Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Proposed modification of 0.4 MTPA Integrated steel plant of M/s Gagan Ferrotech Ltd to 0.3 MTPA Integrated steel plant by changing 1x35 T EAF to 1x350 TPD DRI Kiln & 2x20 T IF
(b)Name of the Company / Organisation M/s Gagan Ferro Tech Limited
(c)Registered Address 4/19-21, Suhatta Complex, City Centre, Durgapur-16. Burdwan,West Bengal,Burdwan,West Bengal-743216
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Vinay Kumar Agarwal
(b)Designation (Owner/ Partner/ CEO) MD
(c)Address A/7, Armstrong Avenue, Sector 2B,Bidhannagar,Durgapur-713212,Kanksa,Burdwan,West Bengal-713216
(d)Pin code 713216
(e)E-mail suv_vinay@yahoo.co.in
(f)STD Code. 343(f)Telephone No. 2543986
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity3(a) Metallurgical industries (ferrous & non ferrous)
Minor Activity
(b)Category A
(c)Proposal Number IA/WB/IND/22096/2010
(d)Master Proposal Number(Single Window) SW/78776/2018
(e)EAC concerned (for category A Projects only) Industrial Projects - 1
(f)Project Type Modernization
4.
Location of the Project:
(a)Plot/Survey/Khasra No. 5,5/1671,5/1673,5/1675,5/1676,5/1679,11/1613,31,35
(b)Pincode 713336
(c)Bounded Latitudes (North)
From
Degree 234124.03
Minutes
Second
From
Degree 234147.87
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 870657.29
Minutes
Second
From
Degree 870704.59
Minutes
Second
(e)Survey of India Topo Sheet No. F45D2
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 105
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 5.81
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project West Bengal
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number J-11011/232/2010-IA-II(I)
(c)Date of Issue of TOR 15 Sep 2010
(f)Previous TOR Letter NA
(b)Date of Apply of EC 01 Oct 2018
(c)Date of Issue of EC 17 May 2019
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :05 May 2018
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :06 Jun 2018
Distance of Public Hearing Venue from the Proposed Project :2.0
Kazi Nazrul Satabarsiki Hall
State :West Bengal
District :Burdwan
Tehsil :Kanksa
Village :Jamuria
72Plantation Drive, Pollution Abatement Measures, Employment Opportunity, Implementation of CSR ActivitiesOthersDMDC
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Bhubaneswar
(iii)Letter No. 102-362/EPE/2877
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Aug 25 2018 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)1.0.10.30OthersMillion Tons Per AnnumRoad,Rail
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)SAF2X9 MVA02X9 MVA
(2.)EAF0001 X 35 T Accorded in EC will be dropped
(3.)Rolling Mill342 TPD1000 TPD1000 TPD
(4.)AOD1X30 T01X30 T
(5.)CCM2 X 3 Strand02 X 3 Strand
(6.)DRI Kilns4X100 TPD1X350 TPD750 TPD
(7.)Induction Furnace3x20 T2X20 T5X20 T
(8.)CPP(AFBC)16 MW08 MWEC was taken for 16 MW which will be reduced to 8 MW
(9.)CPP (WHRB)8 MW8 MW16 MW
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 19 Jun 2018
(iv)Valid Upto 30 Jun 2023
(v)File No. 1441/WPB/Red/(Bwn/Cont(532)/06)
(vi)Application No. CO110117
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 100
(b) Funds Allocated for Environment Management (Capital) (in Crores) 4.0
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 1.0
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.402
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 1074500
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 1074500
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Coal678500Tons per AnnumSouth Africa & Dhamra portRail350 Open MarketCopy of Linkage
(2.)Iron ore396000Tons per AnnumBarbilRail300 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Nov 2017 To 31 Jan 2018
(b)Season Winter
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube1037398.1100
(2.)SO2Micro Gram per Meter Cube24.613.824.180
(3.)NOxMicro Gram per Meter Cube33.521.333.480
(4.)OthersCOMicro Gram per Meter Cube689407687.82000
(5.)PM2.5Micro Gram per Meter Cube55.142.054.560
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TDSmg/l4063505002000
(2.)Chloridesmg/l30162501000
(3.)Fluoridemg/l0.050.0111.5
(4.)TSSmg/l0000
(5.)Heavy MetalsHgmg/l0.00050.00010.0010.002
(6.)Total Hardnessmg/l1801442001000
(7.)OthersAlkalinitymg/l192154200600
(8.)pHNA7.67.216.58.5
    14.3.     No. of Surface Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA7.56.9C
(2.)CODmg/l00C
(3.)DOmg/l7.46.8C
(4.)BODmg/l4.82.4C
(5.)OthersTDSmg/l220174C
    14.4.     No. of Ambient Noise monitoring locations : 7
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))44.140.245
(2.)Leq(Day)A-weighted decibels(dB(A))534855
    14.5.     No. of Soil Sample Monitored locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pHOthersNA7.46.9
(2.)K(Potassium)Percent0.150.10
(3.)N(Nitrogen)Percent0.240.19
(4.)P(Phosphorus)Percent0.210.14
(5.)Electric ConductivityOthersmmhos/cm260202
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 2.23 To 4.23
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 1.82 To 2.3
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Surface10770Copy of Permission LetterPipelineOthersJamuria Municipality441/JM20 Mar 20121500
