Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Proposed Establishment of Synthetic Organic Chemicals, Intermediates and Specialty Chemicals by Reshmika Minerals and Chemicals Private Limited Plot No 23 GIDC Industrial Estate Panoli
(b)Name of the Company / Organisation RESHMIKA MINERALS & CHEMICALS PRIVATE LIMITED
(c)Registered Address Plot No. 23, Panoli GIDC, Dist. Bharuch, Gujarat,,Bharuch,Gujarat-394116
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Sunil Vanarse Vanarse
(b)Designation (Owner/ Partner/ CEO) Director
(c)Address Plot No.23, Panoli GIDC, Dist. Bharuch, Gujarat,,Anklesvar,Bharuch,Gujarat-394116
(d)Pin code 394116
(e)E-mail puranikravi@gmail.com
(f)STD Code. 20(f)Telephone No. 66260000
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(b) Pesticides industry and pesticide specific intermediates (excluding formulations)
Minor Activity5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
(b)Category A
(c)Proposal Number IA/GJ/IND2/79285/2017
(d)Master Proposal Number(Single Window) SW/79283/2018
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Plot No 23 GIDC Industrial Estate Panoli Ankleshwa
(b)Pincode 394116
(c)Bounded Latitudes (North)
From
Degree 21.32
Minutes
Second
From
Degree 21.32
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 72.59
Minutes
Second
From
Degree 73.00
Minutes
Second
(e)Survey of India Topo Sheet No. F43M14 F43M15 F43N2 F43N3
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 34
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 6.6
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Gujarat
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)GujaratMahesanaKadiDangarwa
(2.)GujaratBharuchAnklesvarPanoli
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number IA-J-11011/535/2017-IA-II(I)
(b)Date of Apply of TOR 04 Nov 2017
(c)Date of Issue of TOR / Standard ToR 22 Mar 2018
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason As per EIA notification 2006 proposed project is w
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Reactor Columns Storage Tanks BoilersWill be installedNo
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Propiophenone50OthersTon per month (TPM)Road
(2.)4-Nitro-o-Xylene500OthersTon per month (TPM)Road
(3.)3-Nitro-o-Xylene600OthersTon per month (TPM)Road
(4.)1,3-Dimethyl-2-Nitrobenzene20OthersTon per month (TPM)Road
(5.)2,4-Dimethyl-1-Nitrobenzene80OthersTon per month (TPM)Road
(6.)2,6-Xylidine (2,6 –Dimethyl Aniline)10OthersTon per month (TPM)Road
(7.)2,4-Xylidine (2,4 – Dimethyl Aniline)40OthersTon per month (TPM)Road
(8.)1-Octanoic acid300OthersTon per month (TPM)Road
(9.)Di-Ethyl Ketone (DEK)250OthersTon per month (TPM)Road
(10.)N-(1-Ethylpropyl)-3,4-Xylidine500OthersTon per month (TPM)Road
(11.)Phenyl ethyl alcohol200OthersTon per month (TPM)Road
(12.)Phenyl acetaldehyde20OthersTon per month (TPM)Road
(13.)Phenyl ethyl acetate20OthersTon per month (TPM)Road
(14.)Methyl Ethyl Ketone5OthersTon per month (TPM)Road
(15.)Dilute Sulfuric acid230OthersTon per month (TPM)Road
(16.)3,4-Xylidine (3,4 –Dimethyl Aniline)100OthersTon per month (TPM)Road
(17.)Dilute nitric acid800OthersTon per month (TPM)Road
(18.)2-Cynophenol100OthersTon per month (TPM)Road
(19.)Phenyl acetaldehyde di-methylacetal20OthersTon per month (TPM)Road
(20.)Styrene oxide200OthersTon per month (TPM)Road
(21.)Phenyl ethyl alcohol methyl ether50OthersTon per month (TPM)Road
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 28 Jan 2016
(iv)Valid Upto 05 Oct 2020
(v)File No. GPCB/ANK/CCA-1305/ID-33963/342932
(vi)Application No. 99715
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 130
(b) Funds Allocated for Environment Management (Capital) (in Crores) 7.75
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.975
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 1.35
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 0
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 0
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Raw material0OthersTon per month (TPM)Imported, LocalRoad0 LinkageCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Mar 2018 To 31 May 2018
(b)Season Summer
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube95.380.595100
(2.)SO2Micro Gram per Meter Cube22.31022.180
(3.)OthersCOMili Gram per Meter Cube1.390.91.44
(4.)NOxMicro Gram per Meter Cube28.61628.280
(5.)PM2.5Micro Gram per Meter Cube43.128.442.860
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA7.927.928.58.5
(2.)Total Hardnessmg/l162162200600
(3.)Chloridesmg/l2802802501000
(4.)Fluoridemg/l0011.5
(5.)OthersSulphidemg/l000.050.05
(6.)TSSNA0000
(7.)TDSmg/l3803805002000
(8.)Heavy MetalsLeadmg/l000.010.01
    14.3.     No. of Surface Water monitoring locations : 7
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA8.318.31E
(2.)BODmg/l2020E
(3.)CODmg/l00E
(4.)DOmg/l6.16.1E
(5.)OthersTDSmg/l150150E
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))68.668.670
(2.)Leq(Day)A-weighted decibels(dB(A))73.173.175
    14.5.     No. of Soil Sample Monitored locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pHOthersNA7.787.78
(2.)N(Nitrogen)Percent3.363.36
(3.)P(Phosphorus)Kilogram per hectare26.1626.16
(4.)K(Potassium)Kilogram per hectare310310
(5.)Electric ConductivityMillisiemens per Centimetre308.2308.2
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 2 To 5
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 2 To 5
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Othersfrom GIDC913.50Copy of Permission LetterPipelineOthersfrom GIDC pipeline018 Sep 2018913.5
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic & Industrial165165ETP RO MEEReuse within the Plant & Recycling165
