Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Expansion of “Group Housing Scheme ‘Aarohan Residences’(19.244 Acres)under Mixed Landuse”at Sector 53, Gurugram- Manesar Urban Complex, District Gurugram, Haryana
(b)Name of the Company / Organisation VIPUL LIMITED
(c)Registered Address Vipul Limited, Vipul Tech Square, Golf Course Road, Sector 43, Gurgaon,,Gurgaon,Haryana-122009
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Ravinder Singh
(b)Designation (Owner/ Partner/ CEO) Authorized Signatory
(c)Address M/s. Vipul Limited, Vipul Tech Square, Golf Course Road, Gurgaon,,Gurgaon,Gurgaon,Haryana-122009
(d)Pin code 122009
(e)E-mail poonam_1972@rediffmail.com
(f)STD Code. 124(f)Telephone No. 4065500
(g)Fax No. 4061000
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity8(b) Townships and Area Development projects.
Minor Activity
(b)Category B1
   Reason for Applying at Ministry SEIAA
(c)Proposal Number IA/HR/MIS/78354/2018
(d)Master Proposal Number(Single Window) SW/78352/2018
(e)EAC concerned (for category A Projects only) INFRA-2
(f)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. 1672/3, 1690,1691/2, 1691/1, 1672/1/1, 1692, 1693,
(b)Pincode 122001
(c)Bounded Latitudes (North)
From
Degree 282603.1
Minutes
Second
From
Degree 282613.69
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 770550.7
Minutes
Second
From
Degree 770614.7
Minutes
Second
(e)Survey of India Topo Sheet No. H43X3
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 818
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 0.2109
(j)Seismic Zone 4
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Haryana
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number 21-108/2018-IA-III
(c)Date of Issue of TOR 15 Jun 2018
(f)Previous TOR Letter Copy of Previous TOR letter
(b)Date of Apply of EC 17 Oct 2018
(c)Date of Issue of EC 02 May 2019
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason 8(b) category project
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Chandigarh
(iii)Letter No. 16-45/2016(ENV)-RO(NZ)
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Jun 26 2018 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)403267.045208429.182194837.863403266Otherssquare meterOthersTownship project
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)401387.863 sqm208429.182 sqm192958.681 sqm401387 sqm
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto 02 Jan 1900
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 1549.76
(b) Funds Allocated for Environment Management (Capital) (in Crores) 3.87
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 5
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.695
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 253556
(b)Existing quantity of raw material/fuel 296444
(c)Total quantity of raw material/fuel 550000
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)cement9039Tons per AnnumLocal supplierRoad10 Open MarketCopy of Linkage
(2.)Structural Steel2839Tons per AnnumLocal supplierRoad10 Open MarketCopy of Linkage
(3.)Glass10933Tons per AnnumLocal supplierRoad10 Open MarketCopy of Linkage
(4.)Flyash Based products2997Tons per AnnumLocal supplierRoad10 Open MarketCopy of Linkage
(5.)Aggregate40997Tons per AnnumLocal supplierRoad10 Open MarketCopy of Linkage
(6.)Bricks2484Tons per AnnumLocal supplierRoad10 Open MarketCopy of Linkage
(7.)Sand9281Tons per AnnumLocal supplierRoad10 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 15 Dec 2016 To 15 Mar 2017
(b)Season Winter
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 5
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)NOxMicro Gram per Meter Cube30.112.520.380
(2.)OthersCOMicro Gram per Meter Cube2441.51662.92016.3NS
(3.)PM10Micro Gram per Meter Cube17353136100
(4.)SO2Micro Gram per Meter Cube11.188.780
(5.)PM2.5Micro Gram per Meter Cube83206260
    14.2.     No. of Ground Water monitoring locations : 5
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)Chloridesmg/l107262501000
(2.)pHNA7.326.9678.5
(3.)Fluoridemg/l0.710.1711.5
(4.)Heavy MetalsIronmg/l0.360.30.31
(5.)TSSmg/l2215
(6.)TDSmg/l3121445002000
(7.)Total Hardnessmg/l160110300600
    14.3.     No. of Surface Water monitoring locations : 2
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)CODmg/l5224D
(2.)BODmg/l178D
