Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Expansion for development and production of Uber-2 well and Group Gathering Station, Jambusar, Gujarat
(b)Name of the Company / Organisation ONGC
(c)Registered Address NIL
(d)Legal Status of the Company NIL
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant
(b)Designation (Owner/ Partner/ CEO) ChiefGeneralManager
(c)Address NIL
(d)Pin code 110070
(e)E-mail kumar_rajeeva@ongc.co.in
(f)STD Code. (f)Telephone No.
(g)Fax No. 26129067
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity1(b) Offshore and onshore oil and gas exploration, development & production
Minor Activity1(b) Offshore and onshore oil and gas exploration, development & production
(b)Category A
(c)Proposal Number IA/GJ/IND2/64683/2017
(d)Master Proposal Number(Single Window) SW/78778/2018
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. S/No.939
(b)Pincode 392180
(c)Bounded Latitudes (North)
From
Degree 22.1633333
Minutes
Second
From
Degree 22.19527778
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 72.73527778
Minutes
Second
From
Degree 72.77416667
Minutes
Second
(e)Survey of India Topo Sheet No. F43G12
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 6.25
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 1
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Gujarat
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)GujaratBharuchJambusar
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number IA-J-11011/227/2017-IA-II(I)
(c)Date of Issue of TOR 22 Mar 2018
(f)Previous TOR Letter Copy of Previous TOR letter
(b)Date of Apply of EC 22 Nov 2018
(c)Date of Issue of EC 06 Mar 2019
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :24 Jul 2018
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :28 Aug 2018
Distance of Public Hearing Venue from the Proposed Project :2.5
Sarod
State :Gujarat
District :Bharuch
Tehsil :Jambusar
Village :Sarod
53CSR activites, Air pollution, development of Sarod villageOthers
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Bhopal
(iii)Letter No. 5-31/2009(ENV)/990
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Sep 4 2017 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)HYDROCARBON GAS04000040000Cubic Meter per DayOthersPipeline
(2.)CONDENSATE02121Cubic Meter per DayOthersPipeline
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)00000
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 22 Mar 2018
(iv)Valid Upto 22 Mar 2018
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 29.50
(b) Funds Allocated for Environment Management (Capital) (in Crores) 0.02
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.9
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.02
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 3600
(b)Existing quantity of raw material/fuel 0
(c)Total quantity of raw material/fuel 3600
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)diesel3600OthersLitresBase office at ankleshwarOthersTankers85 OthersOwn sourceCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 06 Mar 2018 To 26 May 2018
(b)Season Summer
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube783772100
(2.)SO2Micro Gram per Meter Cube10.64.01080
(3.)NOxMicro Gram per Meter Cube27.69.024.180
(4.)PM2.5Micro Gram per Meter Cube55144960
    14.2.     No. of Ground Water monitoring locations : 2
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA7.797.156.58.5
(2.)Total Hardnessmg/l31021010600
(3.)Chloridesmg/l2802502501000
(4.)Heavy MetalsLeadmg/l000.050
(5.)TSSmg/l0000
(6.)TDSmg/l153014605002000
(7.)Fluoridemg/l0.420.4211.5
    14.3.     No. of Surface Water monitoring locations : 2
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA8.118.01C
(2.)DOmg/l5.75.5A
(3.)BODmg/l1.31.2A
(4.)CODmg/l1211A
    14.4.     No. of Ambient Noise monitoring locations : 5
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))53.640.855
(2.)Leq(Day)A-weighted decibels(dB(A))70.648.465
    14.5.     No. of Soil Sample Monitored locations : 5
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)Electric ConductivityMillisiemens per Centimetre870190
(2.)K(Potassium)Milligram per Kilogram7521.2
(3.)pHOthersNA7.637.22
(4.)P(Phosphorus)Milligram per Kilogram18.215.3
(5.)N(Nitrogen)Milligram per Kilogram116113
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 10 To 5
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 2 To 5
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersTankers2510Copy of Permission LettermodeOthersTankersOthersNA-22 Mar 201825
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)NA00NAOthersNA00
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 0
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 0