(2.)Surface10770Copy of Permission LetterPipelineOthersJamuria Municipality441/JM20 Mar 20121500
(3.)Surface10770Copy of Permission LetterPipelineOthersJamuria Municipal Supply441/JM20 Mar 20121500
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Industrial28862886Precipitation, Coagulation, Settlement & Filteration with Sludge separationReuse within the Plant & Recycling2886
(2.)Domestic9090Biological TreatmentGreen Belt Renewal Plant90
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 2976
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 2976
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)IF slagIndustrial Waste40000Tons0.3RoadOthersRoad construction & Filling low areas
(2.)DRI KilnFly Ash40000Tons4.73RoadOthersFilling OCP of ECL Mines
(3.)Used GreaseHazardous Waste (as per Hazardous and Other Waste Management rules 2016)0.5Tons170RoadAuthorized Recyclers
(4.)DolcharIndustrial Waste72000Tons0Conveyor BeltOthersUsed in Power Plant
(5.)Power PlantBottom Ash24360Tons4RoadAuthorized Recyclers
(6.)Fe-Mn SlagIndustrial Waste24700Tons0Conveyor BeltCo-Processing
(7.)Si-MnIndustrial Waste13800Tons0.3RoadOthersRoad Construction
(8.)Metal ScrapsIndustrial Waste20000Tons0Conveyor BeltCo-Processing
(9.)Oily SludgeHazardous Waste (as per Hazardous and Other Waste Management rules 2016)0.04Tons170RoadAuthorized Recyclers
(10.)Used oilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)0.062Tons170RoadAuthorized Recyclers
(11.)Power PlantFly Ash36540Tons4RoadAuthorized Recyclers
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube98.14.110.01298.11100
(2.)PM2.5Microgram per Meter Cube54.54.160.0154.5160
(3.)NOxMicrogram per Meter Cube33.44.11033.480
(4.)SO2Microgram per Meter Cube24.17.324.5148.6180
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)2 X 20 IFElectricity301.8OthersTSP2.34 g/s
(2.)Proposed 8 MW CPP to be connected to existing CPPCoal, Dolchar401.5OthersTSP0.54 g/s
(3.)350 TPD DRI KilnCoal421.5OthersTSP1.5 g/s
(4.)350 TPD DRI KilnCoal421.5SO29.75 g/s
(5.)2 X 9 MVA SAFElectricity & Coke301.6OthersTSP2.8 g/s
(6.)Proposed 8 MW CPP to be connected to Existing CPPCoal, Dolchar401.5SO28.67 g/s
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 48
(b)Source CPP & DVC
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 2 X 500 KVA
(e)Stack Height (in m) 14
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 18.85
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 18.85
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 15636
(b)Waste/Barren Land (ha.) 4978
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 2467
(e)Settlements (ha.) 3952
(f)Industrial (ha.) 5054
(g)Forest (ha.) 646
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Transportation 778
    Total (ha.) 33511
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Green belt6.22
(2.)Water Reservoir0.32
(3.)OthersInternal Roads and Administrative building1.09
(4.)Main Plant11.22Land Already Acquired
Total (ha.) 18.85
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)NPANil00
(2.)ESAsNil00
(3.)Wildlife CorridorsNil00
(4.)Critically Polluted AreaNil00
(5.)ESZsNil00
(6.)WLSNil00
(7.)CorridorsNil00
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestNil00
(2.)Archaeological SitesNil00
(3.)Defence InstallationsNil00
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 18.85
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired Acquired
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Ajay River
(ii)Direction of Water Bodies in Buffer Area North
(iii)Distance of Water Bodies in Buffer Area 7.0
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 30
(b)Permanent Employment-During Operation 40
(c)Temporary Employment- During Construction 90
(d)Temporary Employment- During Operation 90
(e)No. of working days 320
(f)Total Manpower 250
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt5.31.326
(2.)Percentage of Total Project Area28.117.035
(3.)No. of Plants766617009366
(4.)Funds Allocated83.3911
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialEmployment Generation, Infrastructure development
(2.)EnvironmentalAfforestation
(3.)FinancialRevenue generation & Economic development
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 1
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. 77
(ii)Name of the EIA Consultant Global Tech Enviro Experts Pvt Ltd
(iii)Address C-23, BJB Nagar Bhubaneswar
(iv)Mobile No. 9438033487
(v)Landline No. 0674243685
(vi)Email Id global1experts@gmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 1
(ix)Validity of Accreditation 23 Nov 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAYou are requested to confirm whether the public hearing was presided by the rank not less than Additional District Magistrate as per the provisions of EIA Notification. 25 Sep 2018
2.NAThe correction have been made as per the instruction received 01 Oct 2018
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantVinay Kumar Agarwal
DesignationMD
Name of Company (Applicant Name should not be given here)M/s Gagan Ferro Tech Limited
Address4/19-21, Suhatta Complex, City Centre, Durgapur-16. Burdwan