(3.)pHNA7.527.26D
(4.)DOmg/l4.13.9D
    14.4.     No. of Ambient Noise monitoring locations : 5
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))56.151.155
(2.)Leq(Day)A-weighted decibels(dB(A))68.659.265
    14.5.     No. of Soil Sample Monitored locations : 4
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pHOthersNA7.966.78
(2.)Electric ConductivityOthersmicromhos/cm415308
(3.)K(Potassium)Othersgm/kg0.080.04
(4.)N(Nitrogen)Othersgm/kg00
(5.)P(Phosphorus)Kilogram per hectare8259
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 3.3 To 79.70
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 3.05 To 77.5
(c)Whether Ground Water Intersection will be there ? NA
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersHUDA656.690Copy of Permission LettermodeOthersNot requiredOthersNAMemo no. 387909 Mar 2016250
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic714950SBRReuse within the Plant & Recycling,Green Belt Renewal Plant,OthersHVAC7140
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 714
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 714
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)MSWMunicipal Solid Waste2.75Tons0OthersNot requiredOthersOrganic to OWC & inorganic to recycler
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube900.00.12090.12100
(2.)PM2.5Microgram per Meter Cube440.00.0344.0360
(3.)SO2Microgram per Meter Cube8.40.00.0368.43680
(4.)NOxMicrogram per Meter Cube20.50.09.429.980
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)DG set 1x 1500 kVAUSLD 300 lt/hr143.200.3SO20.007
(2.)DG set 5 x 1000 kVAUSLD 200 lt/hr143.200.2PM100.005
(3.)DG set 5 x 1000 kVAUSLD 200 lt/hr143.200.2SO20.005
(4.)DG set 2 x 1000 kVAULSD 200 lt/hr99.60.2PM100.005
(5.)DG set 2 x 1000 kVAULSD 200 lt/hr99.60.2SO20.005
(6.)DG set 2 x 1000 kVAULSD 200 lt/hr99.60.2NOx0.89
(7.)DG set 2 x 2000 kVAULSD 400 lt/hr99.60.5NOx2.4
(8.)DG set 2 x 2000 kVAULSD 400 lt/hr99.60.5PM100.009
(9.)DG set 2 x 2000 kVAULSD 400 lt/hr99.60.5SO20.009
(10.)DG set 5 x 1000 kVAUSLD 200 lt/hr143.200.2NOx0.89
(11.)DG set 1 x 1500 kVAUSLD 300 lt/hr143.200.3PM100.007
(12.)DG set 1 x 1500 kVAUSLD 300 lt/hr143.200.3NOx0.937
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 14753
(b)Source DHBVNL
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 7 x1000 kVA, 1 x 1500 kVA, 2 x 2000 kVA
(e)Stack Height (in m) 143.20
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 7.79
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 7.79
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 0.16
(b)Waste/Barren Land (ha.) 1903.22
(c)Grazing/ Community Land (ha.) 4130.98
(d)Surface Water Bodies (ha.) 94.087
(e)Settlements (ha.) 8157.67
(f)Industrial (ha.) 987.91
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Scrub land 17274.64
    Total (ha.) 32548.667
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Township7.79
Total (ha.) 7.79
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)WLSAsola Wildlife Sanctuary10.21ENE dircetion
(2.)Critically Polluted AreaNot applicable0no remark
(3.)NPANot applicable0no remark
(4.)ESAsNot applicable0no remark
(5.)CorridorsNot applicable0no remark
(6.)ESZsNot applicable0no remark
(7.)Wildlife CorridorsNot applicable0no remark
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Defence InstallationsNot applicable0No remark
(2.)ForestRajokri Protected Forest8.50NNE direction
(3.)OthersWater bodyGhata Lake1.77SSE
(4.)Archaeological SitesNot applicable0No remark
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired Not applicable
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Ghata Lake
(ii)Direction of Water Bodies in Buffer Area South East
(iii)Distance of Water Bodies in Buffer Area 1.77
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 509
(c)Temporary Employment- During Construction 781
(d)Temporary Employment- During Operation 3227
(e)No. of working days 365
(f)Total Manpower 4517
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt27415.576175.8127590
(2.)Percentage of Total Project Area35.2030.22635
(3.)No. of Plants1640451685
(4.)Funds Allocated19019
    33.       Project Benefits
S. No. Type of Project BenefitsDetails of Project Benefits
NIL
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For INFRA-2
S. No.Item Details
1.