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 165
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 165
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Waste paper, corrugated boxesMunicipal Solid Waste1Tons0RoadOthersSale to scrap dealer or recycler
(2.)Metal scrapMunicipal Solid Waste3Tons0RoadOthersSale to scrap dealer or recycler
(3.)Used CatalystHazardous Waste (as per Hazardous and Other Waste Management rules 2016)15Tons0RoadOtherssolid waste facility or use for brick
(4.)Used or Spent Catalyst (Transition metal)Hazardous Waste (as per Hazardous and Other Waste Management rules 2016)5Tons0RoadOthersauthorized supplier for reactivation
(5.)Chemical sludge from ETPHazardous Waste (as per Hazardous and Other Waste Management rules 2016)100Tons0RoadTreatment, Storage and Disposal Facility(TSDF)
(6.)Used Empty Barrels or LinersHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1000Tons0RoadAuthorized Recyclers
(7.)Plastic wasteMunicipal Solid Waste2Tons0RoadOthersSale to scrap dealer or recycler
(8.)Wooden wasteMunicipal Solid Waste2Tons0RoadOthersSale to scrap dealer or recycler
(9.)Discarded container bags or LinersHazardous Waste (as per Hazardous and Other Waste Management rules 2016)16.03Tons0RoadOthersdecontamination and reuse
(10.)Process waste or Distillation column residueHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1140Tons0RoadTreatment, Storage and Disposal Facility(TSDF)
(11.)Used or spent OilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)2Tons0RoadOtherssale to registered refiners
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)SO2Microgram per Meter Cube15.81.2015.880
(2.)NOxMicrogram per Meter Cube21.71.20.221.980
(3.)PM2.5Microgram per Meter Cube00000
(4.)PM10Microgram per Meter Cube87.11.20.387.4100
(5.)Others(Specify)NANA00000
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)3 Hot oil generatorNatural gas 1384301PM100.3
(2.)2 High temp hot oil generatorNatural gas 388300.5PM100.3
(3.)3 BoilersNatural gas 676300.8PM100.3
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 1275
(b)Source DGVCL
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 1 no 315 KVA DG 3 no of 500 KVA DG
(e)Stack Height (in m) 6
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 8.963272
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 8.963272
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 0
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 8.963272
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : NA 0
    Total (ha.) 8.963272
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Main Plant8.963272Total plot area
(2.)Green belt2.942043Within plot & adjacent lease area
Total (ha.) 11.905315
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)WLSNot applicable0Not applicable
(2.)ESZsNot applicable0Not applicable
(3.)Wildlife CorridorsNot applicable0Not applicable
(4.)CorridorsNot applicable0Not applicable
(5.)Critically Polluted AreaNot applicable0Not applicable
(6.)ESAsNot applicable0Not applicable
(7.)NPANot applicable0Not applicable
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestNot applicable0Not applicable
(2.)Defence InstallationsNot applicable0Not applicable
(3.)OthersNot applicableNot applicable0Not applicable
(4.)Archaeological SitesNot applicable0Not applicable
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area Kharod lake
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 58
(c)Temporary Employment- During Construction 30
(d)Temporary Employment- During Operation 70
(e)No. of working days 6
(f)Total Manpower 158
32.
Green Belt in Ha:
(a)Total Area of Green Belt 3.04184
(b)Percentage of Total Project Area 33.94
(c)No. of Plants to be Planted 400
(d)Funds Allocated for Plantation 30
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialLocal employment, Social upliftment in nearby area through CER
(2.)FinancialProject will help possibilities of export
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. Sr no 5 of NABET accredited consultant list
(ii)Name of the EIA Consultant Adity Environmental services Pvt Ltd
(iii)Address 107 Hiren Light Industrial estate Mahim Mumbai
(iv)Mobile No. 9821513367
(v)Landline No. 0224212750
(vi)Email Id rajiv@aespl.co.in
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 18 Sep 2018
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAThe project/activity is covered under category B of item 5(f) of the schedule to the EIA Notification, 2006 and requires appraisal/approval at the State level by the concerned SEAC/SEIAA. Please submit your proposal accordingly. 23 Sep 2018
2.NAThe correction have been made as per the instruction received 12 Nov 2018
3.NAIn continuation to our earlier observations,please clarify whether the proposed products identified under category A of item 5(b) are technical grade pesticides. Also, different products (total quantum-3060 TPM) need to be mentioned separately under item 5(b) & 5(f) for actual categorization of the project in terms of the provisions of the EIA Notification, 2006. 20 Nov 2018
4.NAThe correction have been made as per the instruction received 28 Nov 2018
5.NACategory A of item 5(b) of the schedule to the EIA Notification, 2006 covers the units producing technical grade pesticides. In view of the clarifications provided, how the project is justified under category A. 07 Dec 2018
6.NAThe correction have been made as per the instruction received 14 Dec 2018
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantSunil Vanarse Vanarse
DesignationDirector
Name of Company (Applicant Name should not be given here)RESHMIKA MINERALS & CHEMICALS PRIVATE LIMITED
AddressPlot No. 23, Panoli GIDC, Dist. Bharuch, Gujarat