oleum7380Tons per AnnumLocal MarketRoad50 OthersRM AnnexureCopy of Linkage
(9.)Phenol1140Tons per AnnumLocal MarketRoad300 OthersRM AnnexureCopy of Linkage
(10.)ammonia864Tons per AnnumLocal MarketRoad50 OthersRM AnnexureCopy of Linkage
(11.)HCl (30% Solution)8304Tons per AnnumLocal MarketRoad50 OthersRM AnnexureCopy of Linkage
(12.)Soda ash1224Tons per AnnumLocal MarketRoad100 OthersRM AnnexureCopy of Linkage
(13.)Sodium Acetate3840Tons per AnnumLocal MarketRoad100 OthersRM AnnexureCopy of Linkage
(14.)Ethylene Oxide744Tons per AnnumLocal MarketRoad50 OthersRM AnnexureCopy of Linkage
(15.)1,4- DI HYDROXYANTHRAQUINONE84Tons per AnnumLocal MarketRoad50 OthersRM AnnexureCopy of Linkage
(16.)Formaldehyde4332Tons per AnnumLocal MarketRoad50 OthersRM AnnexureCopy of Linkage
(17.)NG460OthersSCM/hrLocal MarketOthersPipeline100 OthersRM AnnexureCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Oct 2017 To 31 Dec 2017
(b)Season Winter
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM2.5Micro Gram per Meter Cube34.7029.3033.5060
(2.)SO2Micro Gram per Meter Cube19.6014.3017.1880
(3.)OtherscoMicro Gram per Meter Cube540.0230.0345.732000
(4.)NOxMicro Gram per Meter Cube24.1017.1020.8280
(5.)PM10Micro Gram per Meter Cube65.2056.2062.93100
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHmg/l7.276.726.58.5
(2.)TSSmg/l235100300
(3.)Fluoridemg/l0000
(4.)Chloridesmg/l545602501000
(5.)OthersCODmg/l16.08.01001000
(6.)Total Hardnessmg/l231138300600
(7.)TDSmg/l14485405002000
    14.3.     No. of Surface Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)OthersTDSmg/l1088238A
(2.)pHOtherspH Unit7.56.8A
(3.)DOmg/l6.906.0A
(4.)CODmg/l968A
(5.)BODmg/l303A
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))61.6054.2070
(2.)Leq(Day)A-weighted decibels(dB(A))68.8060.1075
    14.5.     No. of Soil Sample Monitored locations : 3
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pHOtherspH unit7.87.5
(2.)P(Phosphorus)Milligram per Kilogram00
(3.)Electric ConductivityOthersNA00
(4.)N(Nitrogen)Milligram per Kilogram6050
(5.)K(Potassium)Milligram per Kilogram00
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 10.85 To 2.84
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 3 To 5
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater27000Copy of Permission LetterPipelineTube Well21-4/3481/GJ/IND/2018 - Existing + Proposed27 Jan 20182700
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Processing18751875ETPOthersCETP01875
(2.)floor & drum washing2525ETPOthersCETP025
(3.)Domestic7575ETPOthersCETP075
(4.)Boiler & Cooling270270ETPOthersCETP0270
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 2245
(b)Total Discharged Water (Kilolitre per Day) 2245
(c)Total Reused Water (Kilolitre per Day) 0
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)ETP sludgeHazardous Waste (as per Hazardous and Other Waste Management rules 2016)15000Tons300RoadTreatment, Storage and Disposal Facility(TSDF)
(2.)Discarded containerHazardous Waste (as per Hazardous and Other Waste Management rules 2016)60000Tons50RoadAuthorized Recyclers
(3.)used oilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1.8Tons50RoadAuthorized Recyclers
(4.)process wasteIndustrial Waste60Tons100RoadOthersCHWIF
(5.)distillation residueIndustrial Waste2100Tons100RoadOthersCHWIF
(6.)gypsumIndustrial Waste6000Tons300RoadCo-Processing
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM2.5Microgram per Meter Cube63.621.50.1363.7560
(2.)NOxMicrogram per Meter Cube19.051.50.02519.07580
(3.)SO2Microgram per Meter Cube15.711.50.0515.7680
(4.)PM10Microgram per Meter Cube63.621.50.1363.75100
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)10 TPH boiler + HAGcoal / Lignight361PM101.13
(2.)10 TPH boiler + HAGcoal / Lignite361SO20.87
(3.)DD plant scrubberNA60.2OthersHCL0.0022
(4.)10 TPH boiler + HAGcoal/Lignite361NOx0.43
(5.)spray dryer 9steam(HAG)331.2PM100.9
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 6000