Details of Building Construction:
(a)Maximum Height of the Building (Meters) 143.20
(b)Total No. of Flats to be Build 928
(c)No. of Buildings 11
(d)Total plot area (sqm) 77877.581
(e)Total built up area (sqm) 403267.045
2.
Foreshore Facilities and/or Marine Disposal:
(a)Whether Project Involves Foreshore Activities and/or marine Disposal? No
3.
Rain Water Harvesting:
(a)No. of Storage 16
(b)Capacity 560
(c)No. of Recharge Pits 16
(d)Capacity 560
4.
Parking:
(a)Details of 4 Wheeler/ 2 Wheeler Parking 3799 Four wheelar
5.
Energy Saving Measures:
(a)Source/Mode LED lights
(b)Percentage 38
(c)Quantity 3500
6.
Other details:
(a)Details of impact on Water Bodies and Drainage patters of catchment area Not applicable
(b)Details of Traffic Density Impact Assessment and Modelling Study Copy of Details of Traffic Density Impact Assessment and Modelling Study
(c)In case Underground Tunnel Project below the Forest Land - Subsidence Impact Study report Copy of Underground Tunnel Project below the Forest Land - Subsidence Impact Study report
     7.       Type of Industries to be established with Industrial Estate as per their category A/B
S. No.Type of IndustryNo. of UnitsCategory A/B
NIL
8.
Length of the alignment N/A
9.
Details Bridges/ROB/Interchanges,Flyovers,Vehicle Underpass and Pedestrian Underpass
Details Not Applicable
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1619 RA0042
(ii)Name of the EIA Consultant Kadam Environmental Consultants
(iii)Address 871/B/3, Near Himalaya Machinery, GIDC Makarpura, Vadodara - 390 010, Gujarat India
(iv)Mobile No. 8800688825
(v)Landline No. 0124424243
(vi)Email Id kamal@kadamenviro.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation INFRA-2
(ix)Validity of Accreditation 26 May 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAPlease submit the following; 1. Copy of ToR letter dated 15.06.2018 issued by SEIAA Haryana. 2. Plan for Corporate Environment Responsibility (CER) as specified under Ministry’s Office Memorandum vide F.No. 22-65/2017-IA.III dated 1st May 2018. 3. Action taken report submitted to Regional office Chandigarh for the Non-Compliance Environmental Clearance Condition reported in Certified Compliance Report. 11 Oct 2018
2.NAThe correction have been made as per the instruction received 17 Oct 2018
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterFollowing details are submitted: 1. Mitigative measures for control of air pollution 2. Revised water balance 3. Storm water drainage management plan 4. Mitigation measures for Traffic Management and Control 5. Detailed report on compliance to ECBC norms 05 Jan 2019
2.NAKindly see the Final Minutes of 36th EAC Infra-II Meeting held on 26-28 November, 2018 04 Dec 2018
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantRavinder Singh
DesignationAuthorized Signatory
Name of Company (Applicant Name should not be given here)VIPUL LIMITED
AddressVipul Limited, Vipul Tech Square, Golf Course Road, Sector 43, Gurgaon