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)NAOthersNA0Tons0OthersNAOthersNA
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)SO2Microgram per Meter Cube6.32237.21.1257.45480
(2.)NOxMicrogram per Meter Cube14.91237.254.369.2180
(3.)PM10Microgram per Meter Cube58.29237.21.7760.065100
(4.)PM2.5NA00000
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)DG setDiesel30.254NOx1.2778
(2.)DG setDiesel30.254SO20.0265
(3.)DG setDiesel30.254PM100.0417
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 125
(b)Source DG Sets
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 125
(e)Stack Height (in m) 3
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 0
(c)Government Land (ha.) 1078
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 1078
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 436934.1
(b)Waste/Barren Land (ha.) 101321.3
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 118373.3
(e)Settlements (ha.) 0
(f)Industrial (ha.) 0
(g)Forest (ha.) 200.9
(h)Mangroves (ha.) 6625.4
(i)Marine Area (ha.) 76894 .2
(j)Others (ha.) : salt pan 16251.7
    Total (ha.) 756598
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Otherswell site1078
Total (ha.) 1078
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNA0NA
(2.)WLSNA0NA
(3.)CorridorsNA0NA
(4.)Wildlife CorridorsNA0NA
(5.)ESAsNA0NA
(6.)ESZsNA0NA
(7.)NPANA0NA
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestNA0NA
(2.)Archaeological SitesNA0NA
(3.)Defence InstallationsNA0NA
(4.)OthersNANA0NA
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) Not Applicable
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 1078
(b)Land yet to be acquired(Ha) 0.0
(c)Status of Land acquisition if not acquired 0.0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Yet To Start
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species Pea Fowl
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area Mahi River
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 7
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 8
(e)No. of working days 365
(f)Total Manpower 15
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt000
(2.)Percentage of Total Project Area000
(3.)No. of Plants000
(4.)Funds Allocated000
    33.       Project Benefits
S. No. Type of Project BenefitsDetails of Project Benefits
NIL
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? No
(i)Reason for not Hiring the Consultant ONGC is QCI NABET accredited for preparation of EIA Reports
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAForm-2 is not visible. Please see for the needful. 23 Sep 2018
2.NAThe correction have been made as per the instruction received 24 Sep 2018
3.NAPlease see our observations vide query dated 23/9/2018 for the needful. 29 Sep 2018
4.NAThe correction have been made as per the instruction received 01 Oct 2018
5.NAAs already informed, Form-2 is still not visible. Please look into it and do the needful. 04 Oct 2018
6.NAThe correction have been made as per the instruction received 05 Oct 2018
7.NAPlease clarify/inform the following:- - Data collection and EIA/EMP report prepared/submitted by M/s ONGC Ltd for their own project amounts to conflict of interest, and should have been avoided. - Earlier EC dated 14/11/2008 was only for exploratory drilling of ten wells. How the present project for development and production of one of the wells (Uber-2) qualifies under expansion category. 12 Oct 2018
8.NAThe correction have been made as per the instruction received 16 Oct 2018
9.NAPlease refer our earlier observations vide query dated 12/10/2018 and your response thereto. - Please provide details of ECs granted in favour of M/s ONGC Ltd to the projects for which EIA/EMP reports were prepared by M/s ONGC Ltd. - The proposal does not qualify under expansion category. 25 Oct 2018
10.NAThe correction have been made as per the instruction received 31 Oct 2018
11.NAIn response to our observations vide query dated 25/10/2018, no reply is found on the portal. 07 Nov 2018
12.NAThe correction have been made as per the instruction received 12 Nov 2018
13.NAPlease refer our earlier observations vide queries dated 12/10/2018 & 25/10/2018. As stated earlier, the proposal is for oil/gas development and production from one drilled well, and not admissible under expansion category. There are no details provided against column 6 of Form-2. Please see for correctness of other entries also in Form-2 for consideration of the proposal. 21 Nov 2018
14.NAThe correction have been made as per the instruction received 22 Nov 2018
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of Applicant
DesignationChiefGeneralManager
Name of Company (Applicant Name should not be given here)ONGC
AddressCorporate HSE, 8th Floor Core IV, SCOPE Minar, Delhi 10092
Print