(b)Source DGVCL
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 6760 KVA
(e)Stack Height (in m) 11
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 4.98
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 4.98
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 25307.34
(b)Waste/Barren Land (ha.) 1955.61
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 173.79
(e)Settlements (ha.) 1725.87
(f)Industrial (ha.) 2255.75
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : N.A 0
    Total (ha.) 31418.36
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Green belt1.02
(2.)Main Plant3.96
Total (ha.) 4.98
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Wildlife CorridorsN.A0N.A
(2.)CorridorsN.A0N.A
(3.)Critically Polluted AreaN.A0N.A
(4.)WLSNA0N.A
(5.)NPAN.A0N.A
(6.)ESAsN.A0N.A
(7.)ESZsN.A0N.A
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestN.A0N.A
(2.)Archaeological SitesN.A0N.A
(3.)Defence InstallationsN.A0N.A
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 4.98
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 100% land acquired
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area Mindhola river, 2.6 KM
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 122
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 0
(e)No. of working days 365
(f)Total Manpower 122
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt9017.901167.1010184
(2.)Funds Allocated10515
(3.)No. of Plants12503501600
(4.)Percentage of Total Project Area203151
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)Social• Promoting Education, including Special Education and Employment Enhancing Vocation Skills Especially among Children, Women, Elderly, and the Differently-Able and Livelihood Enhancement Projects. • Improve the Poverty and Malnutrition, Promoting Preventive Health Care and Sanitation and making available Safe Drinking Water.
(2.)FinancialThe company shall earmarks fund up to 91.53 lacs for Proposed CSR activity for 5 year The proposed green belt will enhance the aesthetic beauty of the surrounding environment and Rs. 15.0Lacs fund is allocated for 5 years greenbelt development plan
(3.)Environmental• Ensuring Environmental Sustainability, Ecological Balance, Protection of Flora and Fauna, Animal Welfare, Agro-forestry, Conservation of Natural Resources and Maintaining Quality of Soil, Air and Water.
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1720/RA 0099
(ii)Name of the EIA Consultant EN-VISION ENVIRONMENTAL SERVICES
(iii)Address 201,301, UTC BUILDING, NR.APPLE HOSPITAL, UDHNA DARWAJA, 395002-SURAT
(iv)Mobile No. 9428001891
(v)Landline No. 0261234477
(vi)Email Id eia@en-vision.co.in
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 01 Dec 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NA- Please submit legible copy of the CCR for the EC dated 1/4/2004. - Entry at item 6 of the Form-2 shows details as Nil, which needs to be rectified. - Status of clearance required for ground water withdrawal to meet the requirement for the present industrial operations. 23 Sep 2018
2.NAThe correction have been made as per the instruction received 24 Sep 2018
3.NAOur queries dated 23/9/2018 are yet to be addressed. Further, please clarify about the CTO obtained for the production capacity higher than the EC capacity of 250 TPM. 29 Sep 2018
4.NAThe correction have been made as per the instruction received 01 Oct 2018
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterWith Reference to MOM of 1st EAC (Industry-2) Meeting dated 19-20 Dec 2018 , we hereby submit the Compliance of Online ADS Generated dated 02nd Jan 2019 as per attached. 09 Jan 2019
2.NADeferred 02 Jan 2019
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantAvneep Bansal
DesignationDirector
Name of Company (Applicant Name should not be given here)SPECTRUM DYES AND CHEMICALS PVT. LTD.
AddressBlock no. 484,502, 503 A, 504 & 505. NH-8, Palsana, Dist: Surat, Gujarat.
Print